SAP ABAP Table NTWXPD_INPUT (Input Structure for Expediting Network Activity)
Hierarchy
☛
EA-APPL (Software Component) SAP Enterprise Extension PLM, SCM, Financials
⤷
PS-PRG-TRC (Application Component) Progress Tracking
⤷
EXPD (Package) Expediting for Order

⤷

⤷

Basic Data
Table Category | INTTAB | Structure |
Structure | NTWXPD_INPUT |
![]() |
Short Description | Input Structure for Expediting Network Activity |
Delivery and Maintenance
Pool/cluster | ||
Delivery Class | ||
Data Browser/Table View Maintenance | Display/Maintenance Allowed with Restrictions |
Components
![]() |
Field | Key | Data Element | Domain | Data Type |
Length | Decimal Places |
Short Description | Check table |
---|---|---|---|---|---|---|---|---|---|
1 | ![]() |
EXP_IDENT | CHAR50 | CHAR | 50 | 0 | Identification | ||
2 | ![]() |
0 | 0 | Progress Tracking for Network Activities | |||||
3 | ![]() |
PS_PSPID | PS_PSPID | CHAR | 24 | 0 | Project definition | ||
4 | ![]() |
PS_POSID | PS_POSID | CHAR | 24 | 0 | Work Breakdown Structure Element (WBS Element) | ||
5 | ![]() |
AUFNR | AUFNR | CHAR | 12 | 0 | Order Number | * | |
6 | ![]() |
VORNR | VORNR | CHAR | 4 | 0 | Operation/Activity Number | ||
7 | ![]() |
LTXA1 | TEXT40 | CHAR | 40 | 0 | Operation short text | ||
8 | ![]() |
FSAVD | DATUM | DATS | 8 | 0 | Earliest scheduled start: Execution (date) | ||
9 | ![]() |
FSAVZ | ATIME | TIMS | 6 | 0 | Earliest scheduled start: Execution (time) | ||
10 | ![]() |
FSEDD | DATUM | DATS | 8 | 0 | Earliest scheduled finish: Execution (date) | ||
11 | ![]() |
FSEDZ | ATIME | TIMS | 6 | 0 | Earliest scheduled finish: Execution (time) | ||
12 | ![]() |
SSAVD | DATUM | DATS | 8 | 0 | Latest scheduled start: Execution (date) | ||
13 | ![]() |
SSAVZ | ATIME | TIMS | 6 | 0 | Latest scheduled start: Execution (time) | ||
14 | ![]() |
SSEDD | DATUM | DATS | 8 | 0 | Latest scheduled finish: Execution (date) | ||
15 | ![]() |
SSEDZ | ATIME | TIMS | 6 | 0 | Latest scheduled finish: Execution (time) | ||
16 | ![]() |
ISDD | DATUM | DATS | 8 | 0 | Actual start: Execution (date) | ||
17 | ![]() |
ISDZ | ATIME | TIMS | 6 | 0 | Actual start: Execution/setup (time) | ||
18 | ![]() |
IEDD | DATUM | DATS | 8 | 0 | Actual finish: Execution (date) | ||
19 | ![]() |
IEDZ | ATIME | TIMS | 6 | 0 | Actual finish: Execution (time) | ||
20 | ![]() |
CO_PEDD | DATUM | DATS | 8 | 0 | Forecast finish date of operation from confirmation | ||
21 | ![]() |
CO_PEDZ | ATIME | TIMS | 6 | 0 | Forecast finish time of operation from confirmation | ||
22 | ![]() |
EPANF | DATUM | DATS | 8 | 0 | Dispatched start date for operation | ||
23 | ![]() |
EPANZ | ATIME | TIMS | 6 | 0 | Dispatched start time for operation | ||
24 | ![]() |
EPEND | DATUM | DATS | 8 | 0 | Dispatched finish date | ||
25 | ![]() |
EPENZ | ATIME | TIMS | 6 | 0 | Dispatched finish time | ||
26 | ![]() |
CO_DAUBEA | DAUER_6_1 | QUAN | 7 | 1 | Processing time | ||
27 | ![]() |
BEAZE | EINHEIT | UNIT | 3 | 0 | Unit of measure for processing time | ||
28 | ![]() |
ARBEIT | ARBEIT | QUAN | 7 | 1 | Work involved in the activity | ||
29 | ![]() |
ARBEITE | MEINS | UNIT | 3 | 0 | Unit for work | * | |
30 | ![]() |
CO_ISMNW | MENG13 | QUAN | 13 | 3 | Actual work | ||
31 | ![]() |
PDAU | DAUER_4_1 | QUAN | 5 | 1 | Forecasted duration of activity from confirmation | ||
32 | ![]() |
PDAE | MEINS | UNIT | 3 | 0 | Unit of the forecasted duration from the confirmation | * | |
33 | ![]() |
OFMNW | ARBEIT | QUAN | 7 | 1 | Forecasted work (actual + remaining) |
History
Last changed by/on | SAP | 20100310 |
SAP Release Created in | 602 |