Hierarchy
⤷ SRM-EBP (Application Component) Enterprise Buyer
⤷ CN (Package) R/3 Application development: PS Basic data
Basic Data
Data Element | AUDISP |
Short Description | Ind: Reservation applicable to MRP;Purc. req. is created |
Data Type
Category of Dictionary Type | D | Domain |
Type of Object Referenced | No Information | |
Domain / Name of Reference Type | XFELD | |
Data Type | CHAR | Character String |
Length | 1 | |
Decimal Places | 0 | |
Output Length | 1 | |
Value Table |
Further Characteristics
Search Help: Name | ||
Search Help: Parameters | ||
Parameter ID | ||
Default Component name | ||
Change document | ||
No Input History | ||
Basic direction is set to LTR | ||
No BIDI Filtering |
Field Label
Length | Field Label | |
Short | 10 | Res/PurcRq |
Medium | 15 | Res./Purc. req. |
Long | 20 | Reservation/Purc.req |
Heading | 8 | Res/PReq |
Documentation
Definition
Use this indicator to specify whether/when:
- Purchase requisitions are to be created for externally processed activities and external elements as well as for components.
- Component reservations are to be taken into account in MRP. If the indicator is set, this happens when the order is created, otherwise when the order is released.
Supplementary Documentation - AUDISP 0001
Dependencies
Note that you can not remove this indicator after you release the network header.
Note:
If this indicator is set in the network header, it is only a default for newly created activities or newly assigned material components.
This indicator has no effect on existing activities or components which you have already assigned. In these cases, set the indicator directly in the activity or the component.
Dependencies
If you do not set this indicator, materials planning will ignore reservations and will not create any purchase requisitions until you release the network.
To set all objects assigned to a WBS element, network or an activity as relevant for materials planning, proceed as follows:
In the network header select Edit -> Functions -> Activate PurcReq/Res.
Please note that response times will increase when you set this indicator.
Supplementary Documentation - AUDISP 0002
Dependencies
If you do not set this indicator, materials planning will ignore reservations and will not create any purchase requisitions until the network has status "released".
To set all objects assigned to a WBS element, network or activity as relevant for materials planning, proceed as follows:
- Call up the activity overview.
- Select Edit -> Functions -> Activate PurcReq/Reserv..
Note: response times will increase when you set this indicator.
Supplementary Documentation - AUDISP 0004
Use
Procedure
Examples
Dependencies
When you do not set this indicator, there are the following consequences:
Until you release the maintenance order or manually set the indicator:
- materials planning will ignore any reservations
- and will not create any purchase requisitions
Supplementary Documentation - AUDISP 0005
Use
Procedure
Examples
Dependencies
When you do not set this indicator, there are the following consequences:
Until you release the maintenance order or manually set the indicator:
- materials planning will ignore any reservations
- and will not create any purchase requisitions
Supplementary Documentation - AUDISP 2000
Dependencies
When you release an order or an operation, purchase requisitions are created for external operation and externally procurred components. Reservations for components in MRP are taken into account.
Supplementary Documentation - AUDISP_PLUS0010
Use
You can set this field for the entire network in the network header. However, you can manually activate the requirements for individual operations or components independently of this setting.
History
Last changed by/on | SAP | 19980617 |
SAP Release Created in |