SAP ABAP Table COCF_ORDER_HDR (PP Order header)
Hierarchy
☛
EA-APPL (Software Component) SAP Enterprise Extension PLM, SCM, Financials
⤷
PP-SFC-IS (Application Component) Information System
⤷
COCF_MANDASH (Package) Manufacturind dashboards for mid-market

⤷

⤷

Basic Data
Table Category | INTTAB | Structure |
Structure | COCF_ORDER_HDR |
![]() |
Short Description | PP Order header |
Delivery and Maintenance
Pool/cluster | ||
Delivery Class | ||
Data Browser/Table View Maintenance | Display/Maintenance Allowed with Restrictions |
Components
![]() |
Field | Key | Data Element | Domain | Data Type |
Length | Decimal Places |
Short Description | Check table |
---|---|---|---|---|---|---|---|---|---|
1 | ![]() |
COCF_MD_APPLID | COCF_MD_APPLID | CHAR | 14 | 0 | Application ID for Manufacturing Dashboard | ||
2 | ![]() |
RALDB_VARI | RALDB_VARI | CHAR | 14 | 0 | Variant Name | ||
3 | ![]() |
RALDB_VARI | RALDB_VARI | CHAR | 14 | 0 | Variant Name | ||
4 | ![]() |
AUFNR | AUFNR | CHAR | 12 | 0 | Order Number | * | |
5 | ![]() |
CO_AUFPL | AUFPL | NUMC | 10 | 0 | Routing number of operations in the order | ||
6 | ![]() |
AUFART | AUFART | CHAR | 4 | 0 | Order Type | * | |
7 | ![]() |
AUFTYP | AUFTYP | NUMC | 2 | 0 | Order category | ||
8 | ![]() |
AUFERFDAT | DATUM | DATS | 8 | 0 | Created on | ||
9 | ![]() |
AUFAEDAT | DATUM | DATS | 8 | 0 | Change date for Order Master | ||
10 | ![]() |
J_OBJNR | J_OBJNR | CHAR | 22 | 0 | Object number | * | |
11 | ![]() |
BUKRS | BUKRS | CHAR | 4 | 0 | Company Code | * | |
12 | ![]() |
WERKS_D | WERKS | CHAR | 4 | 0 | Plant | * | |
13 | ![]() |
VAGRP | VAGRP | CHAR | 3 | 0 | Responsible planner group/department | * | |
14 | ![]() |
CO_DISPO | DISPO | CHAR | 3 | 0 | MRP controller for the order | * | |
15 | ![]() |
FEVOR | FEVOR | CHAR | 3 | 0 | Production Supervisor | * | |
16 | ![]() |
CO_GLTRP | DATUM | DATS | 8 | 0 | Basic finish date | ||
17 | ![]() |
CO_GSTRP | DATUM | DATS | 8 | 0 | Basic start date | ||
18 | ![]() |
CO_FTRMS | DATUM | DATS | 8 | 0 | Scheduled release date | ||
19 | ![]() |
CO_GLTRS | DATUM | DATS | 8 | 0 | Scheduled finish | ||
20 | ![]() |
CO_GSTRS | DATUM | DATS | 8 | 0 | Scheduled start | ||
21 | ![]() |
CO_GSTRI | DATUM | DATS | 8 | 0 | Actual start date | ||
22 | ![]() |
CO_GETRI | DATUM | DATS | 8 | 0 | Confirmed Order Finish Date | ||
23 | ![]() |
CO_GLTRI | DATUM | DATS | 8 | 0 | Actual finish date | ||
24 | ![]() |
CO_FTRMI | DATUM | DATS | 8 | 0 | Actual release date | ||
25 | ![]() |
CO_FTRMP | DATUM | DATS | 8 | 0 | Planned release date | ||
26 | ![]() |
MC_GASMG | MENGV15 | QUAN | 15 | 3 | Total Scrap Quantity in the Order | ||
27 | ![]() |
MC_GAMNG | MENGV15 | QUAN | 15 | 3 | Total order quantity | ||
28 | ![]() |
MEINS | MEINS | UNIT | 3 | 0 | Base Unit of Measure | * | |
29 | ![]() |
VERID | VERID | CHAR | 4 | 0 | Production Version | * | |
30 | ![]() |
MDV01 | MDVXX | CHAR | 8 | 0 | Production line | * | |
31 | ![]() |
MDV02 | MDVXX | CHAR | 8 | 0 | Planning identification 2 | * | |
32 | ![]() |
CO_AUFME | MEINS | UNIT | 3 | 0 | Unit of measure for in-house production | * | |
33 | ![]() |
KUNUM | KUNNR | CHAR | 10 | 0 | Customer Number | * | |
34 | ![]() |
MC_VDATUM | DATUM | DATS | 8 | 0 | Date of update for statistics updating | ||
35 | ![]() |
TERMKZ | TERART | CHAR | 1 | 0 | Scheduling type | * | |
36 | ![]() |
MC_FA_FREI | X | CHAR | 1 | 0 | Order has status RELEASED | ||
37 | ![]() |
MC_FA_GLFT | X | CHAR | 1 | 0 | Order has status DELIVERED | ||
38 | ![]() |
MC_FA_RUECK | X | CHAR | 1 | 0 | Order has status CONFIRMED | ||
39 | ![]() |
MC_FA_TGLI | X | CHAR | 1 | 0 | Order has Status PDLV | ||
40 | ![]() |
MC_FA_TRUEC | X | CHAR | 1 | 0 | Order has status PARTIALLY CONFIRMED | ||
41 | ![]() |
CO_GLUZS | UHRZT | TIMS | 6 | 0 | Scheduled finish time | ||
42 | ![]() |
CO_GSUZS | ATIME | TIMS | 6 | 0 | Scheduled Start (Time) | ||
43 | ![]() |
CO_GSUZI | UHRZT | TIMS | 6 | 0 | Actual start time | ||
44 | ![]() |
CO_GEUZI | UHRZT | TIMS | 6 | 0 | Confirmed order finish (time) | ||
45 | ![]() |
PLNME | MEINS | UNIT | 3 | 0 | Task list unit of measure | * | |
46 | ![]() |
CO_LAUFNR | AUFNR | CHAR | 12 | 0 | Leading order in current processing | * | |
47 | ![]() |
MAUFNR | AUFNR | CHAR | 12 | 0 | Number of superior order | * | |
48 | ![]() |
0 | 0 | PP Order Item | |||||
49 | ![]() |
AUFNR | AUFNR | CHAR | 12 | 0 | Order Number | * | |
50 | ![]() |
CO_POSNR | CO_POSNR | NUMC | 4 | 0 | Order item number | ||
51 | ![]() |
MATNR | MATNR | CHAR | 18 | 0 | Material Number | * | |
52 | ![]() |
CO_PWERK | WERKS | CHAR | 4 | 0 | Planning plant for the order | * | |
53 | ![]() |
CO_ETRMP | DATUM | DATS | 8 | 0 | Opening date of the planned order | ||
54 | ![]() |
CO_STRMP | DATUM | DATS | 8 | 0 | Start date of the planned order | ||
55 | ![]() |
CO_LTRMP | DATUM | DATS | 8 | 0 | Delivery date from planned order | ||
56 | ![]() |
CO_LTRMI | DATUM | DATS | 8 | 0 | Actual delivery/finish date | ||
57 | ![]() |
MC_AVMNG | MENGV15_3 | QUAN | 15 | 3 | Fixed quantity of scrap from production | ||
58 | ![]() |
MC_GSMNG | MENGV15_3 | QUAN | 15 | 3 | Total planned order quantity | ||
59 | ![]() |
LAGME | MEINS | UNIT | 3 | 0 | Base Unit of Measure | * | |
60 | ![]() |
MC_MCPAMNG | MENGV15 | QUAN | 15 | 3 | Fixed production scrap qty in unit of in-house production | ||
61 | ![]() |
MC_MCPGMNG | MENGV15 | QUAN | 15 | 3 | Total planned order quantity in unit of in-house production | ||
62 | ![]() |
MC_PSAMG | MENGV15_3 | QUAN | 15 | 3 | Scrap quantity in item | ||
63 | ![]() |
MC_PSMNG | MENGV15_3 | QUAN | 15 | 3 | Order item quantity | ||
64 | ![]() |
MC_WEMNG | MENGV15_3 | QUAN | 15 | 3 | Quantity of goods received | ||
65 | ![]() |
MC_IAMNG | MENGV15_3 | QUAN | 15 | 3 | Actual scrap quantity from an order item | ||
66 | ![]() |
CO_AUFME | MEINS | UNIT | 3 | 0 | Unit of measure for in-house production | * | |
67 | ![]() |
UMREZ | UMBSZ | DEC | 5 | 0 | Numerator for Conversion to Base Units of Measure | ||
68 | ![]() |
UMREN | UMBSN | DEC | 5 | 0 | Denominator for conversion to base units of measure | ||
69 | ![]() |
DFZEH | EINHEIT | UNIT | 3 | 0 | Unit of measure for execution time | ||
70 | ![]() |
S_DFZ | DAUER_6_1V | QUAN | 7 | 1 | Target execution time | ||
71 | ![]() |
I_DFZ | DAUER_6_1V | QUAN | 7 | 1 | Actual execution time | ||
72 | ![]() |
CY_KEINH | MEINS | UNIT | 3 | 0 | Unit of of measure for displaying capacity requirements | * | |
73 | ![]() |
MC_KSUMS | DAUER_6_1V | QUAN | 7 | 1 | Total target capacity requirements | ||
74 | ![]() |
PLNUM | PLNUM | CHAR | 10 | 0 | Planned order number | * | |
75 | ![]() |
CO_KDAUF | VBELN | CHAR | 10 | 0 | Sales order number | * | |
76 | ![]() |
CO_KDPOS | POSNR | NUMC | 6 | 0 | Sales order item | * | |
77 | ![]() |
KDEIN | NUM04 | NUMC | 4 | 0 | Delivery schedule for sales order | ||
78 | ![]() |
LGORT_D | LGORT | CHAR | 4 | 0 | Storage location | * | |
79 | ![]() |
SA_AUFNR | SA_AUFNR | CHAR | 12 | 0 | Run schedule header number | * | |
80 | ![]() |
VERID | VERID | CHAR | 4 | 0 | Production Version | * | |
81 | ![]() |
SERNR | SERNR | CHAR | 8 | 0 | BOM explosion number | * | |
82 | ![]() |
CHARG_D | CHARG | CHAR | 10 | 0 | Batch Number | * | |
83 | ![]() |
GSBER | GSBER | CHAR | 4 | 0 | Business Area | * | |
84 | ![]() |
SAFNR | SAFNR | CHAR | 10 | 0 | SOP order number | ||
85 | ![]() |
MC_PLCHK1P | CHAR1 | CHAR | 1 | 0 | Plausibility check: item w/o actual start | ||
86 | ![]() |
MC_PLCHK2P | CHAR1 | CHAR | 1 | 0 | Plausibility Check: Actual Finish Date before Start Date | ||
87 | ![]() |
DFZEXEH | EINHEIT | UNIT | 3 | 0 | Unit for execution time (exact) | ||
88 | ![]() |
S_DFZ_EX | DAUER_10_2V | QUAN | 12 | 2 | Target execution time (exact) | ||
89 | ![]() |
I_DFZ_EX | DAUER_10_2V | QUAN | 12 | 2 | Actual execution time (exact) | ||
90 | ![]() |
S_DLZ_EX | DAUER_10_2V | QUAN | 12 | 2 | Target lead time (exact) | ||
91 | ![]() |
I_DLZ_EX | DAUER_10_2V | QUAN | 12 | 2 | Actual lead time (exact) | ||
92 | ![]() |
MC_LTRMI | DATUM | DATS | 8 | 0 | Posting date delivery/finish date, actual | ||
93 | ![]() |
SA_GRUND | CO_AGRND | CHAR | 4 | 0 | Reason for scrap | * | |
94 | ![]() |
REM_PSPNR | PS_POSNR | NUMC | 8 | 0 | Production lot (WBS element) | * | |
95 | ![]() |
P_DLZ | DAUER_6_1V | QUAN | 7 | 1 | Planned lead time | ||
96 | ![]() |
S_DLZ | DAUER_6_1V | QUAN | 7 | 1 | Target lead time | ||
97 | ![]() |
I_DLZ | DAUER_6_1V | QUAN | 7 | 1 | Actual lead time | ||
98 | ![]() |
PS_FREI | DAUER_6_1V | QUAN | 7 | 1 | Planned/target deviation in scheduled release date | ||
99 | ![]() |
PI_FREI | DAUER_6_1V | QUAN | 7 | 1 | Planned/actual deviation in scheduled release date | ||
100 | ![]() |
DSI_FREI | DAUER_6_1V | QUAN | 7 | 1 | Target/actual deviation in scheduled release date | ||
101 | ![]() |
PS_STAR | DAUER_6_1V | QUAN | 7 | 1 | Planned/target deviation in start date | ||
102 | ![]() |
PI_STAR | DAUER_6_1V | QUAN | 7 | 1 | Planned/actual deviation in scheduled start date | ||
103 | ![]() |
DSI_STAR | DAUER_6_1V | QUAN | 7 | 1 | Target/actual schedule deviation in start date | ||
104 | ![]() |
PS_LIEF | DAUER_6_1V | QUAN | 7 | 1 | Planned/target deviation in scheduled delivery date | ||
105 | ![]() |
PI_LIEF | DAUER_6_1V | QUAN | 7 | 1 | Planned/actual deviation in scheduled delivery date | ||
106 | ![]() |
DSI_LIEF | DAUER_6_1V | QUAN | 7 | 1 | Target/actual deviation in scheduled delivery date | ||
107 | ![]() |
0 | 0 | PP Order Operation | |||||
108 | ![]() |
CO_AUFPL | AUFPL | NUMC | 10 | 0 | Routing number of operations in the order | ||
109 | ![]() |
CIM_COUNT | CIM_COUNT | NUMC | 8 | 0 | Internal counter | ||
110 | ![]() |
CIM_COUNT | CIM_COUNT | NUMC | 8 | 0 | Internal counter | ||
111 | ![]() |
PLNFOLGE | PLNFOLGE | CHAR | 6 | 0 | Sequence | ||
112 | ![]() |
VORNR | VORNR | CHAR | 4 | 0 | Operation/Activity Number | ||
113 | ![]() |
OBJEKTID | NUM08 | NUMC | 8 | 0 | Object ID | ||
114 | ![]() |
KAPART | KAPART | CHAR | 3 | 0 | Capacity category | * | |
115 | ![]() |
KAPID | KAPID | NUMC | 8 | 0 | Capacity ID | * | |
116 | ![]() |
ARBPL | ARBPL | CHAR | 8 | 0 | Work center | ||
117 | ![]() |
WERKS_D | WERKS | CHAR | 4 | 0 | Plant | * | |
118 | ![]() |
STEUS | STEUS | CHAR | 4 | 0 | Control key | * | |
119 | ![]() |
J_OBJNR | J_OBJNR | CHAR | 22 | 0 | Object number | * | |
120 | ![]() |
VORME | MEINS | UNIT | 3 | 0 | Unit of measure for activity | * | |
121 | ![]() |
UMREN | UMBSN | DEC | 5 | 0 | Denominator for conversion to base units of measure | ||
122 | ![]() |
UMREZ | UMBSZ | DEC | 5 | 0 | Numerator for Conversion to Base Units of Measure | ||
123 | ![]() |
BMSCH | BMSCH | QUAN | 13 | 3 | Base Quantity | ||
124 | ![]() |
VERTEILUNG | VERTEILUNG | CHAR | 2 | 0 | Distribution function for capacity requirements | * | |
125 | ![]() |
WFCID | WFCID | CHAR | 2 | 0 | Factory Calendar | * | |
126 | ![]() |
MC_MGVRG | MENGV15 | QUAN | 15 | 3 | Operation quantity | ||
127 | ![]() |
MC_ASVRG | MENGV15 | QUAN | 15 | 3 | Operation scrap | ||
128 | ![]() |
MC_LMNGA | MENGV15 | QUAN | 15 | 3 | Total quantity confirmed | ||
129 | ![]() |
MC_XMNGA | MENGV15 | QUAN | 15 | 3 | Total scrap quantity confirmed | ||
130 | ![]() |
MC_GMNGA | MENGV15 | QUAN | 15 | 3 | Total Delivered Lot Size | ||
131 | ![]() |
SSADD | DATUM | DATS | 8 | 0 | Latest target input date | ||
132 | ![]() |
IADD | DATUM | DATS | 8 | 0 | Actual input date | ||
133 | ![]() |
FSAVD | DATUM | DATS | 8 | 0 | Earliest scheduled start: Execution (date) | ||
134 | ![]() |
SSAVD | DATUM | DATS | 8 | 0 | Latest scheduled start: Execution (date) | ||
135 | ![]() |
SSAVZ | ATIME | TIMS | 6 | 0 | Latest scheduled start: Execution (time) | ||
136 | ![]() |
ISDD | DATUM | DATS | 8 | 0 | Actual start: Execution (date) | ||
137 | ![]() |
ISDZ | ATIME | TIMS | 6 | 0 | Actual start: Execution/setup (time) | ||
138 | ![]() |
ISAVD | DATUM | DATS | 8 | 0 | Actual operation start (date) | ||
139 | ![]() |
FSEDD | DATUM | DATS | 8 | 0 | Earliest scheduled finish: Execution (date) | ||
140 | ![]() |
SSEDD | DATUM | DATS | 8 | 0 | Latest scheduled finish: Execution (date) | ||
141 | ![]() |
SSEDZ | ATIME | TIMS | 6 | 0 | Latest scheduled finish: Execution (time) | ||
142 | ![]() |
IEDD | DATUM | DATS | 8 | 0 | Actual finish: Execution (date) | ||
143 | ![]() |
IEDZ | ATIME | TIMS | 6 | 0 | Actual finish: Execution (time) | ||
144 | ![]() |
IEAVD | DATUM | DATS | 8 | 0 | Actual finish of operation (date) | ||
145 | ![]() |
N_IEAVD | DATUM | DATS | 8 | 0 | Actual end of successor operation | ||
146 | ![]() |
MC_WARTZ | DAUER_6_1V | QUAN | 7 | 1 | Queue time used for scheduling | ||
147 | ![]() |
WTRZE | EINHEIT | UNIT | 3 | 0 | Unit of measure for queue time | ||
148 | ![]() |
MC_RUEST | DAUER_6_1V | QUAN | 7 | 1 | Scheduled setup time | ||
149 | ![]() |
RSTZE | EINHEIT | UNIT | 3 | 0 | Unit of measure for setup time | ||
150 | ![]() |
MC_BEARZ | DAUER_6_1V | QUAN | 7 | 1 | Scheduled processing time | ||
151 | ![]() |
BEAZE | EINHEIT | UNIT | 3 | 0 | Unit of measure for processing time | ||
152 | ![]() |
MC_ABRUE | DAUER_6_1V | QUAN | 7 | 1 | Scheduled teardown time | ||
153 | ![]() |
ARUZE | EINHEIT | UNIT | 3 | 0 | Unit of measure for teardown | ||
154 | ![]() |
MC_LIEGZ | DAUER_6_1V | QUAN | 7 | 1 | Wait time used for scheduling | ||
155 | ![]() |
MC_LIEGZ | DAUER_6_1V | QUAN | 7 | 1 | Wait time used for scheduling | ||
156 | ![]() |
LIGZE | EINHEIT | UNIT | 3 | 0 | Unit of measure for wait time | ||
157 | ![]() |
MC_TRANZ | DAUER_6_1V | QUAN | 7 | 1 | Move time used for scheduling | ||
158 | ![]() |
MC_KRUES | DAUER_6_1V | QUAN | 7 | 1 | Scheduled cap. requirements for the op. segment "setup" | ||
159 | ![]() |
MC_KBEAS | DAUER_6_1V | QUAN | 7 | 1 | Scheduled cap. requirements for the op. segment "processing" | ||
160 | ![]() |
MC_KABRS | DAUER_6_1V | QUAN | 7 | 1 | Scheduled cap. requirements for the op. segment teardown | ||
161 | ![]() |
CY_KEINH | MEINS | UNIT | 3 | 0 | Unit of of measure for displaying capacity requirements | * | |
162 | ![]() |
TRAZE | EINHEIT | UNIT | 3 | 0 | Unit of measure for move time | ||
163 | ![]() |
DFZEH | EINHEIT | UNIT | 3 | 0 | Unit of measure for execution time | ||
164 | ![]() |
S_DFZ | DAUER_6_1V | QUAN | 7 | 1 | Target execution time | ||
165 | ![]() |
I_DFZ | DAUER_6_1V | QUAN | 7 | 1 | Actual execution time | ||
166 | ![]() |
KAPKZ | X | CHAR | 1 | 0 | SFIS indicator for cumulative updating of capacity data | ||
167 | ![]() |
MC_PLCHK1V | CHAR1 | CHAR | 1 | 0 | Plausibility check: operation without actual input | ||
168 | ![]() |
MC_PLCHK2V | CHAR1 | CHAR | 1 | 0 | Plausibility Check: Actual Finish of Op. before Actual input | ||
169 | ![]() |
MC_PLCHK3V | CHAR1 | CHAR | 1 | 0 | Plausibility check: invalid milestone confirmation | ||
170 | ![]() |
MC_VDATUM | DATUM | DATS | 8 | 0 | Date of update for statistics updating | ||
171 | ![]() |
MC_BUCHDAT | DATUM | DATS | 8 | 0 | Posting date of last confirmation | ||
172 | ![]() |
UVORN | VORNR | CHAR | 4 | 0 | Suboperation | ||
173 | ![]() |
MCVGWRTEH1 | MEINS | UNIT | 3 | 0 | Unit of measure for standard value 1 | * | |
174 | ![]() |
MCSMNG1 | MENGV15 | QUAN | 15 | 3 | Quantity to be confirmed for activity type 1 | ||
175 | ![]() |
MCZMNG1 | MENGV15 | QUAN | 15 | 3 | Target quantity of activity type 1 | ||
176 | ![]() |
MCZMNG1OZ | MENGV15 | QUAN | 15 | 3 | Target quantity/activity type 1 w/o perfmnce efficiency rate | ||
177 | ![]() |
MCVGWRTEH2 | MEINS | UNIT | 3 | 0 | Unit of measure for standard value 2 | * | |
178 | ![]() |
MCSMNG2 | MENGV15 | QUAN | 15 | 3 | Quantity to be confirmed for activity type 2 | ||
179 | ![]() |
MCZMNG2 | MENGV15 | QUAN | 15 | 3 | Target quantity of activity type 2 | ||
180 | ![]() |
MCZMNG2OZ | MENGV15 | QUAN | 15 | 3 | Target quantity/activity type 2 w/o perfmnce efficiency rate | ||
181 | ![]() |
MCVGWRTEH3 | MEINS | UNIT | 3 | 0 | Unit of measure for standard value 3 | * | |
182 | ![]() |
MCSMNG3 | MENGV15 | QUAN | 15 | 3 | Quantity to be confirmed for activity type 3 | ||
183 | ![]() |
MCZMNG3 | MENGV15 | QUAN | 15 | 3 | Target quantity of activity type 3 | ||
184 | ![]() |
MCZMNG3OZ | MENGV15 | QUAN | 15 | 3 | Target quantity/activity type 3 w/o perfmnce efficiency rate | ||
185 | ![]() |
MCVGWRTEH4 | MEINS | UNIT | 3 | 0 | Unit of measure for standard value 4 | * | |
186 | ![]() |
MCSMNG4 | MENGV15 | QUAN | 15 | 3 | Quantity to be confirmed for activity type 4 | ||
187 | ![]() |
MCZMNG4 | MENGV15 | QUAN | 15 | 3 | Target quantity of activity type 4 | ||
188 | ![]() |
MCZMNG4OZ | MENGV15 | QUAN | 15 | 3 | Target quantity/activity type 4 w/o perfmnce efficiency rate | ||
189 | ![]() |
MCVGWRTEH5 | MEINS | UNIT | 3 | 0 | Unit of measure for standard value 5 | * | |
190 | ![]() |
MCSMNG5 | MENGV15 | QUAN | 15 | 3 | Quantity to be confirmed for activity type 5 | ||
191 | ![]() |
MCZMNG5 | MENGV15 | QUAN | 15 | 3 | Target quantity of activity type 5 | ||
192 | ![]() |
MCZMNG5OZ | MENGV15 | QUAN | 15 | 3 | Target quantity/activity type 5 w/o perfmnce efficiency rate | ||
193 | ![]() |
MCVGWRTEH6 | MEINS | UNIT | 3 | 0 | Unit of measure for standard value 6 | * | |
194 | ![]() |
MCSMNG6 | MENGV15 | QUAN | 15 | 3 | Quantity to be confirmed for activity type 6 | ||
195 | ![]() |
MCZMNG6 | MENGV15 | QUAN | 15 | 3 | Target quantity of activity type 6 | ||
196 | ![]() |
MCZMNG6OZ | MENGV15 | QUAN | 15 | 3 | Target quantity/activity type 6 w/o perfmnce efficiency rate | ||
197 | ![]() |
MCISMEH1 | MEINS | UNIT | 3 | 0 | Unit of measure for 1st activity to be confirmed | * | |
198 | ![]() |
MCRUMNG1 | MENGV15 | QUAN | 15 | 3 | Confirmed activity 1 - activity type | ||
199 | ![]() |
MCISMEH2 | MEINS | UNIT | 3 | 0 | Unit of measure for 2nd activity to be confirmed | * | |
200 | ![]() |
MCRUMNG2 | MENGV15 | QUAN | 15 | 3 | Confirmed activity 2 - activity type | ||
201 | ![]() |
MCISMEH3 | MEINS | UNIT | 3 | 0 | Unit of measure for 3rd activity to be confirmed | * | |
202 | ![]() |
MCRUMNG3 | MENGV15 | QUAN | 15 | 3 | Confirmed activity 3 - activity type | ||
203 | ![]() |
MCISMEH4 | MEINS | UNIT | 3 | 0 | Unit of measure for 4th activity to be confirmed | * | |
204 | ![]() |
MCRUMNG4 | MENGV15 | QUAN | 15 | 3 | Confirmed activity 4 - activity type | ||
205 | ![]() |
MCISMEH5 | MEINS | UNIT | 3 | 0 | Unit of measure for 5th activity to be confirmed | * | |
206 | ![]() |
MCRUMNG5 | MENGV15 | QUAN | 15 | 3 | Confirmed activity 5 - activity type | ||
207 | ![]() |
MCISMEH6 | MEINS | UNIT | 3 | 0 | Unit of measure for 6th activity to be confirmed | * | |
208 | ![]() |
MCRUMNG6 | MENGV15 | QUAN | 15 | 3 | Confirmed activity - activity type 6 | ||
209 | ![]() |
MC_LSTEFF1 | MENGV15 | QUAN | 15 | 3 | Efficiency of activity type 1 | ||
210 | ![]() |
MC_LSTEFF2 | MENGV15 | QUAN | 15 | 3 | Efficiency of activity type 2 | ||
211 | ![]() |
MC_LSTEFF3 | MENGV15 | QUAN | 15 | 3 | Efficiency of activity type 3 | ||
212 | ![]() |
MC_LSTEFF4 | MENGV15 | QUAN | 15 | 3 | Efficiency of activity type 4 | ||
213 | ![]() |
MC_LSTEFF5 | MENGV15 | QUAN | 15 | 3 | Efficiency of activity type 4 | ||
214 | ![]() |
MC_LSTEFF6 | MENGV15 | QUAN | 15 | 3 | Efficiency of activity type 6 | ||
215 | ![]() |
MC_ZGR01 | PROZENT101 | DEC | 11 | 1 | Target performance efficiency rate for activity type 1 | ||
216 | ![]() |
MC_ZGR02 | PROZENT101 | DEC | 11 | 1 | Target performance efficiency rate for activity type 2 | ||
217 | ![]() |
MC_ZGR03 | PROZENT101 | DEC | 11 | 1 | Target performance efficiency rate for activity type 3 | ||
218 | ![]() |
MC_ZGR04 | PROZENT101 | DEC | 11 | 1 | Target performance efficiency rate for activity type 4 | ||
219 | ![]() |
MC_ZGR05 | PROZENT101 | DEC | 11 | 1 | Target performance efficiency rate for activity type 5 | ||
220 | ![]() |
MC_ZGR06 | PROZENT101 | DEC | 11 | 1 | Target performance efficiency rate for activity type 6 | ||
221 | ![]() |
MC_VG_FREI | X | CHAR | 1 | 0 | Operation has status RELEASED | ||
222 | ![]() |
MC_VG_RUECK | X | CHAR | 1 | 0 | Operation has status CONFIRMED | ||
223 | ![]() |
MC_VG_TRUEC | X | CHAR | 1 | 0 | Operation has status PARTIALLY CONFIRMED | ||
224 | ![]() |
MC_VG_RMAN | X | CHAR | 1 | 0 | Operation has status RMAN | ||
225 | ![]() |
AP_VERAN | AP_VERAN | CHAR | 3 | 0 | Person responsible for the work center | * | |
226 | ![]() |
KAPPLANER | KAPPLANER | CHAR | 3 | 0 | Capacity planner group | * | |
227 | ![]() |
DFZEXEH | EINHEIT | UNIT | 3 | 0 | Unit for execution time (exact) | ||
228 | ![]() |
S_DFZ_EX | DAUER_10_2V | QUAN | 12 | 2 | Target execution time (exact) | ||
229 | ![]() |
I_DFZ_EX | DAUER_10_2V | QUAN | 12 | 2 | Actual execution time (exact) | ||
230 | ![]() |
SSADZ | ATIME | TIMS | 6 | 0 | Latest target input (time of day) | ||
231 | ![]() |
IADZ | ATIME | TIMS | 6 | 0 | Actual input (time of day) | ||
232 | ![]() |
REFOP24 | REFOP24 | CHAR | 24 | 0 | Reference operation set | ||
233 | ![]() |
PLNTY | PLNTY | CHAR | 1 | 0 | Task List Type | * | |
234 | ![]() |
VPLTY | PLNTY | CHAR | 1 | 0 | Task list type for reference | * | |
235 | ![]() |
PLNNR | PLNNR | CHAR | 8 | 0 | Key for Task List Group | ||
236 | ![]() |
PLNKN | KNTNR | NUMC | 8 | 0 | Number of the task list node | ||
237 | ![]() |
VPLNNR | PLNNR | CHAR | 8 | 0 | Group of the referenced task list | ||
238 | ![]() |
STDKN | KNTNR | NUMC | 8 | 0 | Node of operation within reference operation set | ||
239 | ![]() |
MCRUESTI | DAUER_6_1V | QUAN | 7 | 1 | Actual setup time | ||
240 | ![]() |
MCBEARZI | DAUER_6_1V | QUAN | 7 | 1 | Actual processing time | ||
241 | ![]() |
MCABRUEI | DAUER_6_1V | QUAN | 7 | 1 | Actual teardown | ||
242 | ![]() |
S_DLZ_EX | DAUER_10_2V | QUAN | 12 | 2 | Target lead time (exact) | ||
243 | ![]() |
I_DLZ_EX | DAUER_10_2V | QUAN | 12 | 2 | Actual lead time (exact) | ||
244 | ![]() |
LOHNART | LOART | CHAR | 4 | 0 | Wage type | ||
245 | ![]() |
QUALF | QUALF | CHAR | 2 | 0 | Suitability | * | |
246 | ![]() |
LOHNGRP | LOHNGRP | CHAR | 3 | 0 | Wage group | * | |
247 | ![]() |
CO_AGRND | CO_AGRND | CHAR | 4 | 0 | Reason for Variance | * | |
248 | ![]() |
CO_PERNR | PERNR | NUMC | 8 | 0 | Personnel number | ||
249 | ![]() |
CR_OBJID_I | CR_OBJID | NUMC | 8 | 0 | Actual operating resources object identification | * | |
250 | ![]() |
WERKS_D | WERKS | CHAR | 4 | 0 | Plant | * | |
251 | ![]() |
ARBPL | ARBPL | CHAR | 8 | 0 | Work center | ||
252 | ![]() |
AP_VERAN | AP_VERAN | CHAR | 3 | 0 | Person responsible for the work center | * | |
253 | ![]() |
S_DLZ | DAUER_6_1V | QUAN | 7 | 1 | Target lead time | ||
254 | ![]() |
I_DLZ | DAUER_6_1V | QUAN | 7 | 1 | Actual lead time | ||
255 | ![]() |
X_TAB | DAUER_6_1V | QUAN | 7 | 1 | Deviation from scheduled input date | ||
256 | ![]() |
A_TAB | DAUER_6_1V | QUAN | 7 | 1 | Deviation in scheduled output date | ||
257 | ![]() |
R_TAB | DAUER_6_1V | QUAN | 7 | 1 | Relative schedule deviation | ||
258 | ![]() |
CO_RUECK | CO_RUECK | NUMC | 10 | 0 | Completion confirmation number for the operation | ||
259 | ![]() |
RMNGA | MENGV13 | QUAN | 13 | 3 | Total confirmed rework quantity | ||
260 | ![]() |
CO_IPRZS | MENGV13 | QUAN | 13 | 3 | Confirmed quantity/work for business process | ||
261 | ![]() |
RU_IPRZE | MEINS | UNIT | 3 | 0 | Unit of measurement for conf. quantity for business process | * | |
262 | ![]() |
MCLSTAR01 | LSTAR | CHAR | 6 | 0 | 1. CO activity | * | |
263 | ![]() |
MCLSTAR02 | LSTAR | CHAR | 6 | 0 | 2. CO activity | * | |
264 | ![]() |
MCLSTAR03 | LSTAR | CHAR | 6 | 0 | 3. CO activity | * | |
265 | ![]() |
MCLSTAR04 | LSTAR | CHAR | 6 | 0 | 4. CO activity | * | |
266 | ![]() |
MCLSTAR05 | LSTAR | CHAR | 6 | 0 | 5. CO activity | * | |
267 | ![]() |
MCLSTAR06 | LSTAR | CHAR | 6 | 0 | 6. CO activity | * |
History
Last changed by/on | SAP | 20130529 |
SAP Release Created in | 606 |