SAP ABAP Table INM_TS_PS_NA_SYN_O (Modifiable PS NA Attributes for Export)
Hierarchy
CPRXRPM (Software Component) SAP Portfolio and Project Management 6.0
   PPM-CF (Application Component) Common Functions
     INM_OBJECTS (Package) Implementation of Object Framework
Basic Data
Table Category INTTAB    Structure 
Structure INM_TS_PS_NA_SYN_O   Table Relationship Diagram
Short Description Modifiable PS NA Attributes for Export    
Delivery and Maintenance
Pool/cluster      
Delivery Class      
Data Browser/Table View Maintenance     Display/Maintenance Allowed with Restrictions 
Components
     
Field Key Data Element Domain Data
Type
Length Decimal
Places
Short Description Check
table
1 .INCLUDE       0   0   Data Structure: Activity GetData  
2 NETWORK NW_AUFNR AUFNR CHAR 12   0   Network number *
3 ACTIVITY CN_VORNR VORNR CHAR 4   0   Activity number in network and standard network  
4 DESCRIPTION LTXA1 TEXT40 CHAR 40   0   Operation short text  
5 PROJECT_DEFINITION PS_PSPID PS_PSPID CHAR 24   0   Project definition  
6 WBS_ELEMENT PS_POSID PS_POSID CHAR 24   0   Work Breakdown Structure Element (WBS Element)  
7 CONTROL_KEY STEUS STEUS CHAR 4   0   Control key *
8 PLANT WERKS_D WERKS CHAR 4   0   Plant *
9 WORK_CNTR ARBPL ARBPL CHAR 8   0   Work center  
10 WORK_ACTIVITY ARBEIT ARBEIT QUAN 7   1   Work involved in the activity  
11 WORK_UNIT ARBEITE MEINS UNIT 3   0   Unit for work *
12 WORK_UNIT_ISO ISOCD_UNIT ISOCD_UNIT CHAR 3   0   ISO code for unit of measurement *
13 CALCULATION_KEY     CHAR 1   0    
14 ACTTYPE LSTAR LSTAR CHAR 6   0   Activity Type *
15 PRIORITY NW_PRIO NW_PRIO CHAR 1   0   Priority *
16 MILESTONE MILESTONE MILESTONE CHAR 5   0   Usage *
17 DISTRIBUTION_KEY CR_VERTN CR_VERTL CHAR 8   0   Distr.cap.reqmts (plant maint.,process order, network) *
18 NUMBER_OF_CAPACITIES ANZKAP INT1 INT1 3   0   Number of capacities required  
19 PERCENT_OF_WORK APROZENT INT1 INT1 3   0   Work percentage  
20 EXEC_FACTOR     DEC 3   0    
21 BUSINESS_PROCESS CO_PRZNR CO_PRZNR CHAR 12   0   Business Process *
22 STD_TEXT_KEY     CHAR 7   0    
23 SUBNETWORK_EXISTS     CHAR 1   0    
24 PROJECT_SUMMARIZATION CLASF XFELD CHAR 1   0   Ind.: Take Activity Into Account for Project Summarization  
25 SYSTEM_STATUS J_TXT04 TEXT4 CHAR 4   0   Individual status of an object (short form)  
26 LANGU SPRAS SPRAS LANG 1   0   Language Key *
27 LANGU_ISO LAISO LAISO CHAR 2   0   2-Character SAP Language Code  
28 DURATION_NORMAL DAUNOR DAUER_4_1 QUAN 5   1   Normal duration of the activity  
29 DURATION_NORMAL_UNIT DAUNORE MEINS UNIT 3   0   Normal duration/unit *
30 DURATION_NORMAL_UNIT_ISO ISOCD_UNIT ISOCD_UNIT CHAR 3   0   ISO code for unit of measurement *
31 DURATION_MINIMUM DAUMIN DAUER_4_1 QUAN 5   1   Minimum activity duration  
32 DURATION_MINIMUM_UNIT DAUMINE MEINS UNIT 3   0   Unit for the minimum duration *
33 DURATION_MINIMUM_UNIT_ISO ISOCD_UNIT ISOCD_UNIT CHAR 3   0   ISO code for unit of measurement *
34 FLEXIBLE_DURATION DAUDEHN X CHAR 1   0   Indicator: flexible duration  
35 FACTORY_CALENDAR WFCID WFCID CHAR 2   0   Factory Calendar *
36 REDUCTION_STRATEGY     CHAR 2   0    
37 INFO_REC INFNR INFNR CHAR 10   0   Number of purchasing info record *
38 VENDOR_NO LIFNR LIFNR CHAR 10   0   Account Number of Vendor or Creditor *
39 PURCH_ORG EKORG EKORG CHAR 4   0   Purchasing organization *
40 PUR_GROUP EKGRP EKGRP CHAR 3   0   Purchasing group *
41 MATL_GROUP MATKL MATKL CHAR 9   0   Material Group *
42 AGREEMENT KONNR EBELN CHAR 10   0   Number of principal purchase agreement *
43 AGMT_ITEM KTPNR EBELP NUMC 5   0   Item number of principal purchase agreement *
44 PRICE PREIS WERT11 CURR 11   2   Price  
45 PRICE_UNIT PEINH PACK3 DEC 5   0   Price unit  
46 CURRENCY WAERS WAERS CUKY 5   0   Currency Key *
47 CURRENCY_ISO ISOCD ISOCD CHAR 3   0   ISO currency code  
48 COST_ELEM KSTAR KSTAR CHAR 10   0   Cost Element *
49 PUR_INFO_RECORD_DATA_FIXED     CHAR 1   0    
50 PLND_DELRY PLIFZ DEC3 DEC 3   0   Planned delivery time in days  
51 OPERATION_QTY     QUAN 13   3    
52 OPERATION_MEASURE_UNIT VORME MEINS UNIT 3   0   Unit of measure for activity *
53 OPERATION_MEASURE_UNIT_ISO ISOCD_UNIT ISOCD_UNIT CHAR 3   0   ISO code for unit of measurement *
54 NOT_MRP_APPLICABLE NODISP XFELD CHAR 1   0   Ind: Reserv. not applicable to MRP;Purc. req. not created  
55 SORTED_BY     CHAR 10   0    
56 PREQ_NAME AFNAM AFNAM CHAR 12   0   Name of requisitioner/requester  
57 GR_RCPT WEMPF WEMPF CHAR 12   0   Goods recipient  
58 TRACKINGNO BEDNR CHAR10 CHAR 10   0   Requirement Tracking Number  
59 UNLOAD_PT ABLAD TEXT25 CHAR 25   0   Unloading Point  
60 GOODS_RECIEVED     QUAN 13   3    
61 PURCHASE_REQUISITION     CHAR 10   0    
62 PURCHASE_REQUISITION_ITEM     NUMC 5   0    
63 PURCHASE_ORDER_EXISTS     CHAR 1   0    
64 SERVICE_EXISTS     CHAR 1   0    
65 COMP_CODE BUKRS BUKRS CHAR 4   0   Company Code *
66 FUNC_AREA FKBER FKBER CHAR 16   0   Functional Area *
67 BUS_AREA GSBER GSBER CHAR 4   0   Business Area *
68 PROFIT_CTR PRCTR PRCTR CHAR 10   0   Profit Center *
69 CHANGE_NO AENNR AENNR CHAR 12   0   Change Number *
70 REFERENCE_POINT     CHAR 20   0    
71 CSTG_SHEET AUFKALSM KALSM CHAR 6   0   Costing Sheet *
72 OVERHEAD_KEY AUFZSCHL CHAR6 CHAR 6   0   Overhead key  
73 TAXJURCODE TXJCD TXJCD CHAR 15   0   Tax Jurisdiction *
74 OBJECTCLASS_EXT SCOPE_LD CHAR5 CHAR 5   0   Object class, language-dependent  
75 ACTIVITY_COSTS PRKST PRKST CURR 11   2   Costs in the activity  
76 OBJECT_CURRENCY     CUKY 5   0    
77 OBJECT_CURRENCY_ISO ISOCD ISOCD CHAR 3   0   ISO currency code  
78 REQ_COST_CENTER     CHAR 10   0    
79 CONSTRAINT_TYPE_START EINSCHRA RESTRIKSTR CHAR 1   0   Constraint on the basic start date for the activity  
80 CONSTRAINT_TYPE_FINISH EINSCHRE RESTRIKEND CHAR 1   0   Constraint on the finish date of the activity  
81 CONSTRAINT_START_DATE VORGABESTD VORGABESTR DATS 8   0   Constraint for activity start (Basic)  
82 CONSTRAINT_START_TIME VORGABESTZ ATIME TIMS 6   0   Constraint for activity start time (Basic)  
83 CONSTRAINT_FINISH_DATE VORGABEEND VORGABEEND DATS 8   0   Constraint for finish of activity (Basic)  
84 CONSTRAINT_FINISH_TIME VORGABEENZ ATIME TIMS 6   0   Basic finish time of the activity  
85 EARLY_START_DATE FSAVD DATUM DATS 8   0   Earliest scheduled start: Execution (date)  
86 EARLY_START_TIME FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
87 EARLY_FINISH_DATE FSEDD DATUM DATS 8   0   Earliest scheduled finish: Execution (date)  
88 EARLY_FINISH_TIME FSEDZ ATIME TIMS 6   0   Earliest scheduled finish: Execution (time)  
89 LATEST_START_DATE SSAVD DATUM DATS 8   0   Latest scheduled start: Execution (date)  
90 LATEST_START_TIME SSAVZ ATIME TIMS 6   0   Latest scheduled start: Execution (time)  
91 LATEST_FINISH_DATE SSEDD DATUM DATS 8   0   Latest scheduled finish: Execution (date)  
92 LATEST_FINISH_TIME SSEDZ ATIME TIMS 6   0   Latest scheduled finish: Execution (time)  
93 DURATION_SCHEDULED CO_DAUBEA DAUER_6_1 QUAN 7   1   Processing time  
94 DURATION_SCHEDULED_UNIT BEAZE EINHEIT UNIT 3   0   Unit of measure for processing time  
95 DURATION_SCHEDULED_UNIT_ISO ISOCD_UNIT ISOCD_UNIT CHAR 3   0   ISO code for unit of measurement *
96 FLOAT_FREE PUFFR_FREI PUFFER DEC 3   0   Free float  
97 FLOAT_TOTAL PUFFR_GESM PUFFER DEC 3   0   Total float  
98 WORK_ACTUAL CO_ISMNW MENG13 QUAN 13   3   Actual work  
99 ACTUAL_START_DATE     DATS 8   0    
100 ACTUAL_START_TIME     TIMS 6   0    
101 ACTUAL_FINISH_DATE     DATS 8   0    
102 ACTUAL_FINISH_TIME     TIMS 6   0    
103 WORK_FORECAST OFMNW ARBEIT QUAN 7   1   Forecasted work (actual + remaining)  
104 FORECAST_DURATION PDAU DAUER_4_1 QUAN 5   1   Forecasted duration of activity from confirmation  
105 FORECAST_DURATION_UNIT PDAE MEINS UNIT 3   0   Unit of the forecasted duration from the confirmation *
106 FORECAST_DURATION_UNIT_ISO ISOCD_UNIT ISOCD_UNIT CHAR 3   0   ISO code for unit of measurement *
107 FORECAST_FINISH_DATE CO_PEDD DATUM DATS 8   0   Forecast finish date of operation from confirmation  
108 FORECAST_FINISH_TIME     TIMS 6   0    
109 DISPATCHED_START_DATE     DATS 8   0    
110 DISPATCHED_START_TIME     TIMS 6   0    
111 DISPATCHED_FINISH_DATE     DATS 8   0    
112 DISPATCHED_FINISH_TIME     TIMS 6   0    
113 CONSTRAINT_TYPE_FINISH_FC PS_RESTE RESTRIKEND CHAR 1   0   Forecast date constraint on activity finish  
114 CONSTRAINT_TYPE_START_FC PS_RESTA RESTRIKSTR CHAR 1   0   Forecast date constraint on activity start  
115 CONSTRAINT_START_DATE_FC EWSTARTD DATUM DATS 8   0   Forecasted start date for the activity  
116 CONSTRAINT_START_TIME_FC EWSTARTZ ATIME TIMS 6   0   Forecast start time of the activity  
117 CONSTRAINT_FINISH_DATE_FC EWENDED DATUM DATS 8   0   Forecast finish date  
118 CONSTRAINT_FINISH_TIME_FC EWENDEZ ATIME TIMS 6   0   Forecast finish time for the activity  
119 DURATION_NORMAL_FC EWDAN DAUER_4_1 QUAN 5   1   Normal duration (from forecast) of activity  
120 DURATION_NORMAL_FC_UNIT EWDNE MEINS UNIT 3   0   Unit for forecast normal duration *
121 DURATION_NORMAL_FC_UNIT_ISO ISOCD_UNIT ISOCD_UNIT CHAR 3   0   ISO code for unit of measurement *
122 DURATION_MINIMUM_FC EWDAM DAUER_4_1 QUAN 5   1   Minimum duration (from forecast) for activity  
123 DURATION_MINIMUM_FC_UNIT EWDME MEINS UNIT 3   0   Unit for forecast minimum duration *
124 DURATION_MINIMUM_FC_UNIT_ISO ISOCD_UNIT ISOCD_UNIT CHAR 3   0   ISO code for unit of measurement *
125 EARLY_START_DATE_FC FPAVD DATUM DATS 8   0   Earliest scheduled start date (forecast)  
126 EARLY_START_TIME_FC FPAVZ ATIME TIMS 6   0   Earliest scheduled start time (forecast)  
127 EARLY_FINISH_DATE_FC FPEDD DATUM DATS 8   0   Earliest scheduled finish date (forecast)  
128 EARLY_FINISH_TIME_FC FPEDZ ATIME TIMS 6   0   Earliest scheduled finish time (forecast)  
129 LATEST_START_DATE_FC SPAVD DATUM DATS 8   0   Latest scheduled start date (forecast)  
130 LATEST_START_TIME_FC SPAVZ ATIME TIMS 6   0   Latest scheduled start time (forecast)  
131 LATEST_FINISH_DATE_FC SPEDD DATUM DATS 8   0   Latest scheduled finish date (forecast)  
132 LATEST_FINISH_TIME_FC SPEDZ ATIME TIMS 6   0   Latest scheduled finish time (forecast)  
133 FLOAT_FREE_FC PPUFF_FREI PUFFER DEC 3   0   Free float (from forecast)  
134 FLOAT_TOTAL_FC PPUFF_GESM PUFFER DEC 3   0   Total float (from forecast)  
135 USER_FIELD_KEY SLWID SLWID CHAR 7   0   Key word ID for user-defined fields *
136 USER_FIELD_CHAR20_1 USRCHAR20 USRCHAR20 CHAR 20   0   User field with 20 characters  
137 USER_FIELD_CHAR20_2 USRCHAR20 USRCHAR20 CHAR 20   0   User field with 20 characters  
138 USER_FIELD_CHAR10_1 USRCHAR10 USRCHAR10 CHAR 10   0   User field with 10 characters  
139 USER_FIELD_CHAR10_2 USRCHAR10 USRCHAR10 CHAR 10   0   User field with 10 characters  
140 USER_FIELD_QUAN1 USRQUAN13 USRQUAN13 QUAN 13   3   User field for quantity (length 10.3)  
141 USER_FIELD_UNIT1 USRUNIT MEINS UNIT 3   0   User field: Unit for quantity fields *
142 USER_FIELD_UNIT1_ISO ISOCD_UNIT ISOCD_UNIT CHAR 3   0   ISO code for unit of measurement *
143 USER_FIELD_QUAN2 USRQUAN13 USRQUAN13 QUAN 13   3   User field for quantity (length 10.3)  
144 USER_FIELD_UNIT2 USRUNIT MEINS UNIT 3   0   User field: Unit for quantity fields *
145 USER_FIELD_UNIT2_ISO ISOCD_UNIT ISOCD_UNIT CHAR 3   0   ISO code for unit of measurement *
146 USER_FIELD_CURR1 USRCURR13 USRCURR13 CURR 13   3   User-defined field for values (length 10,3)  
147 USER_FIELD_CUKY1 USRCUKY WAERS CUKY 5   0   User field: Unit for value fields *
148 USER_FIELD_CUKY1_ISO ISOCD ISOCD CHAR 3   0   ISO currency code  
149 USER_FIELD_CURR2 USRCURR13 USRCURR13 CURR 13   3   User-defined field for values (length 10,3)  
150 USER_FIELD_CUKY2 USRCUKY WAERS CUKY 5   0   User field: Unit for value fields *
151 USER_FIELD_CUKY2_ISO ISOCD ISOCD CHAR 3   0   ISO currency code  
152 USER_FIELD_DATE1 USRDATE USRDATE DATS 8   0   User field for date  
153 USER_FIELD_DATE2 USRDATE USRDATE DATS 8   0   User field for date  
154 USER_FIELD_FLAG1 USRFLAG FLAG CHAR 1   0   User-defined field: Indicator for reports  
155 USER_FIELD_FLAG2 USRFLAG FLAG CHAR 1   0   User-defined field: Indicator for reports  
156 OBJECT_ID OBJEKTID NUM08 NUMC 8   0   Object ID  
157 CAPACITY_CATEGORY     CHAR 3   0    
158 CONFIRMATION_NUMBER CO_RUECK CO_RUECK NUMC 10   0   Completion confirmation number for the operation  
159 WAGE_TYPE LOHNART LOART CHAR 4   0   Wage type  
160 TIME_TICKETS     DEC 3   0    
161 CONFIRMATION_SLIPS     NUMC 3   0    
162 SUITABILITY     CHAR 2   0    
163 POC_AGGREGATION_WEIGHT     DEC 8   0    
164 STAT_PROF J_STSMA J_STSMA CHAR 8   0   Status Profile *
165 FORECAST_MATERIAL_COSTS     CURR 11   2    
166 .INCLUDE       0   0    
History
Last changed by/on SAP  20141109 
SAP Release Created in 500_702