Data Element list used by SAP ABAP Table SPSINFO_FC101 (Structure for Project Structure Overview Reporting)
SAP ABAP Table
SPSINFO_FC101 (Structure for Project Structure Overview Reporting) is using
| # | Object Type | Object Name | Object Description | Note |
|---|---|---|---|---|
| 1 | ADMI_RUN_D | Archiving Session Number | ||
| 2 | AENNR | Change Number | ||
| 3 | ARBPL | Work center | ||
| 4 | AUFERLPLAN | Current order revenue plan | ||
| 5 | AUFERLPLANOC | Current Order Revenue Plan in Object Currency | ||
| 6 | AUFERLPLN2 | Order revenue plan (version 2) | ||
| 7 | AUFERLPLN2OC | Order Revenue Plan (Version 2) in Object Currency | ||
| 8 | AUFKSTPLAN | Current order cost plan | ||
| 9 | AUFKSTPLANOC | Current Order Cost Plan in Object Currency | ||
| 10 | AUFKSTPLN2 | Order cost plan (version 2) | ||
| 11 | AUFKSTPLN2OC | Order Cost Plan (Version 2) in Object Currency | ||
| 12 | AUFTRANF | Residual order plan | ||
| 13 | AUFTRANFOC | Residual Order Plan in Object Currency | ||
| 14 | BUDGET | Budget of a Measure (App. Request Variant Was Replaced) | ||
| 15 | BUDGETOC | Appropriation Budget (Appr.Request Variant Replaced) in OC | ||
| 16 | BUKRS | Company Code | ||
| 17 | DEBFINPLN | Current cash budget, debit side | ||
| 18 | DEBFINPLNOC | Current Debit Side Cash Budget in Object Currency | ||
| 19 | DZHLNG | Total debit side payments (down payments and payments) | ||
| 20 | DZHLNGOC | Total Customer Payments (Down Payments and Payments) OC | ||
| 21 | EVACTCORR1 | Budgeted cost of work performed, adjusted | ||
| 22 | EVACTCORR1 | Budgeted cost of work performed, adjusted | ||
| 23 | EVACTORG1 | Budgeted cost of work performed | ||
| 24 | EVACTORG1 | Budgeted cost of work performed | ||
| 25 | EVACTQUANCORR1 | Budgeted cost of work performed, adjusted quantity | ||
| 26 | EVACTQUANORG1 | Budgeted cost of work performed, quantity | ||
| 27 | EVPLANORG1 | Budgeted cost of work scheduled | ||
| 28 | EVPLANORG1 | Budgeted cost of work scheduled | ||
| 29 | EVPLANQUANORG1 | Budgeted cost of work scheduled, quantity | ||
| 30 | EVSCHINDXCORR | Date Index Based on POC_ACT_CORR_AGG1 | ||
| 31 | EVSCHINDXORG | Date Index Based on POC_ACT_ORG_AGG1 | ||
| 32 | EVSCHVARCORR | Schedule Variance Based on EV_ACT_CORR1 | ||
| 33 | EVSCHVARCORR | Schedule Variance Based on EV_ACT_CORR1 | ||
| 34 | EVSCHVARORG | Schedule Variance Based on EV_ACT_ORG1 | ||
| 35 | EVSCHVARORG | Schedule Variance Based on EV_ACT_ORG1 | ||
| 36 | EV_ACT_QUAN_CORR1_UNIT | BCWP, Adjusted Quantity (Unit) | ||
| 37 | EV_ACT_QUAN_ORG1_UNIT | BCWP, Unit of Measure | ||
| 38 | EV_METHOD_ACT | Measurement method in PS progress analysis (actual) | ||
| 39 | EV_METHOD_PLN | Measurement method for PS progress analysis (plan) | ||
| 40 | EV_PLAN_QUAN_ORG1_UNIT | BCWS, Unit of Measure | ||
| 41 | EV_WEIGHTD | Aggregation weight for POC (PS progress) | ||
| 42 | EWALINDXCORR | Cost Index Based on EV_ACT_CORR1 | ||
| 43 | EWALINDXORG | Cost Index Based on EV_ACT_ORG1 | ||
| 44 | EWALVARCORR | Cost Variance Based on EV_ACT_CORR1 | ||
| 45 | EWALVARCORR | Cost Variance Based on EV_ACT_CORR1 | ||
| 46 | EWALVARORG | Cost Variance Based on EV_ACT_ORG1 | ||
| 47 | EWALVARORG | Cost Variance Based on EV_ACT_ORG1 | ||
| 48 | FESTPROBL | Fixed price commitment | ||
| 49 | FESTPROBLOC | Fixed Price Commitment in Object Currency | ||
| 50 | FREIGABE | Release | ||
| 51 | FREIGABEOC | Release in Object Currency | ||
| 52 | FRUEHER_2 | Actual start is before earliest scheduled start | ||
| 53 | GSBER | Business Area | ||
| 54 | HIERSTUFE | Classification: Level in Hierarchy | ||
| 55 | ISTERLOESE | Actual revenues | ||
| 56 | ISTERLOESEOC | Actual Revenues in Object Currency | ||
| 57 | ISTKOSTEN | Actual costs | ||
| 58 | ISTKOSTENOC | Act. Costs in Object Currency | ||
| 59 | J_OBJNR | Object number | ||
| 60 | KOKRS | Controlling Area | ||
| 61 | KREDFINPLN | Current financial budget, credit side | ||
| 62 | KREDFINPLNOC | Current Credit Side Cash Budget in Object Currency | ||
| 63 | KSTOBLGES | Total cost commitment | ||
| 64 | KSTOBLGESOC | Total Cost Commitment in Object Currency | ||
| 65 | KURZTEXT | Short text/description of the object | ||
| 66 | KZHLNG | Total credit side payments (down payments and payments) | ||
| 67 | KZHLNGOC | Total Vendor Payments (Down Payments and Payments) OC | ||
| 68 | LTXSP | Language: The long text was stored in this language | ||
| 69 | MEINH | Unit of Measure for Display | ||
| 70 | NW_PRIO | Priority | ||
| 71 | OTEXT | Object Type Text | ||
| 72 | OWAERS | Object currency for network activity | ||
| 73 | POCACTCORRAGG1 | Adjusted aggregated actual POC | ||
| 74 | POCACTCORRNAGG1 | Adjusted non-aggregated actual percentage of completion | ||
| 75 | POCACTORGAGG1 | Aggregated actual POC | ||
| 76 | POCACTORGNAGG1 | Non-aggregated actual percentage of completion | ||
| 77 | POCPLANORGAGG1 | Aggregate planned percentage of completion | ||
| 78 | POCPLANORGNAGG1 | Non-aggregated planned percentage of completion | ||
| 79 | PPUFF_FREI | Free float (from forecast) | ||
| 80 | PPUFF_GESM | Total float (from forecast) | ||
| 81 | PROERLPLAN | Current project revenue plan | ||
| 82 | PROERLPLANOC | Current Project Revenue Plan in Object Currency | ||
| 83 | PROERLPLN2 | Project revenue plan (version 2) | ||
| 84 | PROERLPLN2OC | Project Revenue Plan (Version 2) in Object Currency | ||
| 85 | PROKSTPLAN | Current project cost plan | ||
| 86 | PROKSTPLANOC | Current Project Cost Plan in Object Currency | ||
| 87 | PROKSTPLN2 | Project cost plan (version 2) | ||
| 88 | PROKSTPLN2OC | Project Cost Plan (Version 2) in Object Currency | ||
| 89 | PS_ABARBA | Percent of completion for work | ||
| 90 | PS_ABARBD | Processing % of duration | ||
| 91 | PS_ARBEH | Unit for work | ||
| 92 | PS_ARBEH | Unit for work | ||
| 93 | PS_ARBEH | Unit for work | ||
| 94 | PS_ARBEH | Unit for work | ||
| 95 | PS_ARBEH | Unit for work | ||
| 96 | PS_DATFS | Earliest start date | ||
| 97 | PS_DATSE | Latest finish date | ||
| 98 | PS_DAUEH | Actual duration unit | ||
| 99 | PS_DAUEH | Actual duration unit | ||
| 100 | PS_DAUEH | Actual duration unit | ||
| 101 | PS_DAUEH | Actual duration unit | ||
| 102 | PS_DAUEH | Actual duration unit | ||
| 103 | PS_EARBEI_2 | Work | ||
| 104 | PS_ECKEN | Finish date (from basic dates) | ||
| 105 | PS_ECKST | Basic start date | ||
| 106 | PS_EDAUER_2 | Duration | ||
| 107 | PS_ENTRY | Entry (line number on a list) | ||
| 108 | PS_IARBEI_VZ | Actual work | ||
| 109 | PS_IDAUER_VZ | Actual duration | ||
| 110 | PS_ISTEN | Actual finish date | ||
| 111 | PS_ISTST | Actual start date | ||
| 112 | PS_IS_ID | ID/Object key | ||
| 113 | PS_PARBEI_VZ | Forecast work | ||
| 114 | PS_PDAUER_VZ | Forecast duration | ||
| 115 | PS_PROGEN | Forecast finish date | ||
| 116 | PS_PROGST | Forecast start date | ||
| 117 | PS_RARBEI_VZ | Remaining work | ||
| 118 | PS_RDAUER_VZ | Remaining duration | ||
| 119 | PS_TEENFR | Earliest scheduled finish (from basic dates) | ||
| 120 | PS_TEENSP | Latest scheduled finish (from basic dates) | ||
| 121 | PS_TESTFR | Earliest scheduled start (from basic dates) | ||
| 122 | PS_TESTSP | Latest scheduled start (from basic dates) | ||
| 123 | PS_TPENFR | Earliest scheduled finish (from forecast dates) | ||
| 124 | PS_TPENSP | Latest scheduled finish (from forecast dates) | ||
| 125 | PS_TPSTFR | Earliest scheduled start (from forecast dates) | ||
| 126 | PS_TPSTSP | Latest scheduled start (from forecast dates) | ||
| 127 | PS_VARBEI_VZ | Tentative work | ||
| 128 | PS_VDAUER_VZ | Tentative duration | ||
| 129 | PS_VERNA | Name of responsible person (Project manager) | ||
| 130 | PS_VERNR_C | Number of responsible person (project mgr)/MRP controller | ||
| 131 | PS_VORLEN | Tentative finish date | ||
| 132 | PS_VORLST | Tentative start date | ||
| 133 | PUFFR_FREI | Free float | ||
| 134 | PUFFR_GESM | Total float | ||
| 135 | SLWID | Key word ID for user-defined fields | ||
| 136 | SPAETER_2 | Actual Finish/Planned Finish After Latest Scheduled Finish | ||
| 137 | STATUSTEXT_2 | Edited status text | ||
| 138 | TABNAME | Table Name | ||
| 139 | USRCHAR10 | User field with 10 characters | ||
| 140 | USRCHAR10 | User field with 10 characters | ||
| 141 | USRCHAR20 | User field with 20 characters | ||
| 142 | USRCHAR20 | User field with 20 characters | ||
| 143 | USRCUKY | User field: Unit for value fields | ||
| 144 | USRCUKY | User field: Unit for value fields | ||
| 145 | USRCURR13 | User-defined field for values (length 10,3) | ||
| 146 | USRCURR13 | User-defined field for values (length 10,3) | ||
| 147 | USRDATE | User field for date | ||
| 148 | USRDATE | User field for date | ||
| 149 | USRFLAG | User-defined field: Indicator for reports | ||
| 150 | USRFLAG | User-defined field: Indicator for reports | ||
| 151 | USRQUAN13 | User field for quantity (length 10.3) | ||
| 152 | USRQUAN13 | User field for quantity (length 10.3) | ||
| 153 | USRUNIT | User field: Unit for quantity fields | ||
| 154 | USRUNIT | User field: Unit for quantity fields | ||
| 155 | VERZUG_2 | Duration After Latest Scheduled Finish | ||
| 156 | VERZ_EINHT | Unit for Duration of the Delay | ||
| 157 | VORBEI_2 | Duration After Earliest Scheduled Start | ||
| 158 | VSGRUPPE | Group for a project version | ||
| 159 | VSNMR | Number or description of a version | ||
| 160 | WAERS | Currency Key | ||
| 161 | WERKS_D | Plant | ||
| 162 | WFCID | Factory Calendar |