SAP ABAP Data Element PS_ABARBD (Processing % of duration)
Hierarchy
☛
SAP_APPL (Software Component) Logistics and Accounting
⤷
PS-IS (Application Component) Information System
⤷
CNIS (Package) Application development R/3 PS information system
⤷
⤷
Basic Data
| Data Element | PS_ABARBD |
| Short Description | Processing % of duration |
Data Type
| Category of Dictionary Type | D | Domain |
| Type of Object Referenced | No Information | |
| Domain / Name of Reference Type | CO_ABARB | |
| Data Type | NUMC | Character string with only digits |
| Length | 3 | |
| Decimal Places | 0 | |
| Output Length | 3 | |
| Value Table |
Further Characteristics
| Search Help: Name | ||
| Search Help: Parameters | ||
| Parameter ID | ||
| Default Component name | ||
| Change document | ||
| No Input History | ||
| Basic direction is set to LTR | ||
| No BIDI Filtering |
Field Label
| Length | Field Label | |
| Short | 10 | % duration |
| Medium | 15 | Proc % of dur. |
| Long | 20 | Processing % of dur. |
| Heading | 3 | %Du |
Documentation
Definition
Specifies the degree of processing of the network activities or the WBS elements in relation to the duration.
The following cases are possible:
For the network activity:
- Activity is finally confirmed
-> Degree of processing duration = 100
- Activity is partially confirmed
-> Degree of proc. duration = 100 x actual duration divided by (actual duration + remaining duration)
- Activity is not yet confirmed
-> Degree of processing for duration = 0
For the WBS element:
- If no actual finish date is entered
-> Degree of processing for the duration = 0
- If no actual finish date is entered
-> Degree of processing for the duration = 100
History
| Last changed by/on | SAP | 19951114 |
| SAP Release Created in |