Data Element list used by SAP ABAP Table RECONST_ACT (Order Activity Structure for Project Reporting)
SAP ABAP Table
RECONST_ACT (Order Activity Structure for Project Reporting) is using
| # | Object Type | Object Name | Object Description | Note |
|---|---|---|---|---|
| 1 | AFNAM | Name of requisitioner/requester | ||
| 2 | ANFKO | Requesting cost center | ||
| 3 | ANFKOKRS | Controlling area of the requesting cost center | ||
| 4 | ANZKAP | Number of capacities required | ||
| 5 | APROZENT | Work percentage | ||
| 6 | ARBEIT | Work involved in the activity | ||
| 7 | ARBEITE | Unit for work | ||
| 8 | ARBEITE | Unit for work | ||
| 9 | ARBPL | Work center | ||
| 10 | ASVRG | Operation scrap | ||
| 11 | AUDISP | Ind: Reservation applicable to MRP;Purc. req. is created | ||
| 12 | AUF_NETNR | Order/Network number | ||
| 13 | AUTYPTEXT | Display field for order category description | ||
| 14 | BEAZE | Unit of measure for processing time | ||
| 15 | BEAZEP | Unit of processing time (Forecast) | ||
| 16 | BSTME | Order unit | ||
| 17 | BUKRS | Company Code | ||
| 18 | CIM_COUNT | Internal counter | ||
| 19 | CK_KALNR | Cost Estimate Number for Cost Est. w/o Qty Structure | ||
| 20 | CK_KLVAR | Costing Variant | ||
| 21 | CN_ELEMENT | Activity element number (work/external/general costs) | ||
| 22 | CN_KZFIX | Indicator: Purchasing info record data are fixed | ||
| 23 | CN_VORNR | Activity number in network and standard network | ||
| 24 | CO_ABARB | Confirmation: Degree of processing | ||
| 25 | CO_ABARB | Confirmation: Degree of processing | ||
| 26 | CO_BANFN | Purchase requisition number | ||
| 27 | CO_BNFPO | Item number of the purchase requisition in the order | ||
| 28 | CO_DAUBEA | Processing time | ||
| 29 | CO_DAUBEAP | Duration of processing time (forecast) | ||
| 30 | CO_LEIKZ | Indicator: No remaining activity expected | ||
| 31 | CO_PEDD | Forecast finish date of operation from confirmation | ||
| 32 | CO_PEDZ | Forecast finish time of operation from confirmation | ||
| 33 | CO_PERNR | Personnel number | ||
| 34 | CO_PRZNR | Business Process | ||
| 35 | CO_RUECK | Completion confirmation number for the operation | ||
| 36 | CP_OEHOFFB | Unit for offset to start | ||
| 37 | CP_OEHOFFE | Unit for offset to finish | ||
| 38 | CP_OOFFSTB | Offset to sub-operation start | ||
| 39 | CP_OOFFSTE | Offset to sub-operation finish | ||
| 40 | CR_VERTN | Distr.cap.reqmts (plant maint.,process order, network) | ||
| 41 | DAUDEHN | Indicator: flexible duration | ||
| 42 | DAUMIN | Minimum activity duration | ||
| 43 | DAUMINE | Unit for the minimum duration | ||
| 44 | DAUNOR | Normal duration of the activity | ||
| 45 | DAUNORE | Normal duration/unit | ||
| 46 | EINSCHRA | Constraint on the basic start date for the activity | ||
| 47 | EINSCHRE | Constraint on the finish date of the activity | ||
| 48 | EKORG | Purchasing organization | ||
| 49 | EPANF | Dispatched start date for operation | ||
| 50 | EPANZ | Dispatched start time for operation | ||
| 51 | EPEND | Dispatched finish date | ||
| 52 | EPENZ | Dispatched finish time | ||
| 53 | ESOKZ | Purchasing info record category | ||
| 54 | EWDAM | Minimum duration (from forecast) for activity | ||
| 55 | EWDAN | Normal duration (from forecast) of activity | ||
| 56 | EWDME | Unit for forecast minimum duration | ||
| 57 | EWDNE | Unit for forecast normal duration | ||
| 58 | EWENDED | Forecast finish date | ||
| 59 | EWENDEZ | Forecast finish time for the activity | ||
| 60 | EWSTARTD | Forecasted start date for the activity | ||
| 61 | EWSTARTZ | Forecast start time of the activity | ||
| 62 | FLG_PURS | Indicator: Purchase order exists | ||
| 63 | FPAVD | Earliest scheduled start date (forecast) | ||
| 64 | FPAVZ | Earliest scheduled start time (forecast) | ||
| 65 | FPEDD | Earliest scheduled finish date (forecast) | ||
| 66 | FPEDZ | Earliest scheduled finish time (forecast) | ||
| 67 | FPLNR | Billing plan number / invoicing plan number | ||
| 68 | FSAVD | Earliest scheduled start: Execution (date) | ||
| 69 | FSAVZ | Earliest scheduled start: Execution (time) | ||
| 70 | FSEDD | Earliest scheduled finish: Execution (date) | ||
| 71 | FSEDZ | Earliest scheduled finish: Execution (time) | ||
| 72 | GSBER | Business Area | ||
| 73 | IDAURE | Unit for actual duration | ||
| 74 | IEDD | Actual finish: Execution (date) | ||
| 75 | IEDZ | Actual finish: Execution (time) | ||
| 76 | INDET | Calculation key | ||
| 77 | INFNR | Number of purchasing info record | ||
| 78 | ISDD | Actual start: Execution (date) | ||
| 79 | ISDZ | Actual start: Execution/setup (time) | ||
| 80 | ISMNW | Actual work | ||
| 81 | KSTAR | Cost Element | ||
| 82 | KTSCH | Standard text key | ||
| 83 | KZLGF | Indicator: fixed lot external processing | ||
| 84 | KZWRTF | Indicator: Fixed price for external processing | ||
| 85 | LIFNR | Account Number of Vendor or Creditor | ||
| 86 | LSTAR | Activity Type | ||
| 87 | LTXA1 | Operation short text | ||
| 88 | MATKL | Material Group | ||
| 89 | MGVRG | Operation Quantity | ||
| 90 | MILESTONE | Usage | ||
| 91 | NW_PRIO | Priority | ||
| 92 | ODAUE | Unit for remaining duration | ||
| 93 | ODAUR | Remaining duration of activity | ||
| 94 | OFMNW | Forecasted work (actual + remaining) | ||
| 95 | OWAERS | Object currency for network activity | ||
| 96 | PDAE | Unit of the forecasted duration from the confirmation | ||
| 97 | PDAU | Forecasted duration of activity from confirmation | ||
| 98 | PLIFZ | Planned delivery time in days | ||
| 99 | POSNR_VA | Sales Document Item | ||
| 100 | PPUFF_FREI | Free float (from forecast) | ||
| 101 | PPUFF_GESM | Total float (from forecast) | ||
| 102 | PREIS | Price | ||
| 103 | PRKST | Costs in the activity | ||
| 104 | PS_ARBTEXT | Short text for the CIM operating resource | ||
| 105 | PS_MLSTTXT | Milestone description | ||
| 106 | PS_RCKMLDB | Indicator: Can be confirmed | ||
| 107 | PS_RESTA | Forecast date constraint on activity start | ||
| 108 | PS_RESTE | Forecast date constraint on activity finish | ||
| 109 | PUFFR_FREI | Free float | ||
| 110 | PUFFR_GESM | Total float | ||
| 111 | REMNW | Remaining work | ||
| 112 | SORTI | Sort Term for Non-Stock Info Records | ||
| 113 | SPAVD | Latest scheduled start date (forecast) | ||
| 114 | SPAVZ | Latest scheduled start time (forecast) | ||
| 115 | SPEDD | Latest scheduled finish date (forecast) | ||
| 116 | SPEDZ | Latest scheduled finish time (forecast) | ||
| 117 | SSAVD | Latest scheduled start: Execution (date) | ||
| 118 | SSAVZ | Latest scheduled start: Execution (time) | ||
| 119 | SSEDD | Latest scheduled finish: Execution (date) | ||
| 120 | SSEDZ | Latest scheduled finish: Execution (time) | ||
| 121 | STEUS | Control key | ||
| 122 | STEUTXT | Control key description | ||
| 123 | VBELN_VA | Sales Document | ||
| 124 | VGTYP | Activity or element category | ||
| 125 | VG_EKGRP | Purchasing group for external processing | ||
| 126 | VORGABEEND | Constraint for finish of activity (Basic) | ||
| 127 | VORGABEENZ | Basic finish time of the activity | ||
| 128 | VORGABESTD | Constraint for activity start (Basic) | ||
| 129 | VORGABESTZ | Constraint for activity start time (Basic) | ||
| 130 | VORME | Unit of measure for activity | ||
| 131 | WAERS | Currency Key | ||
| 132 | WEMNG | Quantity of goods received | ||
| 133 | WKURS | Exchange Rate |