Data Element list used by SAP ABAP Table BAPI_NETWORK_ACTIVITY (BAPI structure for network activities)
SAP ABAP Table
BAPI_NETWORK_ACTIVITY (BAPI structure for network activities) is using
| # | Object Type | Object Name | Object Description | Note |
|---|---|---|---|---|
| 1 | ANZKAP | Number of capacities required | ||
| 2 | APROZENT | Work percentage | ||
| 3 | ARBEIT | Work involved in the activity | ||
| 4 | ARBEITE | Unit for work | ||
| 5 | ARBPL | Work center | ||
| 6 | CLASF | Ind.: Take Activity Into Account for Project Summarization | ||
| 7 | CN_VORNR | Activity number in network and standard network | ||
| 8 | CR_VERTN | Distr.cap.reqmts (plant maint.,process order, network) | ||
| 9 | DAUDEHN | Indicator: flexible duration | ||
| 10 | DAUMIN | Minimum activity duration | ||
| 11 | DAUMINE | Unit for the minimum duration | ||
| 12 | DAUNOR | Normal duration of the activity | ||
| 13 | DAUNORE | Normal duration/unit | ||
| 14 | EINSCHRA | Constraint on the basic start date for the activity | ||
| 15 | EINSCHRE | Constraint on the finish date of the activity | ||
| 16 | EKGRP | Purchasing group | ||
| 17 | EKORG | Purchasing organization | ||
| 18 | EWDAM | Minimum duration (from forecast) for activity | ||
| 19 | EWDAN | Normal duration (from forecast) of activity | ||
| 20 | EWDME | Unit for forecast minimum duration | ||
| 21 | EWDNE | Unit for forecast normal duration | ||
| 22 | EWENDED | Forecast finish date | ||
| 23 | EWENDEZ | Forecast finish time for the activity | ||
| 24 | EWSTARTD | Forecasted start date for the activity | ||
| 25 | EWSTARTZ | Forecast start time of the activity | ||
| 26 | FKBER | Functional Area | ||
| 27 | FKBER_SHORT | Functional Area | ||
| 28 | FPAVD | Earliest scheduled start date (forecast) | ||
| 29 | FPAVZ | Earliest scheduled start time (forecast) | ||
| 30 | FPEDD | Earliest scheduled finish date (forecast) | ||
| 31 | FPEDZ | Earliest scheduled finish time (forecast) | ||
| 32 | FSAVD | Earliest scheduled start: Execution (date) | ||
| 33 | FSAVZ | Earliest scheduled start: Execution (time) | ||
| 34 | FSEDD | Earliest scheduled finish: Execution (date) | ||
| 35 | FSEDZ | Earliest scheduled finish: Execution (time) | ||
| 36 | INFNR | Number of purchasing info record | ||
| 37 | ISOCD | ISO currency code | ||
| 38 | ISOCD | ISO currency code | ||
| 39 | ISOCD | ISO currency code | ||
| 40 | ISOCD_UNIT | ISO code for unit of measurement | ||
| 41 | ISOCD_UNIT | ISO code for unit of measurement | ||
| 42 | ISOCD_UNIT | ISO code for unit of measurement | ||
| 43 | ISOCD_UNIT | ISO code for unit of measurement | ||
| 44 | ISOCD_UNIT | ISO code for unit of measurement | ||
| 45 | ISOCD_UNIT | ISO code for unit of measurement | ||
| 46 | ISOCD_UNIT | ISO code for unit of measurement | ||
| 47 | ISOCD_UNIT | ISO code for unit of measurement | ||
| 48 | KSTAR | Cost Element | ||
| 49 | LIFNR | Account Number of Vendor or Creditor | ||
| 50 | LSTAR | Activity Type | ||
| 51 | LTXA1 | Operation short text | ||
| 52 | MATKL | Material Group | ||
| 53 | MILESTONE | Usage | ||
| 54 | NODISP | Ind: Reserv. not applicable to MRP;Purc. req. not created | ||
| 55 | NW_AUFNR | Network number | ||
| 56 | NW_PRIO | Priority | ||
| 57 | PEINH | Price unit | ||
| 58 | PLIFZ | Planned delivery time in days | ||
| 59 | PPUFF_FREI | Free float (from forecast) | ||
| 60 | PPUFF_GESM | Total float (from forecast) | ||
| 61 | PRCTR | Profit Center | ||
| 62 | PREIS | Price | ||
| 63 | PRKST | Costs in the activity | ||
| 64 | PS_POSID | Work Breakdown Structure Element (WBS Element) | ||
| 65 | PS_PSPID | Project definition | ||
| 66 | PS_RESTA | Forecast date constraint on activity start | ||
| 67 | PS_RESTE | Forecast date constraint on activity finish | ||
| 68 | PUFFR_FREI | Free float | ||
| 69 | PUFFR_GESM | Total float | ||
| 70 | RFPNT | Reference point for BOM transfer | ||
| 71 | SCOPE | Object class (language-independent) | ||
| 72 | SCOPE_LD | Object class, language-dependent | ||
| 73 | SLWID | Key word ID for user-defined fields | ||
| 74 | SPAVD | Latest scheduled start date (forecast) | ||
| 75 | SPAVZ | Latest scheduled start time (forecast) | ||
| 76 | SPEDD | Latest scheduled finish date (forecast) | ||
| 77 | SPEDZ | Latest scheduled finish time (forecast) | ||
| 78 | SSAVD | Latest scheduled start: Execution (date) | ||
| 79 | SSAVZ | Latest scheduled start: Execution (time) | ||
| 80 | SSEDD | Latest scheduled finish: Execution (date) | ||
| 81 | SSEDZ | Latest scheduled finish: Execution (time) | ||
| 82 | STEUS | Control key | ||
| 83 | TXJCD | Tax Jurisdiction | ||
| 84 | USRCHAR10 | User field with 10 characters | ||
| 85 | USRCHAR10 | User field with 10 characters | ||
| 86 | USRCHAR20 | User field with 20 characters | ||
| 87 | USRCHAR20 | User field with 20 characters | ||
| 88 | USRCUKY | User field: Unit for value fields | ||
| 89 | USRCUKY | User field: Unit for value fields | ||
| 90 | USRCURR13 | User-defined field for values (length 10,3) | ||
| 91 | USRCURR13 | User-defined field for values (length 10,3) | ||
| 92 | USRDATE | User field for date | ||
| 93 | USRDATE | User field for date | ||
| 94 | USRFLAG | User-defined field: Indicator for reports | ||
| 95 | USRFLAG | User-defined field: Indicator for reports | ||
| 96 | USRQUAN13 | User field for quantity (length 10.3) | ||
| 97 | USRQUAN13 | User field for quantity (length 10.3) | ||
| 98 | USRUNIT | User field: Unit for quantity fields | ||
| 99 | USRUNIT | User field: Unit for quantity fields | ||
| 100 | VORGABEEND | Constraint for finish of activity (Basic) | ||
| 101 | VORGABEENZ | Basic finish time of the activity | ||
| 102 | VORGABESTD | Constraint for activity start (Basic) | ||
| 103 | VORGABESTZ | Constraint for activity start time (Basic) | ||
| 104 | VORME | Unit of measure for activity | ||
| 105 | WAERS | Currency Key | ||
| 106 | WERKS_D | Plant | ||
| 107 | WFCID | Factory Calendar |