SAP ABAP Data Element EINSCHRE (Constraint on the finish date of the activity)
Hierarchy
☛
SAP_ABA (Software Component) Cross-Application Component
⤷
CA-GTF-PS (Application Component) Cross-Application Objects in Project System
⤷
BC (Package) Cross-Application Objects PP/PS
⤷
⤷
Basic Data
| Data Element | EINSCHRE |
| Short Description | Constraint on the finish date of the activity |
Data Type
| Category of Dictionary Type | D | Domain |
| Type of Object Referenced | No Information | |
| Domain / Name of Reference Type | RESTRIKEND | |
| Data Type | CHAR | Character String |
| Length | 1 | |
| Decimal Places | 0 | |
| Output Length | 1 | |
| Value Table |
Further Characteristics
| Search Help: Name | ||
| Search Help: Parameters | ||
| Parameter ID | ||
| Default Component name | CONSTRAINT_TYPE_FINISH | |
| Change document | ||
| No Input History | ||
| Basic direction is set to LTR | ||
| No BIDI Filtering |
Field Label
| Length | Field Label | |
| Short | 10 | Fin. const |
| Medium | 15 | Fin. constraint |
| Long | 20 | Constraint on finish |
| Heading | 2 | FC |
Documentation
Definition
The key determines whether there is a scheduling constraint for the finish of an activity and what type the constraint is.
Supplementary Documentation - EINSCHRE 0001
Examples
- Activity must end on ...
- The activity should not end before ...
- The activity should not end later than ...
Supplementary Documentation - EINSCHRE 0002
Examples
- Activity must finish on ...
- The activity cannot finish before ...
- The activity cannot finish after ...
Supplementary Documentation - EINSCHRE 2330
Dependencies
When you maintain a key for a constraint, you must also maintain a date for it as well.
Supplementary Documentation - EINSCHRE 4100
Examples
- The activity must end on ...
- The activity should not end earlier than ...
- The activity should not end later than ...
History
| Last changed by/on | SAP | 19990629 |