Basic Data
Data Element | RESHZ |
Short Description | Roll forward period for the master plan |
Data Type
Category of Dictionary Type | D | Domain |
Type of Object Referenced | No Information | |
Domain / Name of Reference Type | RESHZ | |
Data Type | DEC | Counter or amount field with comma and sign |
Length | 2 | |
Decimal Places | 0 | |
Output Length | 3 | |
Value Table |
Further Characteristics
Search Help: Name | ||
Search Help: Parameters | ||
Parameter ID | ||
Default Component name | ROLL_FWD_PERIOD | |
Change document | ||
No Input History | ||
Basic direction is set to LTR | ||
No BIDI Filtering |
Field Label
Length | Field Label | |
Short | 10 | RollFwdPer |
Medium | 15 | Roll fwd period |
Long | 20 | Roll forward period |
Heading | 5 | RollF |
Documentation
Definition
The roll forward period defines a period for updating the master plan. In this period, the system deletes all firmed planned orders that lie before the roll forward period on the time axis.
At the same time the system adjusts the master plan to a new situation, if necessary, that is, if new requirements have been created, new planned orders are created.
The roll forward period is maintained in workdays.
Procedure
You can maintain this period either in the past or in the future.
If you want to maintain this period in the past, you must set a minus sign after the number.
Examples
If you want the system to delete all planned orders from the database that, starting from today's date, are older than two days, enter 2-.
Dependencies
In order to carry out this function, a material must be provided with an MRP type which contains the indicator "Delete firmed planned orders".
For more information on this, please refer to the implementation guide.