Hierarchy
⤷ CA-GTF-PS (Application Component) Cross-Application Objects in Project System
⤷ BC (Package) Cross-Application Objects PP/PS
Basic Data
Data Element | CO_GSTRS |
Short Description | Scheduled start |
Data Type
Category of Dictionary Type | D | Domain |
Type of Object Referenced | No Information | |
Domain / Name of Reference Type | DATUM | |
Data Type | DATS | Date field (YYYYMMDD) stored as char(8) |
Length | 8 | |
Decimal Places | 0 | |
Output Length | 10 | |
Value Table |
Further Characteristics
Search Help: Name | ||
Search Help: Parameters | ||
Parameter ID | ||
Default Component name | PRODUCTION_START_DATE | |
Change document | ||
No Input History | ||
Basic direction is set to LTR | ||
No BIDI Filtering |
Field Label
Length | Field Label | |
Short | 10 | SchedStart |
Medium | 15 | Sched. start |
Long | 20 | Scheduled start |
Heading | 55 | Scheduled start |
Documentation
Definition
Supplementary Documentation - CO_GSTRS 0001
Use
Start date for the execution of the production order.
You can either
- let the system determine this date using lead time scheduling, or
- enter the date as a fixed date on the header screen of the production order.
Supplementary Documentation - CO_GSTRS 0002
Definition
The start date of production is the planned start date of an order without a float before production.
Use
The production dates are calculated in lead time scheduling.
Procedure
Examples
Dependencies
Supplementary Documentation - CO_GSTRS 0050
Procedure
Enter here the scheduled start for the orders for which the manufacturing instructions are to be selected.
The way in which the value entered is interpreted (for example, as a single value or as an interval limit) depends on
- whether you maintain the field only in the left column or also in the right
- which selection option you choose for the value
Supplementary Documentation - CO_GSTRS 0051
Procedure
Enter here the scheduled start of the orders for which manufacturing instructions are to be selected.
Use the selection options to determine how the value entered is to be interpreted (for example, as a single value or as an interval limit).
Supplementary Documentation - CO_GSTRS 0500
Start date for the execution of the production order.
Procedure
You can either
- let the system determine this date via lead time scheduling, or
- enter the date as a fixed date on the header screen of the production order.
Supplementary Documentation - CO_GSTRS 2120
Use
The scheduled start date of the network is calculated using backward scheduling.
History
Last changed by/on | SAP | 19990629 |
SAP Release Created in |