SAP ABAP Table SRCNST100 (Structure for Project Structure Overview Reporting)
Hierarchy
SAP_APPL (Software Component) Logistics and Accounting
   PS-IS (Application Component) Information System
     CNIS (Package) Application development R/3 PS information system
Basic Data
Table Category INTTAB    Structure 
Structure SRCNST100   Table Relationship Diagram
Short Description Structure for Project Structure Overview Reporting    
Delivery and Maintenance
Pool/cluster      
Delivery Class      
Data Browser/Table View Maintenance     Display/Maintenance Allowed with Restrictions 
Components
     
Field Key Data Element Domain Data
Type
Length Decimal
Places
Short Description Check
table
1 .INCLUDE       0   0   Object Structure for Project Reporting  
2 .INCLUDE       0   0   Object Structure for Project Reporting  
3 ARNUMMER ADMI_RUN_D ADMI_RUN CHAR 6   0   Archiving Session Number  
4 VSGRUPPE VSGRUPPE TEXT20 CHAR 20   0   Group for a project version  
5 VSNUMMER VSNMR VSNMR CHAR 12   0   Number or description of a version  
6 OBJEKTID PS_IS_ID CHAR40 CHAR 40   0   ID/Object key  
7 KURZTEXT KURZTEXT TEXT40 CHAR 40   0   Short text/description of the object  
8 OBJEKTTYP OTEXT TEXT25 CHAR 25   0   Object Type Text  
9 .INCLUDE       0   0   Object Structure for Project Reporting  
10 ECKST PS_ECKST DATUM DATS 8   0   Basic start date  
11 ECKEN PS_ECKEN DATUM DATS 8   0   Finish date (from basic dates)  
12 PROGST PS_PROGST DATUM DATS 8   0   Forecast start date  
13 PROGEN PS_PROGEN DATUM DATS 8   0   Forecast finish date  
14 TESTFR PS_TESTFR DATUM DATS 8   0   Earliest scheduled start (from basic dates)  
15 TEENFR PS_TEENFR DATUM DATS 8   0   Earliest scheduled finish (from basic dates)  
16 TESTSP PS_TESTSP DATUM DATS 8   0   Latest scheduled start (from basic dates)  
17 TEENSP PS_TEENSP DATUM DATS 8   0   Latest scheduled finish (from basic dates)  
18 TPSTFR PS_TPSTFR DATUM DATS 8   0   Earliest scheduled start (from forecast dates)  
19 TPENFR PS_TPENFR DATUM DATS 8   0   Earliest scheduled finish (from forecast dates)  
20 TPSTSP PS_TPSTSP DATUM DATS 8   0   Latest scheduled start (from forecast dates)  
21 TPENSP PS_TPENSP DATUM DATS 8   0   Latest scheduled finish (from forecast dates)  
22 VORLST PS_VORLST DATUM DATS 8   0   Tentative start date  
23 VORLEN PS_VORLEN DATUM DATS 8   0   Tentative finish date  
24 ISTST PS_ISTST DATUM DATS 8   0   Actual start date  
25 ISTEN PS_ISTEN DATUM DATS 8   0   Actual finish date  
26 DATFS PS_DATFS DATUM DATS 8   0   Earliest start date  
27 DATSE PS_DATSE DATUM DATS 8   0   Latest finish date  
28 .INCLUDE       0   0   Object Structure for Project Reporting  
29 EDAUER PS_EDAUER_2 DAUER_9_1 QUAN 10   1   Duration  
30 EDAUEH PS_DAUEH MEINS UNIT 3   0   Actual duration unit *
31 PDAUER PS_PDAUER_VZ PS_DAUER_VZ QUAN 10   1   Forecast duration  
32 PDAUEH PS_DAUEH MEINS UNIT 3   0   Actual duration unit *
33 VDAUER PS_VDAUER_VZ PS_DAUER_VZ QUAN 10   1   Tentative duration  
34 VDAUEH PS_DAUEH MEINS UNIT 3   0   Actual duration unit *
35 IDAUER PS_IDAUER_VZ PS_DAUER_VZ QUAN 10   1   Actual duration  
36 IDAUEH PS_DAUEH MEINS UNIT 3   0   Actual duration unit *
37 RDAUER PS_RDAUER_VZ PS_DAUER_VZ QUAN 10   1   Remaining duration  
38 RDAUEH PS_DAUEH MEINS UNIT 3   0   Actual duration unit *
39 ABARBD PS_ABARBD CO_ABARB NUMC 3   0   Processing % of duration  
40 .INCLUDE       0   0   Object Structure for Project Reporting  
41 EARBEI PS_EARBEI_2 PS_ARBEIT_2 QUAN 13   3   Work  
42 EARBEH PS_ARBEH MEINS UNIT 3   0   Unit for work *
43 PARBEI PS_PARBEI_VZ PS_ARBEIT_VZ QUAN 13   3   Forecast work  
44 PARBEH PS_ARBEH MEINS UNIT 3   0   Unit for work *
45 VARBEI PS_VARBEI_VZ PS_ARBEIT_VZ QUAN 13   3   Tentative work  
46 VARBEH PS_ARBEH MEINS UNIT 3   0   Unit for work *
47 IARBEI PS_IARBEI_VZ PS_ARBEIT_VZ QUAN 13   3   Actual work  
48 IARBEH PS_ARBEH MEINS UNIT 3   0   Unit for work *
49 RARBEI PS_RARBEI_VZ PS_ARBEIT_VZ QUAN 13   3   Remaining work  
50 RARBEH PS_ARBEH MEINS UNIT 3   0   Unit for work *
51 .INCLUDE       0   0   Object Structure for Project Reporting  
52 ABARBA PS_ABARBA CO_ABARB NUMC 3   0   Percent of completion for work  
53 SLWID SLWID SLWID CHAR 7   0   Key word ID for user-defined fields *
54 USR00 USRCHAR20 USRCHAR20 CHAR 20   0   User field with 20 characters  
55 USR01 USRCHAR20 USRCHAR20 CHAR 20   0   User field with 20 characters  
56 USR02 USRCHAR10 USRCHAR10 CHAR 10   0   User field with 10 characters  
57 USR03 USRCHAR10 USRCHAR10 CHAR 10   0   User field with 10 characters  
58 .INCLUDE       0   0   Object Structure for Project Reporting  
59 USR04 USRQUAN13 USRQUAN13 QUAN 13   3   User field for quantity (length 10.3)  
60 USE04 USRUNIT MEINS UNIT 3   0   User field: Unit for quantity fields *
61 USR05 USRQUAN13 USRQUAN13 QUAN 13   3   User field for quantity (length 10.3)  
62 USE05 USRUNIT MEINS UNIT 3   0   User field: Unit for quantity fields *
63 USR06 USRCURR13 USRCURR13 CURR 13   3   User-defined field for values (length 10,3)  
64 USE06 USRCUKY WAERS CUKY 5   0   User field: Unit for value fields *
65 USR07 USRCURR13 USRCURR13 CURR 13   3   User-defined field for values (length 10,3)  
66 USE07 USRCUKY WAERS CUKY 5   0   User field: Unit for value fields *
67 USR08 USRDATE USRDATE DATS 8   0   User field for date  
68 USR09 USRDATE USRDATE DATS 8   0   User field for date  
69 .INCLUDE       0   0   Object Structure for Project Reporting  
70 USR10 USRFLAG FLAG CHAR 1   0   User-defined field: Indicator for reports  
71 USR11 USRFLAG FLAG CHAR 1   0   User-defined field: Indicator for reports  
72 VERNR PS_VERNR_C CHAR8 CHAR 8   0   Number of responsible person (project mgr)/MRP controller  
73 VERNA PS_VERNA PS_VERNA CHAR 25   0   Name of responsible person (Project manager)  
74 AENNR AENNR AENNR CHAR 12   0   Change Number *
75 WERKS WERKS_D WERKS CHAR 4   0   Plant *
76 ARBPL ARBPL ARBPL CHAR 8   0   Work center  
77 KALID WFCID WFCID CHAR 2   0   Factory Calendar *
78 TXTSP LTXSP SPRAS LANG 1   0   Language: The long text was stored in this language *
79 PSPRI NW_PRIO NW_PRIO CHAR 1   0   Priority *
80 STATXT STATUSTEXT_2 CHAR80 CHAR 80   0   Edited status text  
81 FRUEHER FRUEHER_2 DAUER_9_1 QUAN 10   1   Actual start is before earliest scheduled start  
82 SPAETER SPAETER_2 DAUER_9_1 QUAN 10   1   Actual Finish/Planned Finish After Latest Scheduled Finish  
83 VERZUG VERZUG_2 DAUER_9_1 QUAN 10   1   Duration After Latest Scheduled Finish  
84 VORBEI VORBEI_2 DAUER_9_1 QUAN 10   1   Duration After Earliest Scheduled Start  
85 VEINH VERZ_EINHT MEINS UNIT 3   0   Unit for Duration of the Delay *
86 PUFGS PUFFR_GESM PUFFER DEC 3   0   Total float  
87 PUFFR PUFFR_FREI PUFFER DEC 3   0   Free float  
88 PUFGP PPUFF_GESM PUFFER DEC 3   0   Total float (from forecast)  
89 PUFFP PPUFF_FREI PUFFER DEC 3   0   Free float (from forecast)  
90 KOKRS KOKRS CACCD CHAR 4   0   Controlling Area *
91 BUKRS BUKRS BUKRS CHAR 4   0   Company Code *
92 GSBER GSBER GSBER CHAR 4   0   Business Area *
93 WAERS WAERS WAERS CUKY 5   0   Currency Key *
94 OWAERS OWAERS WAERS CUKY 5   0   Object currency for network activity *
95 MEINH MEINH MEINS UNIT 3   0   Unit of Measure for Display *
96 .INCLUDE       0   0   Key Figures for Commercial Reporting in Structure Overview  
97 .INCLUDE       0   0   RPSCO_LIS for graphics  
98 PROKSTPLAN PROKSTPLAN WERTV8 CURR 15   2   Current project cost plan  
99 PROKSTPLN2 PROKSTPLN2 WERTV8 CURR 15   2   Project cost plan (version 2)  
100 AUFKSTPLAN AUFKSTPLAN WERTV8 CURR 15   2   Current order cost plan  
101 AUFKSTPLN2 AUFKSTPLN2 WERTV8 CURR 15   2   Order cost plan (version 2)  
102 PROERLPLAN PROERLPLAN WERTV8 CURR 15   2   Current project revenue plan  
103 PROERLPLN2 PROERLPLN2 WERTV8 CURR 15   2   Project revenue plan (version 2)  
104 AUFERLPLAN AUFERLPLAN WERTV8 CURR 15   2   Current order revenue plan  
105 AUFERLPLN2 AUFERLPLN2 WERTV8 CURR 15   2   Order revenue plan (version 2)  
106 KREDFINPLN KREDFINPLN WERTV8 CURR 15   2   Current financial budget, credit side  
107 DEBFINPLN DEBFINPLN WERTV8 CURR 15   2   Current cash budget, debit side  
108 BUDGET BUDGET WERTV8 CURR 15   2   Budget of a Measure (App. Request Variant Was Replaced)  
109 FREIGABE FREIGABE WERTV8 CURR 15   2   Release  
110 AUFTRANF AUFTRANF WERTV8 CURR 15   2   Residual order plan  
111 FESTPROBL FESTPROBL WERTV8 CURR 15   2   Fixed price commitment  
112 KSTOBLGES KSTOBLGES WERTV8 CURR 15   2   Total cost commitment  
113 ISTKOSTEN ISTKOSTEN WERTV8 CURR 15   2   Actual costs  
114 ISTERLOESE ISTERLOESE WERTV8 CURR 15   2   Actual revenues  
115 KZHLNG KZHLNG WERTV8 CURR 15   2   Total credit side payments (down payments and payments)  
116 DZHLNG DZHLNG WERTV8 CURR 15   2   Total debit side payments (down payments and payments)  
117 .INCLU--AP       0   0   Append Structure RCJ_RPSCO_LIS  
118 .INCLUDE       0   0   RPSCO_LIS for Graphic (Object Currency)  
119 PROKSTPLAN_OC PROKSTPLANOC WERTV8 CURR 15   2   Current Project Cost Plan in Object Currency  
120 PROKSTPLN2_OC PROKSTPLN2OC WERTV8 CURR 15   2   Project Cost Plan (Version 2) in Object Currency  
121 AUFKSTPLAN_OC AUFKSTPLANOC WERTV8 CURR 15   2   Current Order Cost Plan in Object Currency  
122 AUFKSTPLN2_OC AUFKSTPLN2OC WERTV8 CURR 15   2   Order Cost Plan (Version 2) in Object Currency  
123 PROERLPLAN_OC PROERLPLANOC WERTV8 CURR 15   2   Current Project Revenue Plan in Object Currency  
124 PROERLPLN2_OC PROERLPLN2OC WERTV8 CURR 15   2   Project Revenue Plan (Version 2) in Object Currency  
125 AUFERLPLAN_OC AUFERLPLANOC WERTV8 CURR 15   2   Current Order Revenue Plan in Object Currency  
126 AUFERLPLN2_OC AUFERLPLN2OC WERTV8 CURR 15   2   Order Revenue Plan (Version 2) in Object Currency  
127 KREDFINPLN_OC KREDFINPLNOC WERTV8 CURR 15   2   Current Credit Side Cash Budget in Object Currency  
128 DEBFINPLN_OC DEBFINPLNOC WERTV8 CURR 15   2   Current Debit Side Cash Budget in Object Currency  
129 BUDGET_OC BUDGETOC WERTV8 CURR 15   2   Appropriation Budget (Appr.Request Variant Replaced) in OC  
130 FREIGABE_OC FREIGABEOC WERTV8 CURR 15   2   Release in Object Currency  
131 AUFTRANF_OC AUFTRANFOC WERTV8 CURR 15   2   Residual Order Plan in Object Currency  
132 FESTPROBL_OC FESTPROBLOC WERTV8 CURR 15   2   Fixed Price Commitment in Object Currency  
133 KSTOBLGES_OC KSTOBLGESOC WERTV8 CURR 15   2   Total Cost Commitment in Object Currency  
134 ISTKOSTEN_OC ISTKOSTENOC WERTV8 CURR 15   2   Act. Costs in Object Currency  
135 ISTERLOESE_OC ISTERLOESEOC WERTV8 CURR 15   2   Actual Revenues in Object Currency  
136 KZHLNG_OC KZHLNGOC WERTV8 CURR 15   2   Total Vendor Payments (Down Payments and Payments) OC  
137 DZHLNG_OC DZHLNGOC WERTV8 CURR 15   2   Total Customer Payments (Down Payments and Payments) OC  
138 .INCLUDE       0   0   Progress Calculation: All  
139 .INCLUDE       0   0   Progress Analysis: Values  
140 EV_PLAN_ORG1 EVPLANORG1 WERTV8 CURR 15   2   Budgeted cost of work scheduled  
141 EV_ACT_ORG1 EVACTORG1 WERTV8 CURR 15   2   Budgeted cost of work performed  
142 EV_ACT_CORR1 EVACTCORR1 WERTV8 CURR 15   2   Budgeted cost of work performed, adjusted  
143 .INCLUDE       0   0   Progress Analysis: Quantities  
144 EV_PLAN_QUAN_ORG1 EVPLANQUANORG1 CQUA8 QUAN 15   3   Budgeted cost of work scheduled, quantity  
145 EV_PLAN_QUAN_ORG1_UNIT EV_PLAN_QUAN_ORG1_UNIT MEINS UNIT 3   0   BCWS, Unit of Measure *
146 EV_ACT_QUAN_ORG1 EVACTQUANORG1 CQUA8 QUAN 15   3   Budgeted cost of work performed, quantity  
147 EV_ACT_QUAN_ORG1_UNIT EV_ACT_QUAN_ORG1_UNIT MEINS UNIT 3   0   BCWP, Unit of Measure *
148 EV_ACT_QUAN_CORR1 EVACTQUANCORR1 CQUA8 QUAN 15   3   Budgeted cost of work performed, adjusted quantity  
149 EV_ACT_QUAN_CORR1_UNIT EV_ACT_QUAN_CORR1_UNIT MEINS UNIT 3   0   BCWP, Adjusted Quantity (Unit) *
150 .INCLUDE       0   0   Progress Analysis: Percentage of completion (POC)  
151 POC_PLAN_ORG_AGG1 POCPLANORGAGG1 EV_PROGRES DEC 6   3   Aggregate planned percentage of completion  
152 POC_PLAN_ORG_NAGG1 POCPLANORGNAGG1 EV_PROGRES DEC 6   3   Non-aggregated planned percentage of completion  
153 POC_ACT_ORG_AGG1 POCACTORGAGG1 EV_PROGRES DEC 6   3   Aggregated actual POC  
154 POC_ACT_ORG_NAGG1 POCACTORGNAGG1 EV_PROGRES DEC 6   3   Non-aggregated actual percentage of completion  
155 POC_ACT_CORR_AGG1 POCACTCORRAGG1 EV_PROGRES DEC 6   3   Adjusted aggregated actual POC  
156 POC_ACT_CORR_NAGG1 POCACTCORRNAGG1 EV_PROGRES DEC 6   3   Adjusted non-aggregated actual percentage of completion  
157 EV_COST_VAR_ORG EWALVARORG WERTV8 CURR 15   2   Cost Variance Based on EV_ACT_ORG1  
158 EV_SCHED_VAR_ORG EVSCHVARORG WERTV8 CURR 15   2   Schedule Variance Based on EV_ACT_ORG1  
159 EV_COST_INDX_ORG EWALINDXORG DEC5_2 DEC 7   2   Cost Index Based on EV_ACT_ORG1  
160 EV_SCHED_INDX_ORG EVSCHINDXORG DEC5_2 DEC 7   2   Date Index Based on POC_ACT_ORG_AGG1  
161 EV_COST_VAR_CORR EWALVARCORR WERTV8 CURR 15   2   Cost Variance Based on EV_ACT_CORR1  
162 EV_SCHED_VAR_CORR EVSCHVARCORR WERTV8 CURR 15   2   Schedule Variance Based on EV_ACT_CORR1  
163 EV_COST_INDX_CORR EWALINDXCORR DEC5_2 DEC 7   2   Cost Index Based on EV_ACT_CORR1  
164 EV_SCHED_INDX_CORR EVSCHINDXCORR DEC5_2 DEC 7   2   Date Index Based on POC_ACT_CORR_AGG1  
165 .INCLU--AP       0   0   Append Structure: Progress Determination  
166 .INCLUDE       0   0   Progress Determination (Object Currency)  
167 .INCLUDE       0   0   Progress Analysis: Progress Values (PV; Object Currency)  
168 EV_PLAN_ORG1_OC EVPLANORG1 WERTV8 CURR 15   2   Budgeted cost of work scheduled  
169 EV_ACT_ORG1_OC EVACTORG1 WERTV8 CURR 15   2   Budgeted cost of work performed  
170 EV_ACT_CORR1_OC EVACTCORR1 WERTV8 CURR 15   2   Budgeted cost of work performed, adjusted  
171 EV_COST_VAR_ORG_OC EWALVARORG WERTV8 CURR 15   2   Cost Variance Based on EV_ACT_ORG1  
172 EV_SCHED_VAR_ORG_OC EVSCHVARORG WERTV8 CURR 15   2   Schedule Variance Based on EV_ACT_ORG1  
173 EV_SCHED_VAR_CORR_OC EWALVARCORR WERTV8 CURR 15   2   Cost Variance Based on EV_ACT_CORR1  
174 EV_COST_VAR_CORR_OC EVSCHVARCORR WERTV8 CURR 15   2   Schedule Variance Based on EV_ACT_CORR1  
175 .INCLUDE       0   0   Object Structure for Project Reporting  
176 EVMET_P1 EV_METHOD_PLN CHAR10 CHAR 10   0   Measurement method for PS progress analysis (plan)  
177 EVMET_A1 EV_METHOD_ACT CHAR10 CHAR 10   0   Measurement method in PS progress analysis (actual)  
178 EVGEW EV_WEIGHTD DEC8 DEC 8   0   Aggregation weight for POC (PS progress)  
179 .INCLUDE       0   0    
180 OBJNR J_OBJNR J_OBJNR CHAR 22   0   Object number *
181 HIERSTUFE HIERSTUFE INT4 INT4 10   0   Classification: Level in Hierarchy  
182 TABNAME TABNAME AS4TAB CHAR 30   0   Table Name *
183 TABINDEX PS_ENTRY SYST_LONG INT4 10   0   Entry (line number on a list)  
History
Last changed by/on SAP  20130529 
SAP Release Created in 600