1 | Data Element | ANFKO | Requesting cost center | |
2 | Data Element | ANFKOKRS | Controlling area of the requesting cost center | |
3 | Data Element | ANZKAP | Number of capacities required | |
4 | Data Element | APROZENT | Work percentage | |
5 | Data Element | ARBEIT | Work involved in the activity | |
6 | Data Element | ARBEITE | Unit for work | |
7 | Data Element | BEARZEIT | Processing time | |
8 | Data Element | BEAZE | Unit of measure for processing time | |
9 | Data Element | BEAZEP | Unit of processing time (Forecast) | |
10 | Data Element | BEDID | ID of the capacity requirements record | |
11 | Data Element | BMSCH | Base Quantity | |
12 | Data Element | CIM_COUNT | Internal counter | |
13 | Data Element | CO_APLZL | General counter for order | |
14 | Data Element | CO_AUFPL | Routing number of operations in the order | |
15 | Data Element | CP_UMREN | Denominator for converting rtg and op units of measure | |
16 | Data Element | CP_UMREZ | Numerator for converting task list and oper. un. of measure | |
17 | Data Element | CR_OBJID | Object ID of the resource | |
18 | Data Element | CR_VERTN | Distr.cap.reqmts (plant maint.,process order, network) | |
19 | Data Element | DAUDEHN | Indicator: flexible duration | |
20 | Data Element | FPAVD | Earliest scheduled start date (forecast) | |
21 | Data Element | FPAVZ | Earliest scheduled start time (forecast) | |
22 | Data Element | FPEDD | Earliest scheduled finish date (forecast) | |
23 | Data Element | FPEDZ | Earliest scheduled finish time (forecast) | |
24 | Data Element | INDET | Calculation key | |
25 | Data Element | KTSCH | Standard text key | |
26 | Data Element | LSTAR | Activity Type | |
27 | Data Element | MANDT | Client | |
28 | Data Element | OFMNW | Forecasted work (actual + remaining) | |
29 | Data Element | PBEARZEIT | Processing time (forecast) | |
30 | Data Element | PPUFF_FREI | Free float (from forecast) | |
31 | Data Element | PPUFF_GESM | Total float (from forecast) | |
32 | Data Element | SPAVD | Latest scheduled start date (forecast) | |
33 | Data Element | SPAVZ | Latest scheduled start time (forecast) | |
34 | Data Element | SPEDD | Latest scheduled finish date (forecast) | |
35 | Data Element | SPEDZ | Latest scheduled finish time (forecast) | |
36 | Data Element | STEUS | Control key | |
37 | Data Element | VORME | Unit of measure for activity | |
38 | Data Element | WERKS_D | Plant |