Data Element list used by SAP ABAP Table KBED01_UPDATE_RELEVANT (Fields relevant to the update from KBED/Z (sim. vers.))
SAP ABAP Table KBED01_UPDATE_RELEVANT (Fields relevant to the update from KBED/Z (sim. vers.)) is using
# Object Type Object Name Object Description Note
     
1 Data Element  ARBEIT Work involved in the activity
2 Data Element  ARBEITE Unit for work
3 Data Element  ARBPLATZ Work center ID
4 Data Element  ARUZE Unit of measure for teardown
5 Data Element  ASVRG Operation scrap
6 Data Element  BEAZE Unit of measure for processing time
7 Data Element  BEDKZ Indicator: Remaining split record
8 Data Element  BMSCH Base Quantity
9 Data Element  CANUMF Counter for the main capacity requirements record
10 Data Element  CIM_COUNT Internal counter
11 Data Element  CO_APLZL General counter for order
12 Data Element  CO_AUFPL Routing number of operations in the order
13 Data Element  CO_ISMNGEH Unit of measure for the activity to be confirmed
14 Data Element  CO_ISMNGEH Unit of measure for the activity to be confirmed
15 Data Element  CO_ISMNGEH Unit of measure for the activity to be confirmed
16 Data Element  CO_ISMNGEH Unit of measure for the activity to be confirmed
17 Data Element  CO_ISMNGEH Unit of measure for the activity to be confirmed
18 Data Element  CO_ISMNGEH Unit of measure for the activity to be confirmed
19 Data Element  CO_ISMNW Actual work
20 Data Element  CO_LEIKZ Indicator: No remaining activity expected
21 Data Element  CO_LEIKZ Indicator: No remaining activity expected
22 Data Element  CO_LEIKZ Indicator: No remaining activity expected
23 Data Element  CO_LEIKZ Indicator: No remaining activity expected
24 Data Element  CO_LEIKZ Indicator: No remaining activity expected
25 Data Element  CO_LEIKZ Indicator: No remaining activity expected
26 Data Element  CO_LEIKZ Indicator: No remaining activity expected
27 Data Element  CO_PEDD Forecast finish date of operation from confirmation
28 Data Element  CO_PEDZ Forecast finish time of operation from confirmation
29 Data Element  CO_RUMNG Previously confirmed activity
30 Data Element  CO_RUMNG Previously confirmed activity
31 Data Element  CO_RUMNG Previously confirmed activity
32 Data Element  CO_RUMNG Previously confirmed activity
33 Data Element  CO_RUMNG Previously confirmed activity
34 Data Element  CO_RUMNG Previously confirmed activity
35 Data Element  CO_SCHAETZ Forecast value used to update the standard value
36 Data Element  CO_SCHAETZ Forecast value used to update the standard value
37 Data Element  CO_SCHAETZ Forecast value used to update the standard value
38 Data Element  CO_SCHAETZ Forecast value used to update the standard value
39 Data Element  CO_SCHAETZ Forecast value used to update the standard value
40 Data Element  CO_SCHAETZ Forecast value used to update the standard value
41 Data Element  CP_UMREN Denominator for converting rtg and op units of measure
42 Data Element  CP_UMREZ Numerator for converting task list and oper. un. of measure
43 Data Element  CR_VERTL Distribution of capacity requirements (Planned/prod.order)
44 Data Element  CY_BSTKZ Indicator rqmts.record is confirmed (cap.availability check)
45 Data Element  CY_KABRRES Remaining capacity requirements for op. segment "tear down"
46 Data Element  CY_KABRSOL Scheduled cap. requirements for the op. segment teardown
47 Data Element  CY_KBEARES Remaining capacity rqmts.for operation segment "Processing"
48 Data Element  CY_KBEASOL Process target capacity requirements for operation segment
49 Data Element  CY_KBSTA Status of a capacity requirements (object number)
50 Data Element  CY_KEINH Unit of of measure for displaying capacity requirements
51 Data Element  CY_KRUERES Remaining capacity rqmts. for operation segment "Setup"
52 Data Element  CY_KRUESOL Scheduled cap. requirements for the op. segment "setup"
53 Data Element  CY_PEREX Entry in KPER exists for this split
54 Data Element  CY_SPLIT Split number
55 Data Element  DAUNOR Normal duration of the activity
56 Data Element  DAUNORE Normal duration/unit
57 Data Element  DZEIER Unit for the break time
58 Data Element  FENDD Earliest finish /date
59 Data Element  FENDU Earliest finish /time
60 Data Element  FSSAD Earliest scheduled start: Teardown (date)
61 Data Element  FSSAZ Earliest scheduled start: Teardown (time)
62 Data Element  FSSBD Earliest scheduled start: Processing (date)
63 Data Element  FSSBZ Earliest scheduled start: Processing (time)
64 Data Element  FSTAD Earliest start / date
65 Data Element  FSTAU Earliest start / time
66 Data Element  IEBD Actual finish: Processing (date)
67 Data Element  IEBZ Actual processing finish (time)
68 Data Element  IEDD Actual finish: Execution (date)
69 Data Element  IEDZ Actual finish: Execution (time)
70 Data Element  IENDD Actual finish / date
71 Data Element  IENDU Actual finish / time
72 Data Element  IERD Actual finish: Setup (date)
73 Data Element  IERZ Actual finish: Setup (time)
74 Data Element  ISAD Actual start: Teardown (date)
75 Data Element  ISAZ Actual start: Teardown (time)
76 Data Element  ISBD Actual start: Processing (date)
77 Data Element  ISBZ Actual start: Processing (time)
78 Data Element  ISDD Actual start: Execution (date)
79 Data Element  ISDZ Actual start: Execution/setup (time)
80 Data Element  ISERH Confirmed break time
81 Data Element  ISPLI Actual number of splits
82 Data Element  ISTAD Actual start / date
83 Data Element  ISTAU Actual start / time
84 Data Element  KAPID Capacity ID
85 Data Element  LMNGA Total Yield Confirmed
86 Data Element  MANDT Client
87 Data Element  MAXBD_KZ Indicator: Capacity fully committed
88 Data Element  MGVRG Operation Quantity
89 Data Element  OBJKZ Indicator: Remaining split record
90 Data Element  OBSTA Object status (order status)
91 Data Element  OFMNW Forecasted work (actual + remaining)
92 Data Element  OTYPE Object Type
93 Data Element  PDAE Unit of the forecasted duration from the confirmation
94 Data Element  PDAU Forecasted duration of activity from confirmation
95 Data Element  PENDD Forecast finish / date
96 Data Element  PENDU Forecast finish / time
97 Data Element  PERNR_D Personnel Number
98 Data Element  PHASE_KZ Indicator: Phase
99 Data Element  PLNAL Group Counter
100 Data Element  PLNFOLGE Sequence
101 Data Element  PLNNR Key for Task List Group
102 Data Element  PLNTY Task List Type
103 Data Element  PLSCN Planning Scenario of Long-Term Planning
104 Data Element  RMNGA Total confirmed rework quantity
105 Data Element  RSTUF Reduction level which reduces operation lead time
106 Data Element  RSTZE Unit of measure for setup time
107 Data Element  SAFNR SOP order number
108 Data Element  SENDD Latest finish / date
109 Data Element  SENDU Latest finish / time
110 Data Element  SSSAD Latest scheduled start: Teardown (date)
111 Data Element  SSSAZ Latest scheduled start: Teardown (time)
112 Data Element  SSSBD Latest scheduled start: Processing (date)
113 Data Element  SSSBZ Latest scheduled start: Processing (time)
114 Data Element  SSTAD Latest start / date
115 Data Element  SSTAU Latest start / time
116 Data Element  TYPKZ Type of object causing the load (order category)
117 Data Element  USRQUAN13 User field for quantity (length 10.3)
118 Data Element  USRQUAN13 User field for quantity (length 10.3)
119 Data Element  USRUNIT User field: Unit for quantity fields
120 Data Element  USRUNIT User field: Unit for quantity fields
121 Data Element  VGWRT Standard Value
122 Data Element  VGWRT Standard Value
123 Data Element  VGWRT Standard Value
124 Data Element  VGWRT Standard Value
125 Data Element  VGWRT Standard Value
126 Data Element  VGWRT Standard Value
127 Data Element  VGWRTEH Unit of measure for the standard value
128 Data Element  VGWRTEH Unit of measure for the standard value
129 Data Element  VGWRTEH Unit of measure for the standard value
130 Data Element  VGWRTEH Unit of measure for the standard value
131 Data Element  VGWRTEH Unit of measure for the standard value
132 Data Element  VGWRTEH Unit of measure for the standard value
133 Data Element  VORME Unit of measure for activity
134 Data Element  VORNR Operation/Activity Number
135 Data Element  XMNGA Total scrap quantity confirmed