SAP ABAP Data Element FSEDZ (Earliest scheduled finish: Execution (time))
Hierarchy
☛
SAP_ABA (Software Component) Cross-Application Component
⤷ CA-GTF-PS (Application Component) Cross-Application Objects in Project System
⤷ BC (Package) Cross-Application Objects PP/PS
⤷ CA-GTF-PS (Application Component) Cross-Application Objects in Project System
⤷ BC (Package) Cross-Application Objects PP/PS
Basic Data
Data Element | FSEDZ |
Short Description | Earliest scheduled finish: Execution (time) |
Data Type
Category of Dictionary Type | D | Domain |
Type of Object Referenced | No Information | |
Domain / Name of Reference Type | ATIME | |
Data Type | TIMS | Time field (hhmmss), stored as char(6) |
Length | 6 | |
Decimal Places | 0 | |
Output Length | 8 | |
Value Table |
Further Characteristics
Search Help: Name | ||
Search Help: Parameters | ||
Parameter ID | ||
Default Component name | ||
Change document | ||
No Input History | ||
Basic direction is set to LTR | ||
No BIDI Filtering |
Field Label
Length | Field Label | |
Short | 10 | Earl. fin. |
Medium | 15 | Earliest finish |
Long | 20 | Earliest finish time |
Heading | 15 | Earliest finish |
Documentation
Definition
Earliest time at which the execution of the operation or activity (PS) can finish.
Supplementary Documentation - FSEDZ 0001
Use
The execution time of the operation is made up of a setup time, a processing time and a teardown time.
If the execution of the operation is carried out immediately (that is without making use of the queue time), then all operation segments are carried out on the earliest possible date.
Dependencies
This date is determined via lead time scheduling.
History
Last changed by/on | SAP | 19990629 |