SAP ABAP Table RCJ_PS_ORD (All Objects in the Project Planning Board)
Hierarchy
SAP_APPL (Software Component) Logistics and Accounting
   PS-ST-OPR-PPB (Application Component) Project Planning Board
     CN_PPT_GRAFIK (Package) Project Planning Board
Basic Data
Table Category INTTAB    Structure 
Structure RCJ_PS_ORD   Table Relationship Diagram
Short Description All Objects in the Project Planning Board    
Delivery and Maintenance
Pool/cluster      
Delivery Class      
Data Browser/Table View Maintenance     Display/Maintenance Allowed with Restrictions 
Components
     
Field Key Data Element Domain Data
Type
Length Decimal
Places
Short Description Check
table
1 .INCLUDE       0   0   Object Structure for Project Reporting  
2 OBJEKTID OBJEKT_ID CHAR30 CHAR 30   0   ID/Object key  
3 KURZTEXT KURZTEXT TEXT40 CHAR 40   0   Short text/description of the object  
4 OBJEKTTYP OTEXT TEXT25 CHAR 25   0   Object Type Text  
5 ECKST PS_ECKST DATUM DATS 8   0   Basic start date  
6 ECKEN PS_ECKEN DATUM DATS 8   0   Finish date (from basic dates)  
7 PROGST PS_PROGST DATUM DATS 8   0   Forecast start date  
8 PROGEN PS_PROGEN DATUM DATS 8   0   Forecast finish date  
9 TESTFR PS_TESTFR DATUM DATS 8   0   Earliest scheduled start (from basic dates)  
10 TEENFR PS_TEENFR DATUM DATS 8   0   Earliest scheduled finish (from basic dates)  
11 TESTSP PS_TESTSP DATUM DATS 8   0   Latest scheduled start (from basic dates)  
12 TEENSP PS_TEENSP DATUM DATS 8   0   Latest scheduled finish (from basic dates)  
13 TPSTFR PS_TPSTFR DATUM DATS 8   0   Earliest scheduled start (from forecast dates)  
14 TPENFR PS_TPENFR DATUM DATS 8   0   Earliest scheduled finish (from forecast dates)  
15 TPSTSP PS_TPSTSP DATUM DATS 8   0   Latest scheduled start (from forecast dates)  
16 TPENSP PS_TPENSP DATUM DATS 8   0   Latest scheduled finish (from forecast dates)  
17 ISTST PS_ISTST DATUM DATS 8   0   Actual start date  
18 ISTEN PS_ISTEN DATUM DATS 8   0   Actual finish date  
19 DATFS PS_DATFS DATUM DATS 8   0   Earliest start date  
20 DATSE PS_DATSE DATUM DATS 8   0   Latest finish date  
21 EDAUER PS_EDAUER DAUER_4_1 QUAN 5   1   Duration  
22 EDAUEH PS_DAUEH MEINS UNIT 3   0   Actual duration unit T006
23 PDAUER PS_PDAUER DAUER_4_1 QUAN 5   1   Forecast duration  
24 PDAUEH PS_DAUEH MEINS UNIT 3   0   Actual duration unit T006
25 VDAUER PS_VDAUER DAUER_4_1 QUAN 5   1   Tentative duration  
26 VDAUEH PS_DAUEH MEINS UNIT 3   0   Actual duration unit T006
27 IDAUER PS_IDAUER DAUER_4_1 QUAN 5   1   Actual duration  
28 IDAUEH PS_DAUEH MEINS UNIT 3   0   Actual duration unit T006
29 RDAUER PS_RDAUER DAUER_4_1 QUAN 5   1   Remaining duration  
30 RDAUEH PS_DAUEH MEINS UNIT 3   0   Actual duration unit T006
31 ABARBD PS_ABARBD CO_ABARB NUMC 3   0   Processing % of duration  
32 EARBEI PS_EARBEI PS_ARBEIT QUAN 9   1   Work  
33 EARBEH PS_ARBEH MEINS UNIT 3   0   Unit for work T006
34 PARBEI PS_PARBEI PS_ARBEIT QUAN 9   1   Forecast work  
35 PARBEH PS_ARBEH MEINS UNIT 3   0   Unit for work T006
36 VARBEI PS_VARBEI PS_ARBEIT QUAN 9   1   Tentative work  
37 VARBEH PS_ARBEH MEINS UNIT 3   0   Unit for work T006
38 IARBEI PS_IARBEI PS_ARBEIT QUAN 9   1   Actual work  
39 IARBEH PS_ARBEH MEINS UNIT 3   0   Unit for work T006
40 RARBEI PS_RARBEI PS_ARBEIT QUAN 9   1   Remaining work  
41 RARBEH PS_ARBEH MEINS UNIT 3   0   Unit for work T006
42 ABARBA PS_ABARBA CO_ABARB NUMC 3   0   Percent of completion for work  
43 USR00 USRCHAR20 USRCHAR20 CHAR 20   0   User field with 20 characters  
44 USR01 USRCHAR20 USRCHAR20 CHAR 20   0   User field with 20 characters  
45 USR02 USRCHAR10 USRCHAR10 CHAR 10   0   User field with 10 characters  
46 USR03 USRCHAR10 USRCHAR10 CHAR 10   0   User field with 10 characters  
47 USR04 USRQUAN13 USRQUAN13 QUAN 13   3   User field for quantity (length 10.3)  
48 USE04 USRUNIT MEINS UNIT 3   0   User field: Unit for quantity fields T006
49 USR05 USRQUAN13 USRQUAN13 QUAN 13   3   User field for quantity (length 10.3)  
50 USE05 USRUNIT MEINS UNIT 3   0   User field: Unit for quantity fields T006
51 USR06 USRCURR13 USRCURR13 CURR 13   3   User-defined field for values (length 10,3)  
52 USE06 USRCUKY WAERS CUKY 5   0   User field: Unit for value fields TCURC
53 USR07 USRCURR13 USRCURR13 CURR 13   3   User-defined field for values (length 10,3)  
54 USE07 USRCUKY WAERS CUKY 5   0   User field: Unit for value fields TCURC
55 USR08 USRDATE USRDATE DATS 8   0   User field for date  
56 USR09 USRDATE USRDATE DATS 8   0   User field for date  
57 USR10 USRFLAG FLAG CHAR 1   0   User-defined field: Indicator for reports  
58 USR11 USRFLAG FLAG CHAR 1   0   User-defined field: Indicator for reports  
59 VERNR PS_VERNR_C CHAR8 CHAR 8   0   Number of responsible person (project mgr)/MRP controller  
60 VERNA PS_VERNA PS_VERNA CHAR 25   0   Name of responsible person (Project manager)  
61 ARBPL ARBPL ARBPL CHAR 8   0   Work center  
62 PSPRI NW_PRIO NW_PRIO CHAR 1   0   Priority TCN07
63 STATXT STATUSTEXT CHAR40 CHAR 40   0   Edited status text  
64 STUFE PS_STUFE INT1 INT1 3   0   Level in project hierarchy  
65 FRUEHER FRUEHER DAUER_4_1 QUAN 5   1   Actual start is before earliest scheduled start  
66 SPAETER SPAETER DAUER_4_1 QUAN 5   1   Actual Finish/Planned Finish After Latest Scheduled Finish  
67 VERZUG VERZUG DAUER_4_1 QUAN 5   1   Duration After Latest Scheduled Finish  
68 VORBEI VORBEI DAUER_4_1 QUAN 5   1   Duration After Latest Scheduled Start  
69 VEINH VERZ_EINHT MEINS UNIT 3   0   Unit for Duration of the Delay T006
70 WAERS WAERS WAERS CUKY 5   0   Currency Key TCURC
71 OWAERS OWAERS WAERS CUKY 5   0   Object currency for network activity *
72 PUFGS PUFFR_GESM PUFFER DEC 3   0   Total float  
73 PUFFR PUFFR_FREI PUFFER DEC 3   0   Free float  
74 PUFGP PPUFF_GESM PUFFER DEC 3   0   Total float (from forecast)  
75 PUFFP PPUFF_FREI PUFFER DEC 3   0   Free float (from forecast)  
76 GESBR PS_PGSBR GSBER CHAR 4   0   Business area for WBS element *
77 PRCTR PRCTR PRCTR CHAR 10   0   Profit Center *
78 SAKTO SAKTO SAKNR CHAR 10   0   Cost Element *
79 KALID FABKL WFCID CHAR 2   0   Factory calendar key *
80 WERKS WERKS_D WERKS CHAR 4   0   Plant *
81 BUKRS BUKRS BUKRS CHAR 4   0   Company Code *
82 ASTNR PS_ASTNR PS_ASTNR NUMC 8   0   Applicant number *
83 KALSM AUFKALSM KALSM CHAR 6   0   Costing Sheet *
84 ZSCHL AUFZSCHL CHAR6 CHAR 6   0   Overhead key  
85 ABGSL ABGR_SCHL ABGR_SCHL CHAR 6   0   Results Analysis Key *
86 ZSCHM PS_ZSCHM PS_ZSCHM CHAR 7   0   Interest Profile for Project/Order Interest Calculation *
87 PLAKZ PS_PLAKZ XFELD CHAR 1   0   Indicator: Planning element  
88 BELKZ PS_BELKZ XFELD CHAR 1   0   Indicator: Account assignment element  
89 FAKKZ PS_FAKKZ XFELD CHAR 1   0   Indicator: Billing element  
90 .INCLUDE       0   0   Key Figures for Commercial Reporting in Structure Overview  
91 .INCLUDE       0   0   RPSCO_LIS for graphics  
92 PROKSTPLAN PROKSTPLAN WERTV8 CURR 15   2   Current project cost plan  
93 PROKSTPLN2 PROKSTPLN2 WERTV8 CURR 15   2   Project cost plan (version 2)  
94 AUFKSTPLAN AUFKSTPLAN WERTV8 CURR 15   2   Current order cost plan  
95 AUFKSTPLN2 AUFKSTPLN2 WERTV8 CURR 15   2   Order cost plan (version 2)  
96 PROERLPLAN PROERLPLAN WERTV8 CURR 15   2   Current project revenue plan  
97 PROERLPLN2 PROERLPLN2 WERTV8 CURR 15   2   Project revenue plan (version 2)  
98 AUFERLPLAN AUFERLPLAN WERTV8 CURR 15   2   Current order revenue plan  
99 AUFERLPLN2 AUFERLPLN2 WERTV8 CURR 15   2   Order revenue plan (version 2)  
100 KREDFINPLN KREDFINPLN WERTV8 CURR 15   2   Current financial budget, credit side  
101 DEBFINPLN DEBFINPLN WERTV8 CURR 15   2   Current cash budget, debit side  
102 BUDGET BUDGET WERTV8 CURR 15   2   Budget of a Measure (App. Request Variant Was Replaced)  
103 FREIGABE FREIGABE WERTV8 CURR 15   2   Release  
104 AUFTRANF AUFTRANF WERTV8 CURR 15   2   Residual order plan  
105 FESTPROBL FESTPROBL WERTV8 CURR 15   2   Fixed price commitment  
106 KSTOBLGES KSTOBLGES WERTV8 CURR 15   2   Total cost commitment  
107 ISTKOSTEN ISTKOSTEN WERTV8 CURR 15   2   Actual costs  
108 ISTERLOESE ISTERLOESE WERTV8 CURR 15   2   Actual revenues  
109 KZHLNG KZHLNG WERTV8 CURR 15   2   Total credit side payments (down payments and payments)  
110 DZHLNG DZHLNG WERTV8 CURR 15   2   Total debit side payments (down payments and payments)  
111 .INCLU--AP       0   0   Append Structure RCJ_RPSCO_LIS  
112 .INCLUDE       0   0   RPSCO_LIS for Graphic (Object Currency)  
113 PROKSTPLAN_OC PROKSTPLANOC WERTV8 CURR 15   2   Current Project Cost Plan in Object Currency  
114 PROKSTPLN2_OC PROKSTPLN2OC WERTV8 CURR 15   2   Project Cost Plan (Version 2) in Object Currency  
115 AUFKSTPLAN_OC AUFKSTPLANOC WERTV8 CURR 15   2   Current Order Cost Plan in Object Currency  
116 AUFKSTPLN2_OC AUFKSTPLN2OC WERTV8 CURR 15   2   Order Cost Plan (Version 2) in Object Currency  
117 PROERLPLAN_OC PROERLPLANOC WERTV8 CURR 15   2   Current Project Revenue Plan in Object Currency  
118 PROERLPLN2_OC PROERLPLN2OC WERTV8 CURR 15   2   Project Revenue Plan (Version 2) in Object Currency  
119 AUFERLPLAN_OC AUFERLPLANOC WERTV8 CURR 15   2   Current Order Revenue Plan in Object Currency  
120 AUFERLPLN2_OC AUFERLPLN2OC WERTV8 CURR 15   2   Order Revenue Plan (Version 2) in Object Currency  
121 KREDFINPLN_OC KREDFINPLNOC WERTV8 CURR 15   2   Current Credit Side Cash Budget in Object Currency  
122 DEBFINPLN_OC DEBFINPLNOC WERTV8 CURR 15   2   Current Debit Side Cash Budget in Object Currency  
123 BUDGET_OC BUDGETOC WERTV8 CURR 15   2   Appropriation Budget (Appr.Request Variant Replaced) in OC  
124 FREIGABE_OC FREIGABEOC WERTV8 CURR 15   2   Release in Object Currency  
125 AUFTRANF_OC AUFTRANFOC WERTV8 CURR 15   2   Residual Order Plan in Object Currency  
126 FESTPROBL_OC FESTPROBLOC WERTV8 CURR 15   2   Fixed Price Commitment in Object Currency  
127 KSTOBLGES_OC KSTOBLGESOC WERTV8 CURR 15   2   Total Cost Commitment in Object Currency  
128 ISTKOSTEN_OC ISTKOSTENOC WERTV8 CURR 15   2   Act. Costs in Object Currency  
129 ISTERLOESE_OC ISTERLOESEOC WERTV8 CURR 15   2   Actual Revenues in Object Currency  
130 KZHLNG_OC KZHLNGOC WERTV8 CURR 15   2   Total Vendor Payments (Down Payments and Payments) OC  
131 DZHLNG_OC DZHLNGOC WERTV8 CURR 15   2   Total Customer Payments (Down Payments and Payments) OC  
132 .INCLUDE       0   0   Progress Calculation: All  
133 .INCLUDE       0   0   Progress Analysis: Values  
134 EV_PLAN_ORG1 EVPLANORG1 WERTV8 CURR 15   2   Budgeted cost of work scheduled  
135 EV_ACT_ORG1 EVACTORG1 WERTV8 CURR 15   2   Budgeted cost of work performed  
136 EV_ACT_CORR1 EVACTCORR1 WERTV8 CURR 15   2   Budgeted cost of work performed, adjusted  
137 .INCLUDE       0   0   Progress Analysis: Quantities  
138 EV_PLAN_QUAN_ORG1 EVPLANQUANORG1 CQUA8 QUAN 15   3   Budgeted cost of work scheduled, quantity  
139 EV_PLAN_QUAN_ORG1_UNIT EV_PLAN_QUAN_ORG1_UNIT MEINS UNIT 3   0   BCWS, Unit of Measure *
140 EV_ACT_QUAN_ORG1 EVACTQUANORG1 CQUA8 QUAN 15   3   Budgeted cost of work performed, quantity  
141 EV_ACT_QUAN_ORG1_UNIT EV_ACT_QUAN_ORG1_UNIT MEINS UNIT 3   0   BCWP, Unit of Measure *
142 EV_ACT_QUAN_CORR1 EVACTQUANCORR1 CQUA8 QUAN 15   3   Budgeted cost of work performed, adjusted quantity  
143 EV_ACT_QUAN_CORR1_UNIT EV_ACT_QUAN_CORR1_UNIT MEINS UNIT 3   0   BCWP, Adjusted Quantity (Unit) *
144 .INCLUDE       0   0   Progress Analysis: Percentage of completion (POC)  
145 POC_PLAN_ORG_AGG1 POCPLANORGAGG1 EV_PROGRES DEC 6   3   Aggregate planned percentage of completion  
146 POC_PLAN_ORG_NAGG1 POCPLANORGNAGG1 EV_PROGRES DEC 6   3   Non-aggregated planned percentage of completion  
147 POC_ACT_ORG_AGG1 POCACTORGAGG1 EV_PROGRES DEC 6   3   Aggregated actual POC  
148 POC_ACT_ORG_NAGG1 POCACTORGNAGG1 EV_PROGRES DEC 6   3   Non-aggregated actual percentage of completion  
149 POC_ACT_CORR_AGG1 POCACTCORRAGG1 EV_PROGRES DEC 6   3   Adjusted aggregated actual POC  
150 POC_ACT_CORR_NAGG1 POCACTCORRNAGG1 EV_PROGRES DEC 6   3   Adjusted non-aggregated actual percentage of completion  
151 EV_COST_VAR_ORG EWALVARORG WERTV8 CURR 15   2   Cost Variance Based on EV_ACT_ORG1  
152 EV_SCHED_VAR_ORG EVSCHVARORG WERTV8 CURR 15   2   Schedule Variance Based on EV_ACT_ORG1  
153 EV_COST_INDX_ORG EWALINDXORG DEC5_2 DEC 7   2   Cost Index Based on EV_ACT_ORG1  
154 EV_SCHED_INDX_ORG EVSCHINDXORG DEC5_2 DEC 7   2   Date Index Based on POC_ACT_ORG_AGG1  
155 EV_COST_VAR_CORR EWALVARCORR WERTV8 CURR 15   2   Cost Variance Based on EV_ACT_CORR1  
156 EV_SCHED_VAR_CORR EVSCHVARCORR WERTV8 CURR 15   2   Schedule Variance Based on EV_ACT_CORR1  
157 EV_COST_INDX_CORR EWALINDXCORR DEC5_2 DEC 7   2   Cost Index Based on EV_ACT_CORR1  
158 EV_SCHED_INDX_CORR EVSCHINDXCORR DEC5_2 DEC 7   2   Date Index Based on POC_ACT_CORR_AGG1  
159 .INCLU--AP       0   0   Append Structure: Progress Determination  
160 .INCLUDE       0   0   Progress Determination (Object Currency)  
161 .INCLUDE       0   0   Progress Analysis: Progress Values (PV; Object Currency)  
162 EV_PLAN_ORG1_OC EVPLANORG1 WERTV8 CURR 15   2   Budgeted cost of work scheduled  
163 EV_ACT_ORG1_OC EVACTORG1 WERTV8 CURR 15   2   Budgeted cost of work performed  
164 EV_ACT_CORR1_OC EVACTCORR1 WERTV8 CURR 15   2   Budgeted cost of work performed, adjusted  
165 EV_COST_VAR_ORG_OC EWALVARORG WERTV8 CURR 15   2   Cost Variance Based on EV_ACT_ORG1  
166 EV_SCHED_VAR_ORG_OC EVSCHVARORG WERTV8 CURR 15   2   Schedule Variance Based on EV_ACT_ORG1  
167 EV_SCHED_VAR_CORR_OC EWALVARCORR WERTV8 CURR 15   2   Cost Variance Based on EV_ACT_CORR1  
168 EV_COST_VAR_CORR_OC EVSCHVARCORR WERTV8 CURR 15   2   Schedule Variance Based on EV_ACT_CORR1  
169 STEUS STEUS STEUS CHAR 4   0   Control key *
170 DABEA CO_DAUBEA DAUER_6_1 QUAN 7   1   Processing time  
171 BEAZE BEAZE EINHEIT UNIT 3   0   Unit of measure for processing time  
172 PLIFZ PLIFZ DEC3 DEC 3   0   Planned delivery time in days  
173 PRART PS_PRART PS_PRART CHAR 2   0   Project type *
174 .INCLUDE       0   0   Structur extension for planned data  
175 OBJNR J_OBJNR J_OBJNR CHAR 22   0   Object number *
176 GJAHR GJAHR GJAHR NUMC 4   0   Fiscal Year  
177 PERIO CO_PERIO PERBL NUMC 3   0   Period  
178 MEINH MEINH MEINS UNIT 3   0   Unit of Measure for Display *
179 PERIV PERIV PERIV CHAR 2   0   Fiscal Year Variant *
180 UNTRG PS_UNTRG CHAR1 CHAR 1   0   Indicator: Element is subdivided  
181 SEL SELKZ SELKZ CHAR 1   0   Selection flag  
182 OBJEKTID_ONLY OBJEKT_ID CHAR30 CHAR 30   0   ID/Object key  
183 OBJEKTID_WITH_A OBJEKT_ID CHAR30 CHAR 30   0   ID/Object key  
184 TESTFRZ FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
185 TEENFRZ FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
186 TESTSPZ FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
187 TEENSPZ FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
188 TPSTFRZ FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
189 TPENFRZ FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
190 TPSTSPZ FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
191 TPENSPZ FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
192 ISTSTZ FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
193 ISTENZ FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
194 FPEDATE FSAVD DATUM DATS 8   0   Earliest scheduled start: Execution (date)  
195 FPETIME FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
196 FPPDATE FSAVD DATUM DATS 8   0   Earliest scheduled start: Execution (date)  
197 FPPTIME FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
198 ECKSTZ FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
199 ECKENZ FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
200 PROGSTZ FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
201 PROGENZ FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
202 EPANF FSAVD DATUM DATS 8   0   Earliest scheduled start: Execution (date)  
203 EPANZ FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
204 EPEND FSAVD DATUM DATS 8   0   Earliest scheduled start: Execution (date)  
205 EPENZ FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
206 EINSA EINSCHRA RESTRIKSTR CHAR 1   0   Constraint on the basic start date for the activity  
207 EINSE EINSCHRA RESTRIKSTR CHAR 1   0   Constraint on the basic start date for the activity  
208 EWSTD FSAVD DATUM DATS 8   0   Earliest scheduled start: Execution (date)  
209 EWSTDZ FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
210 EWEND FSAVD DATUM DATS 8   0   Earliest scheduled start: Execution (date)  
211 EWENDZ FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
212 EWSTA EINSCHRA RESTRIKSTR CHAR 1   0   Constraint on the basic start date for the activity  
213 EWSTE EINSCHRA RESTRIKSTR CHAR 1   0   Constraint on the basic start date for the activity  
214 ISBD FSAVD DATUM DATS 8   0   Earliest scheduled start: Execution (date)  
215 ISBZ FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
216 IEBD FSAVD DATUM DATS 8   0   Earliest scheduled start: Execution (date)  
217 IEBZ FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
218 PEDD FSAVD DATUM DATS 8   0   Earliest scheduled start: Execution (date)  
219 PEDZ FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
220 EINRUECK PS_STUFE INT1 INT1 3   0   Level in project hierarchy  
221 TABIX PS_WBSIND SYST_LONG INT4 10   0   Document table index for WBS elements  
222 EXT_AUFNR AUFNR AUFNR CHAR 12   0   Order Number *
223 VORNR VORNR VORNR CHAR 4   0   Operation/Activity Number  
224 UVORN VORNR VORNR CHAR 4   0   Operation/Activity Number  
225 NETZ_TABIX PS_WBSIND SYST_LONG INT4 10   0   Document table index for WBS elements  
226 AUFNRDTN AUFNR AUFNR CHAR 12   0   Order Number *
227 VORNRTN VORNR VORNR CHAR 4   0   Operation/Activity Number  
228 NETZ_STUFE PS_STUFE INT1 INT1 3   0   Level in project hierarchy  
229 CHART_ID BCCHARTID BCINT4 INT4 10   0   Identification of chart in bar chart  
230 STD_SORT PS_WBSIND SYST_LONG INT4 10   0   Document table index for WBS elements  
231 AUFNRD AUFNR AUFNR CHAR 12   0   Order Number *
232 AUFPT CO_AUFPL AUFPL NUMC 10   0   Routing number of operations in the order  
233 APLZT CO_APLZL CO_APLZL NUMC 8   0   General counter for order *
234 AUFPL CO_AUFPL AUFPL NUMC 10   0   Routing number of operations in the order  
235 APLZL CO_APLZL CO_APLZL NUMC 8   0   General counter for order *
236 ROWNUMBER BCROWNUMB BCINT4 INT4 10   0   Line number in bar chart  
237 PSIND PS_WBSIND SYST_LONG INT4 10   0   Document table index for WBS elements  
238 NWIND PS_NWIND SYST_LONG INT4 10   0   Document table index for networks  
239 FLIND INDEX_PLFL TABIX INT4 10   0   Index referring to record table for sequences  
240 ACIND PS_ACTIND SYST_LONG INT4 10   0   Doc. table index for activities  
241 VEIND PS_ACTIND SYST_LONG INT4 10   0   Doc. table index for activities  
242 MSIND PS_MSTIND SYST_LONG INT4 10   0   Document table index for milestones  
243 CRIND PS_MATIND TABIX INT4 10   0   Document table index for material components  
244 OBJECT SELKZ SELKZ CHAR 1   0   Selection flag  
245 PSPNR PS_POSNR PS_POSNR NUMC 8   0   WBS Element *
246 LOEKZ SELKZ SELKZ CHAR 1   0   Selection flag  
247 LOEVM SELKZ SELKZ CHAR 1   0   Selection flag  
248 KAPID CY_IND_OBJ SYST_LONG INT4 10   0   Index to object  
249 HAS_TEXT SELKZ SELKZ CHAR 1   0   Selection flag  
250 FLG_VAB SELKZ SELKZ CHAR 1   0   Selection flag  
251 DISPLAY SELKZ SELKZ CHAR 1   0   Selection flag  
252 DB_READ SELKZ SELKZ CHAR 1   0   Selection flag  
253 BOX_ID BCBOXID BCINT4 INT4 10   0   Identification for box in bar chart  
254 NODE_ID BCNODEID BCINT4 INT4 10   0   Identification for nodes in bar chart  
255 GRID_ID BCBOXID BCINT4 INT4 10   0   Identification for box in bar chart  
256 CAL_ID BCBOXID BCINT4 INT4 10   0   Identification for box in bar chart  
257 FLG_DISPLAY SELKZ SELKZ CHAR 1   0   Selection flag  
258 FLG_COLAPSED SELKZ SELKZ CHAR 1   0   Selection flag  
259 MARK_COPY SELKZ SELKZ CHAR 1   0   Selection flag  
260 MARK SELKZ SELKZ CHAR 1   0   Selection flag  
261 AUTYP AUFTYP AUFTYP NUMC 2   0   Order category  
262 AUART AUFART AUFART CHAR 4   0   Order Type *
263 OWAER OWAERS WAERS CUKY 5   0   Object currency for network activity *
264 AUSBLENDEN SELKZ SELKZ CHAR 1   0   Selection flag  
Foreign Keys
Source Table Source Column Foreign Table Foreign Column Dependency Factor Cardinality left Cardinality right
1 RCJ_PS_ORD EARBEH T006 MSEHI REF C CN
2 RCJ_PS_ORD EDAUEH T006 MSEHI REF C CN
3 RCJ_PS_ORD IARBEH T006 MSEHI REF C CN
4 RCJ_PS_ORD IDAUEH T006 MSEHI REF C CN
5 RCJ_PS_ORD PARBEH T006 MSEHI REF C CN
6 RCJ_PS_ORD PDAUEH T006 MSEHI REF C CN
7 RCJ_PS_ORD PSPRI TCN07 NPRIO REF C CN
8 RCJ_PS_ORD RARBEH T006 MSEHI REF C CN
9 RCJ_PS_ORD RDAUEH T006 MSEHI REF C CN
10 RCJ_PS_ORD USE04 T006 MSEHI    
11 RCJ_PS_ORD USE05 T006 MSEHI    
12 RCJ_PS_ORD USE06 TCURC WAERS    
13 RCJ_PS_ORD USE07 TCURC WAERS    
14 RCJ_PS_ORD VARBEH T006 MSEHI REF C CN
15 RCJ_PS_ORD VDAUEH T006 MSEHI REF C CN
16 RCJ_PS_ORD VEINH T006 MSEHI REF C CN
17 RCJ_PS_ORD WAERS TCURC WAERS REF C CN
History
Last changed by/on SAP  20130529 
SAP Release Created in