SAP ABAP Data Element PS_VDAUER (Tentative duration)
Hierarchy
☛
SAP_APPL (Software Component) Logistics and Accounting
⤷ PS-IS (Application Component) Information System
⤷ CNIS (Package) Application development R/3 PS information system
⤷ PS-IS (Application Component) Information System
⤷ CNIS (Package) Application development R/3 PS information system
Basic Data
Data Element | PS_VDAUER |
Short Description | Tentative duration |
Data Type
Category of Dictionary Type | D | Domain |
Type of Object Referenced | No Information | |
Domain / Name of Reference Type | DAUER_4_1 | |
Data Type | QUAN | Quantity field, points to a unit field with format UNIT |
Length | 5 | |
Decimal Places | 1 | |
Output Length | 7 | |
Value Table |
Further Characteristics
Search Help: Name | ||
Search Help: Parameters | ||
Parameter ID | ||
Default Component name | ||
Change document | ||
No Input History | ||
Basic direction is set to LTR | ||
No BIDI Filtering |
Field Label
Length | Field Label | |
Short | 10 | Tent. dur. |
Medium | 15 | Tentative durtn |
Long | 20 | Tentative duration |
Heading | 7 | TentDur |
Documentation
Definition
Indicates the provisional duration of network activities and WBS
elements.
The provisional duration informs most exactly the expected duration.
The system differentiates the following cases for network
activities:
- Activity is confirmed at the end -> provisional duration = actual
- duration
- Activity is partially confirmed
- Forecast duration from the confirmation exists
- -> provisional duration = forecast duration from the confirmation
- Forecast end date from the confirmation exists
- -> provisional duration = forecast end date minus actual start date
- niether forecast duration nor forecast end date from the confirmation exists:
- if forecast duration does not equal 0 -> provisional duration =
- forecast duration from the forecast circle
- if forecast duration equals 0 -> provisional duration = duration
- Activity has not yet been confirmed:
- if forecast duration does not equal 0
- -> provisional duration = forecast duration from the forcast circle
- if forecast duration equals 0
- -> provisional duration = duration
The following cases are differentiated for WBS elements:
- WBS actual end date is set
-> provisional duration = actual duration
- Forecast duration is given
-> provisional duration = forecast duration
- all other cases
-> provisional duration = duration
History
Last changed by/on | SAP | 19951114 |
SAP Release Created in |