Data Element list used by SAP ABAP Table PSHLP_TREX_ACTY_DATES_ST (Activity Dates structure for TREX)
SAP ABAP Table
PSHLP_TREX_ACTY_DATES_ST (Activity Dates structure for TREX) is using
| # | Object Type | Object Name | Object Description | Note |
|---|---|---|---|---|
| 1 | ABRUE | Teardown | ||
| 2 | AFAKT | Execution Factor | ||
| 3 | ARBEIT | Work involved in the activity | ||
| 4 | ARBEITE | Unit for work | ||
| 5 | ARUZE | Unit of measure for teardown | ||
| 6 | ASVRG | Operation scrap | ||
| 7 | BEARZEIT | Processing time | ||
| 8 | BEAZE | Unit of measure for processing time | ||
| 9 | BEAZEP | Unit of processing time (Forecast) | ||
| 10 | BMSCH | Base Quantity | ||
| 11 | CO_APLZL | General counter for order | ||
| 12 | CO_AUFPL | Routing number of operations in the order | ||
| 13 | CO_IPRZS | Confirmed quantity/work for business process | ||
| 14 | CO_ISMNGEH | Unit of measure for the activity to be confirmed | ||
| 15 | CO_ISMNGEH | Unit of measure for the activity to be confirmed | ||
| 16 | CO_ISMNGEH | Unit of measure for the activity to be confirmed | ||
| 17 | CO_ISMNGEH | Unit of measure for the activity to be confirmed | ||
| 18 | CO_ISMNGEH | Unit of measure for the activity to be confirmed | ||
| 19 | CO_ISMNGEH | Unit of measure for the activity to be confirmed | ||
| 20 | CO_ISMNW | Actual work | ||
| 21 | CO_PEDD | Forecast finish date of operation from confirmation | ||
| 22 | CO_PEDZ | Forecast finish time of operation from confirmation | ||
| 23 | CO_RUMNG | Previously confirmed activity | ||
| 24 | CO_RUMNG | Previously confirmed activity | ||
| 25 | CO_RUMNG | Previously confirmed activity | ||
| 26 | CO_RUMNG | Previously confirmed activity | ||
| 27 | CO_RUMNG | Previously confirmed activity | ||
| 28 | CO_RUMNG | Previously confirmed activity | ||
| 29 | CO_SCHAETZ | Forecast value used to update the standard value | ||
| 30 | CO_SCHAETZ | Forecast value used to update the standard value | ||
| 31 | CO_SCHAETZ | Forecast value used to update the standard value | ||
| 32 | CO_SCHAETZ | Forecast value used to update the standard value | ||
| 33 | CO_SCHAETZ | Forecast value used to update the standard value | ||
| 34 | CO_SCHAETZ | Forecast value used to update the standard value | ||
| 35 | CP_OBZOFFB | Reference date for start of sub-operation | ||
| 36 | CP_OBZOFFE | Reference date for finish of sub-operation | ||
| 37 | CP_OEHOFFB | Unit for offset to start | ||
| 38 | CP_OEHOFFE | Unit for offset to finish | ||
| 39 | CP_OOFFSTB | Offset to sub-operation start | ||
| 40 | CP_OOFFSTE | Offset to sub-operation finish | ||
| 41 | CP_UMREN | Denominator for converting rtg and op units of measure | ||
| 42 | CP_UMREZ | Numerator for converting task list and oper. un. of measure | ||
| 43 | DAUMIN | Minimum activity duration | ||
| 44 | DAUMINE | Unit for the minimum duration | ||
| 45 | DAUNOR | Normal duration of the activity | ||
| 46 | DAUNORE | Normal duration/unit | ||
| 47 | DZEIER | Unit for the break time | ||
| 48 | DZEILM | Unit for the maximum wait time | ||
| 49 | DZEILP | Unit for the required wait time | ||
| 50 | DZEIMB | Unit for the minimum processing time | ||
| 51 | DZEIMU | Unit for the minimum overlap time | ||
| 52 | DZEITM | Unit for the minimum move time | ||
| 53 | DZEITN | Unit for the standard move time | ||
| 54 | DZEIWM | Unit for the minumum queue time | ||
| 55 | DZEIWN | Unit for the standard queue time | ||
| 56 | DZLMAX | Maximum wait time | ||
| 57 | DZLPRO | Minimum wait time | ||
| 58 | DZMERH | Break | ||
| 59 | DZMINB | Minimum processing time | ||
| 60 | DZMINU | Minimum overlap time | ||
| 61 | DZTMIN | Minimum move time | ||
| 62 | DZTNOR | Standard move time | ||
| 63 | DZWMIN | Minimum queue time | ||
| 64 | DZWNOR | Standard queue time | ||
| 65 | EINSCHRA | Constraint on the basic start date for the activity | ||
| 66 | EINSCHRE | Constraint on the finish date of the activity | ||
| 67 | EPANF | Dispatched start date for operation | ||
| 68 | EPANZ | Dispatched start time for operation | ||
| 69 | EPEND | Dispatched finish date | ||
| 70 | EPENZ | Dispatched finish time | ||
| 71 | EWDAM | Minimum duration (from forecast) for activity | ||
| 72 | EWDAN | Normal duration (from forecast) of activity | ||
| 73 | EWDME | Unit for forecast minimum duration | ||
| 74 | EWDNE | Unit for forecast normal duration | ||
| 75 | EWENDED | Forecast finish date | ||
| 76 | EWENDEZ | Forecast finish time for the activity | ||
| 77 | EWSTARTD | Forecasted start date for the activity | ||
| 78 | EWSTARTZ | Forecast start time of the activity | ||
| 79 | FPAVD | Earliest scheduled start date (forecast) | ||
| 80 | FPAVZ | Earliest scheduled start time (forecast) | ||
| 81 | FPEDD | Earliest scheduled finish date (forecast) | ||
| 82 | FPEDZ | Earliest scheduled finish time (forecast) | ||
| 83 | FSAVD | Earliest scheduled start: Execution (date) | ||
| 84 | FSAVZ | Earliest scheduled start: Execution (time) | ||
| 85 | FSEDD | Earliest scheduled finish: Execution (date) | ||
| 86 | FSEDZ | Earliest scheduled finish: Execution (time) | ||
| 87 | FSELD | Earliest scheduled finish: Wait (date) | ||
| 88 | FSELZ | Earliest scheduled finish: Wait (time) | ||
| 89 | FSSAD | Earliest scheduled start: Teardown (date) | ||
| 90 | FSSAZ | Earliest scheduled start: Teardown (time) | ||
| 91 | FSSBD | Earliest scheduled start: Processing (date) | ||
| 92 | FSSBZ | Earliest scheduled start: Processing (time) | ||
| 93 | FSSLD | Earliest scheduled start: Wait (date) | ||
| 94 | FSSLZ | Earliest scheduled start: Wait (time) | ||
| 95 | GMNGA | Confirmed yield in order unit of measure | ||
| 96 | IEAVD | Actual finish of operation (date) | ||
| 97 | IEBD | Actual finish: Processing (date) | ||
| 98 | IEBZ | Actual processing finish (time) | ||
| 99 | IEDD | Actual finish: Execution (date) | ||
| 100 | IEDZ | Actual finish: Execution (time) | ||
| 101 | IERD | Actual finish: Setup (date) | ||
| 102 | IERZ | Actual finish: Setup (time) | ||
| 103 | ISAD | Actual start: Teardown (date) | ||
| 104 | ISAVD | Actual operation start (date) | ||
| 105 | ISAZ | Actual start: Teardown (time) | ||
| 106 | ISBD | Actual start: Processing (date) | ||
| 107 | ISBZ | Actual start: Processing (time) | ||
| 108 | ISDD | Actual start: Execution (date) | ||
| 109 | ISDZ | Actual start: Execution/setup (time) | ||
| 110 | ISERH | Confirmed break time | ||
| 111 | KNOTE | Transportation Connection Points | ||
| 112 | LD_TAKT | takt within a line segment | ||
| 113 | LIEGEZEIT | Wait time used for scheduling | ||
| 114 | LIGZE | Unit of measure for wait time | ||
| 115 | LMNGA | Total Yield Confirmed | ||
| 116 | LOAD_DATE | Date on Which Data Was Cached in TREX-Based Cache | ||
| 117 | LOAD_UNAME | User Who Loaded Data in TREX-Based Cache | ||
| 118 | MANDT | Client | ||
| 119 | MGVRG | Operation Quantity | ||
| 120 | MINWEI | Minimum Send-Ahead Quantity | ||
| 121 | OFMNW | Forecasted work (actual + remaining) | ||
| 122 | OPRE1 | Unit for remaining quantity of business process | ||
| 123 | OPRZ1 | Remaining quantity for business process | ||
| 124 | PBEARZEIT | Processing time (forecast) | ||
| 125 | PDAE | Unit of the forecasted duration from the confirmation | ||
| 126 | PDAU | Forecasted duration of activity from confirmation | ||
| 127 | PLIFZ | Planned delivery time in days | ||
| 128 | PPUFF_FREI | Free float (from forecast) | ||
| 129 | PPUFF_GESM | Total float (from forecast) | ||
| 130 | PSPM_INDICATOR | Indicates PMCS date influence activity scheduling | ||
| 131 | PS_EXPIRY_DATE | Date from Which Cached Data Is Invalid | ||
| 132 | PS_RESTA | Forecast date constraint on activity start | ||
| 133 | PS_RESTE | Forecast date constraint on activity finish | ||
| 134 | PUFFR_FREI | Free float | ||
| 135 | PUFFR_GESM | Total float | ||
| 136 | QRASTEREH | Grid Unit of Measure | ||
| 137 | QRASTMENG | Quantity Between Two Inspections | ||
| 138 | QRASTZEHT | Time Unit | ||
| 139 | QRASTZFAK | Time Factor | ||
| 140 | RMNGA | Total confirmed rework quantity | ||
| 141 | RSTZE | Unit of measure for setup time | ||
| 142 | RUEST | Setup time | ||
| 143 | RU_IPRZE | Unit of measurement for conf. quantity for business process | ||
| 144 | RU_IPRZK | No remaining quantity expected for business process | ||
| 145 | RWFAK | Rework factor (is not used yet) | ||
| 146 | SPAVD | Latest scheduled start date (forecast) | ||
| 147 | SPAVZ | Latest scheduled start time (forecast) | ||
| 148 | SPEDD | Latest scheduled finish date (forecast) | ||
| 149 | SPEDZ | Latest scheduled finish time (forecast) | ||
| 150 | SSAVD | Latest scheduled start: Execution (date) | ||
| 151 | SSAVZ | Latest scheduled start: Execution (time) | ||
| 152 | SSEDD | Latest scheduled finish: Execution (date) | ||
| 153 | SSEDZ | Latest scheduled finish: Execution (time) | ||
| 154 | SSELD | Latest scheduled finish: Wait time (date) | ||
| 155 | SSELZ | Latest scheduled finish: Wait time | ||
| 156 | SSSAD | Latest scheduled start: Teardown (date) | ||
| 157 | SSSAZ | Latest scheduled start: Teardown (time) | ||
| 158 | SSSBD | Latest scheduled start: Processing (date) | ||
| 159 | SSSBZ | Latest scheduled start: Processing (time) | ||
| 160 | SSSLD | Latest scheduled start: Wait time (date) | ||
| 161 | SSSLZ | Latest scheduled start: Wait time | ||
| 162 | TRANSZEIT | Move time used for scheduling | ||
| 163 | TRAZE | Unit of measure for move time | ||
| 164 | VGWRT | Standard Value | ||
| 165 | VGWRT | Standard Value | ||
| 166 | VGWRT | Standard Value | ||
| 167 | VGWRT | Standard Value | ||
| 168 | VGWRT | Standard Value | ||
| 169 | VGWRT | Standard Value | ||
| 170 | VGWRTEH | Unit of measure for the standard value | ||
| 171 | VGWRTEH | Unit of measure for the standard value | ||
| 172 | VGWRTEH | Unit of measure for the standard value | ||
| 173 | VGWRTEH | Unit of measure for the standard value | ||
| 174 | VGWRTEH | Unit of measure for the standard value | ||
| 175 | VGWRTEH | Unit of measure for the standard value | ||
| 176 | VORGABEEND2 | Constraint for Finish of Activity (Basic) | ||
| 177 | VORGABEENZ | Basic finish time of the activity | ||
| 178 | VORGABESTD | Constraint for activity start (Basic) | ||
| 179 | VORGABESTZ | Constraint for activity start time (Basic) | ||
| 180 | VORME | Unit of measure for activity | ||
| 181 | VSTGA | Deadline deviation reason | ||
| 182 | VSTZW | Deadline function | ||
| 183 | WARTEZEIT | Queue time used for scheduling | ||
| 184 | WTRZE | Unit of measure for queue time | ||
| 185 | XMNGA | Total scrap quantity confirmed |