Data Element list used by SAP ABAP Table SPSINFO_FC101 (Structure for Project Structure Overview Reporting)
SAP ABAP Table
SPSINFO_FC101 (Structure for Project Structure Overview Reporting) is using
# | Object Type | Object Name | Object Description | Note |
---|---|---|---|---|
![]() |
![]() |
|||
1 | ![]() |
ADMI_RUN_D | Archiving Session Number | |
2 | ![]() |
AENNR | Change Number | |
3 | ![]() |
ARBPL | Work center | |
4 | ![]() |
AUFERLPLAN | Current order revenue plan | |
5 | ![]() |
AUFERLPLANOC | Current Order Revenue Plan in Object Currency | |
6 | ![]() |
AUFERLPLN2 | Order revenue plan (version 2) | |
7 | ![]() |
AUFERLPLN2OC | Order Revenue Plan (Version 2) in Object Currency | |
8 | ![]() |
AUFKSTPLAN | Current order cost plan | |
9 | ![]() |
AUFKSTPLANOC | Current Order Cost Plan in Object Currency | |
10 | ![]() |
AUFKSTPLN2 | Order cost plan (version 2) | |
11 | ![]() |
AUFKSTPLN2OC | Order Cost Plan (Version 2) in Object Currency | |
12 | ![]() |
AUFTRANF | Residual order plan | |
13 | ![]() |
AUFTRANFOC | Residual Order Plan in Object Currency | |
14 | ![]() |
BUDGET | Budget of a Measure (App. Request Variant Was Replaced) | |
15 | ![]() |
BUDGETOC | Appropriation Budget (Appr.Request Variant Replaced) in OC | |
16 | ![]() |
BUKRS | Company Code | |
17 | ![]() |
DEBFINPLN | Current cash budget, debit side | |
18 | ![]() |
DEBFINPLNOC | Current Debit Side Cash Budget in Object Currency | |
19 | ![]() |
DZHLNG | Total debit side payments (down payments and payments) | |
20 | ![]() |
DZHLNGOC | Total Customer Payments (Down Payments and Payments) OC | |
21 | ![]() |
EVACTCORR1 | Budgeted cost of work performed, adjusted | |
22 | ![]() |
EVACTCORR1 | Budgeted cost of work performed, adjusted | |
23 | ![]() |
EVACTORG1 | Budgeted cost of work performed | |
24 | ![]() |
EVACTORG1 | Budgeted cost of work performed | |
25 | ![]() |
EVACTQUANCORR1 | Budgeted cost of work performed, adjusted quantity | |
26 | ![]() |
EVACTQUANORG1 | Budgeted cost of work performed, quantity | |
27 | ![]() |
EVPLANORG1 | Budgeted cost of work scheduled | |
28 | ![]() |
EVPLANORG1 | Budgeted cost of work scheduled | |
29 | ![]() |
EVPLANQUANORG1 | Budgeted cost of work scheduled, quantity | |
30 | ![]() |
EVSCHINDXCORR | Date Index Based on POC_ACT_CORR_AGG1 | |
31 | ![]() |
EVSCHINDXORG | Date Index Based on POC_ACT_ORG_AGG1 | |
32 | ![]() |
EVSCHVARCORR | Schedule Variance Based on EV_ACT_CORR1 | |
33 | ![]() |
EVSCHVARCORR | Schedule Variance Based on EV_ACT_CORR1 | |
34 | ![]() |
EVSCHVARORG | Schedule Variance Based on EV_ACT_ORG1 | |
35 | ![]() |
EVSCHVARORG | Schedule Variance Based on EV_ACT_ORG1 | |
36 | ![]() |
EV_ACT_QUAN_CORR1_UNIT | BCWP, Adjusted Quantity (Unit) | |
37 | ![]() |
EV_ACT_QUAN_ORG1_UNIT | BCWP, Unit of Measure | |
38 | ![]() |
EV_METHOD_ACT | Measurement method in PS progress analysis (actual) | |
39 | ![]() |
EV_METHOD_PLN | Measurement method for PS progress analysis (plan) | |
40 | ![]() |
EV_PLAN_QUAN_ORG1_UNIT | BCWS, Unit of Measure | |
41 | ![]() |
EV_WEIGHTD | Aggregation weight for POC (PS progress) | |
42 | ![]() |
EWALINDXCORR | Cost Index Based on EV_ACT_CORR1 | |
43 | ![]() |
EWALINDXORG | Cost Index Based on EV_ACT_ORG1 | |
44 | ![]() |
EWALVARCORR | Cost Variance Based on EV_ACT_CORR1 | |
45 | ![]() |
EWALVARCORR | Cost Variance Based on EV_ACT_CORR1 | |
46 | ![]() |
EWALVARORG | Cost Variance Based on EV_ACT_ORG1 | |
47 | ![]() |
EWALVARORG | Cost Variance Based on EV_ACT_ORG1 | |
48 | ![]() |
FESTPROBL | Fixed price commitment | |
49 | ![]() |
FESTPROBLOC | Fixed Price Commitment in Object Currency | |
50 | ![]() |
FREIGABE | Release | |
51 | ![]() |
FREIGABEOC | Release in Object Currency | |
52 | ![]() |
FRUEHER_2 | Actual start is before earliest scheduled start | |
53 | ![]() |
GSBER | Business Area | |
54 | ![]() |
HIERSTUFE | Classification: Level in Hierarchy | |
55 | ![]() |
ISTERLOESE | Actual revenues | |
56 | ![]() |
ISTERLOESEOC | Actual Revenues in Object Currency | |
57 | ![]() |
ISTKOSTEN | Actual costs | |
58 | ![]() |
ISTKOSTENOC | Act. Costs in Object Currency | |
59 | ![]() |
J_OBJNR | Object number | |
60 | ![]() |
KOKRS | Controlling Area | |
61 | ![]() |
KREDFINPLN | Current financial budget, credit side | |
62 | ![]() |
KREDFINPLNOC | Current Credit Side Cash Budget in Object Currency | |
63 | ![]() |
KSTOBLGES | Total cost commitment | |
64 | ![]() |
KSTOBLGESOC | Total Cost Commitment in Object Currency | |
65 | ![]() |
KURZTEXT | Short text/description of the object | |
66 | ![]() |
KZHLNG | Total credit side payments (down payments and payments) | |
67 | ![]() |
KZHLNGOC | Total Vendor Payments (Down Payments and Payments) OC | |
68 | ![]() |
LTXSP | Language: The long text was stored in this language | |
69 | ![]() |
MEINH | Unit of Measure for Display | |
70 | ![]() |
NW_PRIO | Priority | |
71 | ![]() |
OTEXT | Object Type Text | |
72 | ![]() |
OWAERS | Object currency for network activity | |
73 | ![]() |
POCACTCORRAGG1 | Adjusted aggregated actual POC | |
74 | ![]() |
POCACTCORRNAGG1 | Adjusted non-aggregated actual percentage of completion | |
75 | ![]() |
POCACTORGAGG1 | Aggregated actual POC | |
76 | ![]() |
POCACTORGNAGG1 | Non-aggregated actual percentage of completion | |
77 | ![]() |
POCPLANORGAGG1 | Aggregate planned percentage of completion | |
78 | ![]() |
POCPLANORGNAGG1 | Non-aggregated planned percentage of completion | |
79 | ![]() |
PPUFF_FREI | Free float (from forecast) | |
80 | ![]() |
PPUFF_GESM | Total float (from forecast) | |
81 | ![]() |
PROERLPLAN | Current project revenue plan | |
82 | ![]() |
PROERLPLANOC | Current Project Revenue Plan in Object Currency | |
83 | ![]() |
PROERLPLN2 | Project revenue plan (version 2) | |
84 | ![]() |
PROERLPLN2OC | Project Revenue Plan (Version 2) in Object Currency | |
85 | ![]() |
PROKSTPLAN | Current project cost plan | |
86 | ![]() |
PROKSTPLANOC | Current Project Cost Plan in Object Currency | |
87 | ![]() |
PROKSTPLN2 | Project cost plan (version 2) | |
88 | ![]() |
PROKSTPLN2OC | Project Cost Plan (Version 2) in Object Currency | |
89 | ![]() |
PS_ABARBA | Percent of completion for work | |
90 | ![]() |
PS_ABARBD | Processing % of duration | |
91 | ![]() |
PS_ARBEH | Unit for work | |
92 | ![]() |
PS_ARBEH | Unit for work | |
93 | ![]() |
PS_ARBEH | Unit for work | |
94 | ![]() |
PS_ARBEH | Unit for work | |
95 | ![]() |
PS_ARBEH | Unit for work | |
96 | ![]() |
PS_DATFS | Earliest start date | |
97 | ![]() |
PS_DATSE | Latest finish date | |
98 | ![]() |
PS_DAUEH | Actual duration unit | |
99 | ![]() |
PS_DAUEH | Actual duration unit | |
100 | ![]() |
PS_DAUEH | Actual duration unit | |
101 | ![]() |
PS_DAUEH | Actual duration unit | |
102 | ![]() |
PS_DAUEH | Actual duration unit | |
103 | ![]() |
PS_EARBEI_2 | Work | |
104 | ![]() |
PS_ECKEN | Finish date (from basic dates) | |
105 | ![]() |
PS_ECKST | Basic start date | |
106 | ![]() |
PS_EDAUER_2 | Duration | |
107 | ![]() |
PS_ENTRY | Entry (line number on a list) | |
108 | ![]() |
PS_IARBEI_VZ | Actual work | |
109 | ![]() |
PS_IDAUER_VZ | Actual duration | |
110 | ![]() |
PS_ISTEN | Actual finish date | |
111 | ![]() |
PS_ISTST | Actual start date | |
112 | ![]() |
PS_IS_ID | ID/Object key | |
113 | ![]() |
PS_PARBEI_VZ | Forecast work | |
114 | ![]() |
PS_PDAUER_VZ | Forecast duration | |
115 | ![]() |
PS_PROGEN | Forecast finish date | |
116 | ![]() |
PS_PROGST | Forecast start date | |
117 | ![]() |
PS_RARBEI_VZ | Remaining work | |
118 | ![]() |
PS_RDAUER_VZ | Remaining duration | |
119 | ![]() |
PS_TEENFR | Earliest scheduled finish (from basic dates) | |
120 | ![]() |
PS_TEENSP | Latest scheduled finish (from basic dates) | |
121 | ![]() |
PS_TESTFR | Earliest scheduled start (from basic dates) | |
122 | ![]() |
PS_TESTSP | Latest scheduled start (from basic dates) | |
123 | ![]() |
PS_TPENFR | Earliest scheduled finish (from forecast dates) | |
124 | ![]() |
PS_TPENSP | Latest scheduled finish (from forecast dates) | |
125 | ![]() |
PS_TPSTFR | Earliest scheduled start (from forecast dates) | |
126 | ![]() |
PS_TPSTSP | Latest scheduled start (from forecast dates) | |
127 | ![]() |
PS_VARBEI_VZ | Tentative work | |
128 | ![]() |
PS_VDAUER_VZ | Tentative duration | |
129 | ![]() |
PS_VERNA | Name of responsible person (Project manager) | |
130 | ![]() |
PS_VERNR_C | Number of responsible person (project mgr)/MRP controller | |
131 | ![]() |
PS_VORLEN | Tentative finish date | |
132 | ![]() |
PS_VORLST | Tentative start date | |
133 | ![]() |
PUFFR_FREI | Free float | |
134 | ![]() |
PUFFR_GESM | Total float | |
135 | ![]() |
SLWID | Key word ID for user-defined fields | |
136 | ![]() |
SPAETER_2 | Actual Finish/Planned Finish After Latest Scheduled Finish | |
137 | ![]() |
STATUSTEXT_2 | Edited status text | |
138 | ![]() |
TABNAME | Table Name | |
139 | ![]() |
USRCHAR10 | User field with 10 characters | |
140 | ![]() |
USRCHAR10 | User field with 10 characters | |
141 | ![]() |
USRCHAR20 | User field with 20 characters | |
142 | ![]() |
USRCHAR20 | User field with 20 characters | |
143 | ![]() |
USRCUKY | User field: Unit for value fields | |
144 | ![]() |
USRCUKY | User field: Unit for value fields | |
145 | ![]() |
USRCURR13 | User-defined field for values (length 10,3) | |
146 | ![]() |
USRCURR13 | User-defined field for values (length 10,3) | |
147 | ![]() |
USRDATE | User field for date | |
148 | ![]() |
USRDATE | User field for date | |
149 | ![]() |
USRFLAG | User-defined field: Indicator for reports | |
150 | ![]() |
USRFLAG | User-defined field: Indicator for reports | |
151 | ![]() |
USRQUAN13 | User field for quantity (length 10.3) | |
152 | ![]() |
USRQUAN13 | User field for quantity (length 10.3) | |
153 | ![]() |
USRUNIT | User field: Unit for quantity fields | |
154 | ![]() |
USRUNIT | User field: Unit for quantity fields | |
155 | ![]() |
VERZUG_2 | Duration After Latest Scheduled Finish | |
156 | ![]() |
VERZ_EINHT | Unit for Duration of the Delay | |
157 | ![]() |
VORBEI_2 | Duration After Earliest Scheduled Start | |
158 | ![]() |
VSGRUPPE | Group for a project version | |
159 | ![]() |
VSNMR | Number or description of a version | |
160 | ![]() |
WAERS | Currency Key | |
161 | ![]() |
WERKS_D | Plant | |
162 | ![]() |
WFCID | Factory Calendar |