SAP ABAP Data Element CO_GLTRP (Basic finish date)
Hierarchy
SAP_ABA (Software Component) Cross-Application Component
   CA-GTF-PS (Application Component) Cross-Application Objects in Project System
     BC (Package) Cross-Application Objects PP/PS
Basic Data
Data Element CO_GLTRP
Short Description Basic finish date  
Data Type
Category of Dictionary Type D   Domain
Type of Object Referenced     No Information
Domain / Name of Reference Type DATUM    
Data Type DATS   Date field (YYYYMMDD) stored as char(8) 
Length 8    
Decimal Places 0    
Output Length 10    
Value Table      
Further Characteristics
Search Help: Name    
Search Help: Parameters    
Parameter ID   
Default Component name FINISH_DATE   
Change document    
No Input History    
Basic direction is set to LTR    
No BIDI Filtering    
Field Label
  Length  Field Label  
Short 10 Basic fin. 
Medium 15 Basic fin. date 
Long 20 Basic finish date 
Heading 55 Basic finish date 
Documentation

Definition

Order finish date

Supplementary Documentation - CO_GLTRP 0001

Definition

Date on which the required quantity of the material is available (that is, the requirements date of the material).

  • If, on order creation, a planned order exists for the production order/ process order, the basic dates are copied from the planned order.
  • If no planned order exists on order creation, you must specify at least one basic date.

    The scheduling type determines the basic dates that you must specify.

Dependencies

The order finish date is accurate to the day. However, for scheduling, production requires a completion date that also specifies the time. To ensure that the material to be manufactured is available on the order finish date, the completion date must be before 00:00 hours on the order finish date.

If, however, an in-house production time of 0 days is maintained in the material master, an exception is made to this rule. In this case, it is assumed that the material can be manufactured in a single workday. The completion date is then before 24:00 hours on the order finish date.

Example

The last operation of an order was completed on Thursday at 5 pm (17:00 hours). No float after production was maintained for the order.

  • If an in-house production time greater than 0 days is maintained in the material master record, the order finish date is Friday.
  • If an in-house production time of 0 days is maintained in the material master record, the order finish date is Thursday.

Supplementary Documentation - CO_GLTRP 0003

Use

You enter the basic finish date of the refurbishment order in this field.

Procedure

Examples

Dependencies

MRP expects the refurbished repairable spares to be given back on the date entered in this field.

Supplementary Documentation - CO_GLTRP 0050

Procedure

Enter the basic date of the orders for which manufacturing instructions are to be selected.

The way in which the value entered is interpreted (for example, as a single value or as an interval limit) depends on

  • whether you maintain the field only in the left column or also in the right
  • which selection option you choose for the value

Supplementary Documentation - CO_GLTRP 0051

Procedure

Enter the basic date of the orders here for which manufacturing instructions are to be selected.

Use the selection options to determine how the value entered is to be interpreted (for example, as a single value or as an interval limit).

Supplementary Documentation - CO_GLTRP 2120

Use

Start date for scheduling a network backwards.

A network is always scheduled forwards and backwards.

  • Forward scheduling calculates the earliest start and finish dates of the activities and the scheduled finish date of the network.
  • Backward scheduling calculates the latest start and finish dates of the activities and the scheduled start date of the network.

Dependencies

You can determine whether a network is first to be scheduled forwards or backwards via the scheduling type.

Supplementary Documentation - CO_GLTRP 3010

Use

In overall scheduling of the network the system calculates

  • from all the networks that are linked to one another by relationships or
  • from all the orders that are linked to one another

the largest common basic finish date as default value for scheduling.

You can overwrite the default value.