SAP ABAP Table IFNETACTIM (Interface structure for network activities -> Import only)
Hierarchy
SAP_APPL (Software Component) Logistics and Accounting
   PS-ST-OPR (Application Component) Operative Structures
     CNIF (Package) External 'Interface for Project Management System (PS)'
Basic Data
Table Category INTTAB    Structure 
Structure IFNETACTIM   Table Relationship Diagram
Short Description Interface structure for network activities -> Import only    
Delivery and Maintenance
Pool/cluster      
Delivery Class      
Data Browser/Table View Maintenance     Display/Maintenance Allowed with Restrictions 
Components
     
Field Key Data Element Domain Data
Type
Length Decimal
Places
Short Description Check
table
1 AUFNR AUF_NETNR AUFNR CHAR 12   0   Order/Network number *
2 VORNR CN_VORNR VORNR CHAR 4   0   Activity number in network and standard network  
3 STEUS STEUS STEUS CHAR 4   0   Control key *
4 ARBPL ARBPL ARBPL CHAR 8   0   Work center  
5 WERKS WERKS_D WERKS CHAR 4   0   Plant *
6 LTXA1 LTXA1 TEXT40 CHAR 40   0   Operation short text  
7 LIFNR LIFNR LIFNR CHAR 10   0   Account Number of Vendor or Creditor *
8 PREIS PREIS WERT11 CURR 11   2   Price  
9 PEINH PEINH PACK3 DEC 5   0   Price unit  
10 SAKTO KSTAR KSTAR CHAR 10   0   Cost Element *
11 WAERS WAERS WAERS CUKY 5   0   Currency Key *
12 INFNR INFNR INFNR CHAR 10   0   Number of purchasing info record *
13 EKORG EKORG EKORG CHAR 4   0   Purchasing organization *
14 EKGRP VG_EKGRP EKGRP CHAR 3   0   Purchasing group for external processing *
15 MATKL MATKL MATKL CHAR 9   0   Material Group *
16 DDEHN DAUDEHN X CHAR 1   0   Indicator: flexible duration  
17 ANZZL ANZKAP INT1 INT1 3   0   Number of capacities required  
18 PRZNT APROZENT INT1 INT1 3   0   Work percentage  
19 MLSTN MILESTONE MILESTONE CHAR 5   0   Usage *
20 LARNT LSTAR LSTAR CHAR 6   0   Activity Type *
21 PRKST PRKST PRKST CURR 11   2   Costs in the activity  
22 PSPID PS_PSPID PS_PSPID CHAR 24   0   Project definition  
23 POSID PS_POSID PS_POSID CHAR 24   0   Work Breakdown Structure Element (WBS Element)  
24 KALID WFCID WFCID CHAR 2   0   Factory Calendar *
25 VERTL CR_VERTN CR_VERTL CHAR 8   0   Distr.cap.reqmts (plant maint.,process order, network) *
26 NPRIO NW_PRIO NW_PRIO CHAR 1   0   Priority *
27 TXJCD TXJCD TXJCD CHAR 15   0   Tax Jurisdiction *
28 SCOPE SCOPE_CV SCOPE_CV CHAR 2   0   Object Class  
29 PRCTR PRCTR PRCTR CHAR 10   0   Profit Center *
30 NO_DISP NODISP XFELD CHAR 1   0   Ind: Reserv. not applicable to MRP;Purc. req. not created  
31 CLASF CLASF XFELD CHAR 1   0   Ind.: Take Activity Into Account for Project Summarization  
32 MEINH VORME MEINS UNIT 3   0   Unit of measure for activity *
33 PLIFZ PLIFZ DEC3 DEC 3   0   Planned delivery time in days  
34 DAUNO DAUNOR DAUER_4_1 QUAN 5   1   Normal duration of the activity  
35 DAUNE DAUNORE MEINS UNIT 3   0   Normal duration/unit *
36 DAUMI DAUMIN DAUER_4_1 QUAN 5   1   Minimum activity duration  
37 DAUME DAUMINE MEINS UNIT 3   0   Unit for the minimum duration *
38 EINSA EINSCHRA RESTRIKSTR CHAR 1   0   Constraint on the basic start date for the activity  
39 EINSE EINSCHRE RESTRIKEND CHAR 1   0   Constraint on the finish date of the activity  
40 ARBEI ARBEIT ARBEIT QUAN 7   1   Work involved in the activity  
41 ARBEH ARBEITE MEINS UNIT 3   0   Unit for work *
42 FSAVD FSAVD DATUM DATS 8   0   Earliest scheduled start: Execution (date)  
43 FSAVZ FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
44 FSEDD FSEDD DATUM DATS 8   0   Earliest scheduled finish: Execution (date)  
45 FSEDZ FSEDZ ATIME TIMS 6   0   Earliest scheduled finish: Execution (time)  
46 SSAVD SSAVD DATUM DATS 8   0   Latest scheduled start: Execution (date)  
47 SSAVZ SSAVZ ATIME TIMS 6   0   Latest scheduled start: Execution (time)  
48 SSEDD SSEDD DATUM DATS 8   0   Latest scheduled finish: Execution (date)  
49 SSEDZ SSEDZ ATIME TIMS 6   0   Latest scheduled finish: Execution (time)  
50 PUFFR PUFFR_FREI PUFFER DEC 3   0   Free float  
51 PUFGS PUFFR_GESM PUFFER DEC 3   0   Total float  
52 NTANF VORGABESTD VORGABESTR DATS 8   0   Constraint for activity start (Basic)  
53 NTANZ VORGABESTZ ATIME TIMS 6   0   Constraint for activity start time (Basic)  
54 NTEND VORGABEEND VORGABEEND DATS 8   0   Constraint for finish of activity (Basic)  
55 NTENZ VORGABEENZ ATIME TIMS 6   0   Basic finish time of the activity  
56 SLWID SLWID SLWID CHAR 7   0   Key word ID for user-defined fields *
57 USR00 USRCHAR20 USRCHAR20 CHAR 20   0   User field with 20 characters  
58 USR01 USRCHAR20 USRCHAR20 CHAR 20   0   User field with 20 characters  
59 USR02 USRCHAR10 USRCHAR10 CHAR 10   0   User field with 10 characters  
60 USR03 USRCHAR10 USRCHAR10 CHAR 10   0   User field with 10 characters  
61 USR04 USRQUAN13 USRQUAN13 QUAN 13   3   User field for quantity (length 10.3)  
62 USE04 USRUNIT MEINS UNIT 3   0   User field: Unit for quantity fields *
63 USR05 USRQUAN13 USRQUAN13 QUAN 13   3   User field for quantity (length 10.3)  
64 USE05 USRUNIT MEINS UNIT 3   0   User field: Unit for quantity fields *
65 USR06 USRCURR13 USRCURR13 CURR 13   3   User-defined field for values (length 10,3)  
66 USE06 USRCUKY WAERS CUKY 5   0   User field: Unit for value fields *
67 USR07 USRCURR13 USRCURR13 CURR 13   3   User-defined field for values (length 10,3)  
68 USE07 USRCUKY WAERS CUKY 5   0   User field: Unit for value fields *
69 USR08 USRDATE USRDATE DATS 8   0   User field for date  
70 USR09 USRDATE USRDATE DATS 8   0   User field for date  
71 USR10 USRFLAG FLAG CHAR 1   0   User-defined field: Indicator for reports  
72 USR11 USRFLAG FLAG CHAR 1   0   User-defined field: Indicator for reports  
73 .INCLUDE       0   0    
74 PEDD CO_PEDD DATUM DATS 8   0   Forecast finish date of operation from confirmation  
75 PEDZ CO_PEDZ ATIME TIMS 6   0   Forecast finish time of operation from confirmation  
76 PDAU PDAU DAUER_4_1 QUAN 5   1   Forecasted duration of activity from confirmation  
77 PDAE PDAE MEINS UNIT 3   0   Unit of the forecasted duration from the confirmation *
78 EWSTD EWSTARTD DATUM DATS 8   0   Forecasted start date for the activity  
79 EWSTZ EWSTARTZ ATIME TIMS 6   0   Forecast start time of the activity  
80 EWEND EWENDED DATUM DATS 8   0   Forecast finish date  
81 EWENZ EWENDEZ ATIME TIMS 6   0   Forecast finish time for the activity  
82 EWDAN EWDAN DAUER_4_1 QUAN 5   1   Normal duration (from forecast) of activity  
83 EWDNE EWDNE MEINS UNIT 3   0   Unit for forecast normal duration *
84 EWDAM EWDAM DAUER_4_1 QUAN 5   1   Minimum duration (from forecast) for activity  
85 EWDME EWDME MEINS UNIT 3   0   Unit for forecast minimum duration *
86 EWSTE PS_RESTE RESTRIKEND CHAR 1   0   Forecast date constraint on activity finish  
87 EWSTA PS_RESTA RESTRIKSTR CHAR 1   0   Forecast date constraint on activity start  
88 FPAVD FPAVD DATUM DATS 8   0   Earliest scheduled start date (forecast)  
89 FPAVZ FPAVZ ATIME TIMS 6   0   Earliest scheduled start time (forecast)  
90 FPEDD FPEDD DATUM DATS 8   0   Earliest scheduled finish date (forecast)  
91 FPEDZ FPEDZ ATIME TIMS 6   0   Earliest scheduled finish time (forecast)  
92 SPAVD SPAVD DATUM DATS 8   0   Latest scheduled start date (forecast)  
93 SPAVZ SPAVZ ATIME TIMS 6   0   Latest scheduled start time (forecast)  
94 SPEDD SPEDD DATUM DATS 8   0   Latest scheduled finish date (forecast)  
95 SPEDZ SPEDZ ATIME TIMS 6   0   Latest scheduled finish time (forecast)  
96 BEAZP BEAZEP EINHEIT UNIT 3   0   Unit of processing time (Forecast)  
97 PUFGP PPUFF_GESM PUFFER DEC 3   0   Total float (from forecast)  
98 PUFFP PPUFF_FREI PUFFER DEC 3   0   Free float (from forecast)  
99 BEARP PBEARZEIT CX_ZEIT FLTP 16   16   Processing time (forecast)  
100 DAPBE CO_DAUBEAP DAUER_6_1 QUAN 7   1   Duration of processing time (forecast)  
History
Last changed by/on SAP  20130529 
SAP Release Created in