Data Element list used by SAP ABAP Table ACT01_TIME (Fields from ACT01 with time ref.(for authztn check LDB PSJ))
SAP ABAP Table
ACT01_TIME (Fields from ACT01 with time ref.(for authztn check LDB PSJ)) is using
| # | Object Type | Object Name | Object Description | Note |
|---|---|---|---|---|
| 1 | ABRUE | Teardown | ||
| 2 | ARUZE | Unit of measure for teardown | ||
| 3 | BEARZEIT | Processing time | ||
| 4 | BEAZE | Unit of measure for processing time | ||
| 5 | BEAZEP | Unit of processing time (Forecast) | ||
| 6 | CO_DAUABR | Teardown time | ||
| 7 | CO_DAUBEA | Processing time | ||
| 8 | CO_DAUBEAP | Duration of processing time (forecast) | ||
| 9 | CO_DAUDRF | Duration of execution time (setup + processing + teardown) | ||
| 10 | CO_DAULIE | Wait time | ||
| 11 | CO_DAURUE | Setup time | ||
| 12 | CO_DAUTRA | Duration of move time | ||
| 13 | CO_DAUWAR | Queue time | ||
| 14 | CO_PEDD | Forecast finish date of operation from confirmation | ||
| 15 | CO_PEDZ | Forecast finish time of operation from confirmation | ||
| 16 | CP_OBZOFFE | Reference date for finish of sub-operation | ||
| 17 | CP_OEHOFFB | Unit for offset to start | ||
| 18 | CP_OEHOFFE | Unit for offset to finish | ||
| 19 | CP_OOFFSTB | Offset to sub-operation start | ||
| 20 | CP_OOFFSTE | Offset to sub-operation finish | ||
| 21 | DAUMIN | Minimum activity duration | ||
| 22 | DAUMINE | Unit for the minimum duration | ||
| 23 | DAUNOR | Normal duration of the activity | ||
| 24 | DAUNORE | Normal duration/unit | ||
| 25 | DZEILM | Unit for the maximum wait time | ||
| 26 | DZEILP | Unit for the required wait time | ||
| 27 | DZEIMB | Unit for the minimum processing time | ||
| 28 | DZEIMU | Unit for the minimum overlap time | ||
| 29 | DZEITM | Unit for the minimum move time | ||
| 30 | DZEITN | Unit for the standard move time | ||
| 31 | DZEIWM | Unit for the minumum queue time | ||
| 32 | DZEIWN | Unit for the standard queue time | ||
| 33 | DZLMAX | Maximum wait time | ||
| 34 | DZLPRO | Minimum wait time | ||
| 35 | DZMINB | Minimum processing time | ||
| 36 | DZMINU | Minimum overlap time | ||
| 37 | DZTMIN | Minimum move time | ||
| 38 | DZTNOR | Standard move time | ||
| 39 | DZWMIN | Minimum queue time | ||
| 40 | DZWNOR | Standard queue time | ||
| 41 | EINSCHRA | Constraint on the basic start date for the activity | ||
| 42 | EINSCHRE | Constraint on the finish date of the activity | ||
| 43 | EPANF | Dispatched start date for operation | ||
| 44 | EPANZ | Dispatched start time for operation | ||
| 45 | EPEND | Dispatched finish date | ||
| 46 | EPENZ | Dispatched finish time | ||
| 47 | EWDAM | Minimum duration (from forecast) for activity | ||
| 48 | EWDAN | Normal duration (from forecast) of activity | ||
| 49 | EWDME | Unit for forecast minimum duration | ||
| 50 | EWDNE | Unit for forecast normal duration | ||
| 51 | EWENDED | Forecast finish date | ||
| 52 | EWENDEZ | Forecast finish time for the activity | ||
| 53 | EWSTARTD | Forecasted start date for the activity | ||
| 54 | EWSTARTZ | Forecast start time of the activity | ||
| 55 | FPAVD | Earliest scheduled start date (forecast) | ||
| 56 | FPAVZ | Earliest scheduled start time (forecast) | ||
| 57 | FPEDD | Earliest scheduled finish date (forecast) | ||
| 58 | FPEDZ | Earliest scheduled finish time (forecast) | ||
| 59 | FSAVD | Earliest scheduled start: Execution (date) | ||
| 60 | FSAVZ | Earliest scheduled start: Execution (time) | ||
| 61 | FSEDD | Earliest scheduled finish: Execution (date) | ||
| 62 | FSEDZ | Earliest scheduled finish: Execution (time) | ||
| 63 | FSELD | Earliest scheduled finish: Wait (date) | ||
| 64 | FSELZ | Earliest scheduled finish: Wait (time) | ||
| 65 | FSEVD | Earliest finish of operation (date) | ||
| 66 | FSEVZ | Earliest finish of operation (time) | ||
| 67 | FSSAD | Earliest scheduled start: Teardown (date) | ||
| 68 | FSSAZ | Earliest scheduled start: Teardown (time) | ||
| 69 | FSSBD | Earliest scheduled start: Processing (date) | ||
| 70 | FSSBZ | Earliest scheduled start: Processing (time) | ||
| 71 | FSSLD | Earliest scheduled start: Wait (date) | ||
| 72 | FSSLZ | Earliest scheduled start: Wait (time) | ||
| 73 | IEAVD | Actual finish of operation (date) | ||
| 74 | IEBD | Actual finish: Processing (date) | ||
| 75 | IEBZ | Actual processing finish (time) | ||
| 76 | IEDD | Actual finish: Execution (date) | ||
| 77 | IEDZ | Actual finish: Execution (time) | ||
| 78 | IERD | Actual finish: Setup (date) | ||
| 79 | IERZ | Actual finish: Setup (time) | ||
| 80 | ISAD | Actual start: Teardown (date) | ||
| 81 | ISAVD | Actual operation start (date) | ||
| 82 | ISAZ | Actual start: Teardown (time) | ||
| 83 | ISBD | Actual start: Processing (date) | ||
| 84 | ISBZ | Actual start: Processing (time) | ||
| 85 | ISDD | Actual start: Execution (date) | ||
| 86 | ISDZ | Actual start: Execution/setup (time) | ||
| 87 | ISERH | Confirmed break time | ||
| 88 | LIEGEZEIT | Wait time used for scheduling | ||
| 89 | LIGZE | Unit of measure for wait time | ||
| 90 | PBEARZEIT | Processing time (forecast) | ||
| 91 | PDAE | Unit of the forecasted duration from the confirmation | ||
| 92 | PDAU | Forecasted duration of activity from confirmation | ||
| 93 | PLIFZ | Planned delivery time in days | ||
| 94 | PLIFZ | Planned delivery time in days | ||
| 95 | PPUFF_FREI | Free float (from forecast) | ||
| 96 | PPUFF_GESM | Total float (from forecast) | ||
| 97 | PS_RESTA | Forecast date constraint on activity start | ||
| 98 | PS_RESTE | Forecast date constraint on activity finish | ||
| 99 | PUFFR_FREI | Free float | ||
| 100 | PUFFR_GESM | Total float | ||
| 101 | RSTZE | Unit of measure for setup time | ||
| 102 | RUEST | Setup time | ||
| 103 | SPAVD | Latest scheduled start date (forecast) | ||
| 104 | SPAVZ | Latest scheduled start time (forecast) | ||
| 105 | SPEDD | Latest scheduled finish date (forecast) | ||
| 106 | SPEDZ | Latest scheduled finish time (forecast) | ||
| 107 | SSAVD | Latest scheduled start: Execution (date) | ||
| 108 | SSAVZ | Latest scheduled start: Execution (time) | ||
| 109 | SSEDD | Latest scheduled finish: Execution (date) | ||
| 110 | SSEDZ | Latest scheduled finish: Execution (time) | ||
| 111 | SSELD | Latest scheduled finish: Wait time (date) | ||
| 112 | SSELZ | Latest scheduled finish: Wait time | ||
| 113 | SSEVD | Latest finish date of operation | ||
| 114 | SSEVZ | Latest operation finish (time) | ||
| 115 | SSSAD | Latest scheduled start: Teardown (date) | ||
| 116 | SSSAZ | Latest scheduled start: Teardown (time) | ||
| 117 | SSSBD | Latest scheduled start: Processing (date) | ||
| 118 | SSSBZ | Latest scheduled start: Processing (time) | ||
| 119 | SSSLD | Latest scheduled start: Wait time (date) | ||
| 120 | SSSLZ | Latest scheduled start: Wait time | ||
| 121 | TRANSZEIT | Move time used for scheduling | ||
| 122 | TRAZE | Unit of measure for move time | ||
| 123 | VORGABEEND | Constraint for finish of activity (Basic) | ||
| 124 | VORGABEENZ | Basic finish time of the activity | ||
| 125 | VORGABESTD | Constraint for activity start (Basic) | ||
| 126 | VORGABESTZ | Constraint for activity start time (Basic) | ||
| 127 | WARTEZEIT | Queue time used for scheduling | ||
| 128 | WTRZE | Unit of measure for queue time |