Data Element list used by SAP ABAP Table RCJ_PS_PLAN (Object Structure for Project Reporting)
SAP ABAP Table RCJ_PS_PLAN (Object Structure for Project Reporting) is using
# Object Type Object Name Object Description Note
     
1 Data Element  ABGR_SCHL Results Analysis Key
2 Data Element  ARBPL Work center
3 Data Element  AUFERLPLAN Current order revenue plan
4 Data Element  AUFERLPLANOC Current Order Revenue Plan in Object Currency
5 Data Element  AUFERLPLN2 Order revenue plan (version 2)
6 Data Element  AUFERLPLN2OC Order Revenue Plan (Version 2) in Object Currency
7 Data Element  AUFKALSM Costing Sheet
8 Data Element  AUFKSTPLAN Current order cost plan
9 Data Element  AUFKSTPLANOC Current Order Cost Plan in Object Currency
10 Data Element  AUFKSTPLN2 Order cost plan (version 2)
11 Data Element  AUFKSTPLN2OC Order Cost Plan (Version 2) in Object Currency
12 Data Element  AUFTRANF Residual order plan
13 Data Element  AUFTRANFOC Residual Order Plan in Object Currency
14 Data Element  AUFZSCHL Overhead key
15 Data Element  BEAZE Unit of measure for processing time
16 Data Element  BUDGET Budget of a Measure (App. Request Variant Was Replaced)
17 Data Element  BUDGETOC Appropriation Budget (Appr.Request Variant Replaced) in OC
18 Data Element  BUKRS Company Code
19 Data Element  CO_DAUBEA Processing time
20 Data Element  DEBFINPLN Current cash budget, debit side
21 Data Element  DEBFINPLNOC Current Debit Side Cash Budget in Object Currency
22 Data Element  DZHLNG Total debit side payments (down payments and payments)
23 Data Element  DZHLNGOC Total Customer Payments (Down Payments and Payments) OC
24 Data Element  EVACTCORR1 Budgeted cost of work performed, adjusted
25 Data Element  EVACTCORR1 Budgeted cost of work performed, adjusted
26 Data Element  EVACTORG1 Budgeted cost of work performed
27 Data Element  EVACTORG1 Budgeted cost of work performed
28 Data Element  EVACTQUANCORR1 Budgeted cost of work performed, adjusted quantity
29 Data Element  EVACTQUANORG1 Budgeted cost of work performed, quantity
30 Data Element  EVPLANORG1 Budgeted cost of work scheduled
31 Data Element  EVPLANORG1 Budgeted cost of work scheduled
32 Data Element  EVPLANQUANORG1 Budgeted cost of work scheduled, quantity
33 Data Element  EVSCHINDXCORR Date Index Based on POC_ACT_CORR_AGG1
34 Data Element  EVSCHINDXORG Date Index Based on POC_ACT_ORG_AGG1
35 Data Element  EVSCHVARCORR Schedule Variance Based on EV_ACT_CORR1
36 Data Element  EVSCHVARCORR Schedule Variance Based on EV_ACT_CORR1
37 Data Element  EVSCHVARORG Schedule Variance Based on EV_ACT_ORG1
38 Data Element  EVSCHVARORG Schedule Variance Based on EV_ACT_ORG1
39 Data Element  EV_ACT_QUAN_CORR1_UNIT BCWP, Adjusted Quantity (Unit)
40 Data Element  EV_ACT_QUAN_ORG1_UNIT BCWP, Unit of Measure
41 Data Element  EV_PLAN_QUAN_ORG1_UNIT BCWS, Unit of Measure
42 Data Element  EWALINDXCORR Cost Index Based on EV_ACT_CORR1
43 Data Element  EWALINDXORG Cost Index Based on EV_ACT_ORG1
44 Data Element  EWALVARCORR Cost Variance Based on EV_ACT_CORR1
45 Data Element  EWALVARCORR Cost Variance Based on EV_ACT_CORR1
46 Data Element  EWALVARORG Cost Variance Based on EV_ACT_ORG1
47 Data Element  EWALVARORG Cost Variance Based on EV_ACT_ORG1
48 Data Element  FABKL Factory calendar key
49 Data Element  FESTPROBL Fixed price commitment
50 Data Element  FESTPROBLOC Fixed Price Commitment in Object Currency
51 Data Element  FREIGABE Release
52 Data Element  FREIGABEOC Release in Object Currency
53 Data Element  FRUEHER Actual start is before earliest scheduled start
54 Data Element  ISTERLOESE Actual revenues
55 Data Element  ISTERLOESEOC Actual Revenues in Object Currency
56 Data Element  ISTKOSTEN Actual costs
57 Data Element  ISTKOSTENOC Act. Costs in Object Currency
58 Data Element  KREDFINPLN Current financial budget, credit side
59 Data Element  KREDFINPLNOC Current Credit Side Cash Budget in Object Currency
60 Data Element  KSTOBLGES Total cost commitment
61 Data Element  KSTOBLGESOC Total Cost Commitment in Object Currency
62 Data Element  KURZTEXT Short text/description of the object
63 Data Element  KZHLNG Total credit side payments (down payments and payments)
64 Data Element  KZHLNGOC Total Vendor Payments (Down Payments and Payments) OC
65 Data Element  NW_PRIO Priority
66 Data Element  OBJEKT_ID ID/Object key
67 Data Element  OTEXT Object Type Text
68 Data Element  OWAERS Object currency for network activity
69 Data Element  PLIFZ Planned delivery time in days
70 Data Element  POCACTCORRAGG1 Adjusted aggregated actual POC
71 Data Element  POCACTCORRNAGG1 Adjusted non-aggregated actual percentage of completion
72 Data Element  POCACTORGAGG1 Aggregated actual POC
73 Data Element  POCACTORGNAGG1 Non-aggregated actual percentage of completion
74 Data Element  POCPLANORGAGG1 Aggregate planned percentage of completion
75 Data Element  POCPLANORGNAGG1 Non-aggregated planned percentage of completion
76 Data Element  PPUFF_FREI Free float (from forecast)
77 Data Element  PPUFF_GESM Total float (from forecast)
78 Data Element  PRCTR Profit Center
79 Data Element  PROERLPLAN Current project revenue plan
80 Data Element  PROERLPLANOC Current Project Revenue Plan in Object Currency
81 Data Element  PROERLPLN2 Project revenue plan (version 2)
82 Data Element  PROERLPLN2OC Project Revenue Plan (Version 2) in Object Currency
83 Data Element  PROKSTPLAN Current project cost plan
84 Data Element  PROKSTPLANOC Current Project Cost Plan in Object Currency
85 Data Element  PROKSTPLN2 Project cost plan (version 2)
86 Data Element  PROKSTPLN2OC Project Cost Plan (Version 2) in Object Currency
87 Data Element  PS_ABARBA Percent of completion for work
88 Data Element  PS_ABARBD Processing % of duration
89 Data Element  PS_ARBEH Unit for work
90 Data Element  PS_ARBEH Unit for work
91 Data Element  PS_ARBEH Unit for work
92 Data Element  PS_ARBEH Unit for work
93 Data Element  PS_ARBEH Unit for work
94 Data Element  PS_ASTNR Applicant number
95 Data Element  PS_BELKZ Indicator: Account assignment element
96 Data Element  PS_DATFS Earliest start date
97 Data Element  PS_DATSE Latest finish date
98 Data Element  PS_DAUEH Actual duration unit
99 Data Element  PS_DAUEH Actual duration unit
100 Data Element  PS_DAUEH Actual duration unit
101 Data Element  PS_DAUEH Actual duration unit
102 Data Element  PS_DAUEH Actual duration unit
103 Data Element  PS_EARBEI Work
104 Data Element  PS_ECKEN Finish date (from basic dates)
105 Data Element  PS_ECKST Basic start date
106 Data Element  PS_EDAUER Duration
107 Data Element  PS_FAKKZ Indicator: Billing element
108 Data Element  PS_IARBEI Actual work
109 Data Element  PS_IDAUER Actual duration
110 Data Element  PS_ISTEN Actual finish date
111 Data Element  PS_ISTST Actual start date
112 Data Element  PS_PARBEI Forecast work
113 Data Element  PS_PDAUER Forecast duration
114 Data Element  PS_PGSBR Business area for WBS element
115 Data Element  PS_PLAKZ Indicator: Planning element
116 Data Element  PS_PRART Project type
117 Data Element  PS_PROGEN Forecast finish date
118 Data Element  PS_PROGST Forecast start date
119 Data Element  PS_RARBEI Remaining work
120 Data Element  PS_RDAUER Remaining duration
121 Data Element  PS_STUFE Level in project hierarchy
122 Data Element  PS_TEENFR Earliest scheduled finish (from basic dates)
123 Data Element  PS_TEENSP Latest scheduled finish (from basic dates)
124 Data Element  PS_TESTFR Earliest scheduled start (from basic dates)
125 Data Element  PS_TESTSP Latest scheduled start (from basic dates)
126 Data Element  PS_TPENFR Earliest scheduled finish (from forecast dates)
127 Data Element  PS_TPENSP Latest scheduled finish (from forecast dates)
128 Data Element  PS_TPSTFR Earliest scheduled start (from forecast dates)
129 Data Element  PS_TPSTSP Latest scheduled start (from forecast dates)
130 Data Element  PS_VARBEI Tentative work
131 Data Element  PS_VDAUER Tentative duration
132 Data Element  PS_VERNA Name of responsible person (Project manager)
133 Data Element  PS_VERNR_C Number of responsible person (project mgr)/MRP controller
134 Data Element  PS_ZSCHM Interest Profile for Project/Order Interest Calculation
135 Data Element  PUFFR_FREI Free float
136 Data Element  PUFFR_GESM Total float
137 Data Element  SAKTO Cost Element
138 Data Element  SPAETER Actual Finish/Planned Finish After Latest Scheduled Finish
139 Data Element  STATUSTEXT Edited status text
140 Data Element  STEUS Control key
141 Data Element  USRCHAR10 User field with 10 characters
142 Data Element  USRCHAR10 User field with 10 characters
143 Data Element  USRCHAR20 User field with 20 characters
144 Data Element  USRCHAR20 User field with 20 characters
145 Data Element  USRCUKY User field: Unit for value fields
146 Data Element  USRCUKY User field: Unit for value fields
147 Data Element  USRCURR13 User-defined field for values (length 10,3)
148 Data Element  USRCURR13 User-defined field for values (length 10,3)
149 Data Element  USRDATE User field for date
150 Data Element  USRDATE User field for date
151 Data Element  USRFLAG User-defined field: Indicator for reports
152 Data Element  USRFLAG User-defined field: Indicator for reports
153 Data Element  USRQUAN13 User field for quantity (length 10.3)
154 Data Element  USRQUAN13 User field for quantity (length 10.3)
155 Data Element  USRUNIT User field: Unit for quantity fields
156 Data Element  USRUNIT User field: Unit for quantity fields
157 Data Element  VERZUG Duration After Latest Scheduled Finish
158 Data Element  VERZ_EINHT Unit for Duration of the Delay
159 Data Element  VORBEI Duration After Latest Scheduled Start
160 Data Element  WAERS Currency Key
161 Data Element  WERKS_D Plant