SAP ABAP Table AD03_RPSCO_LISC (Key Figures for Commercial Reporting in Structure Overview)
Hierarchy
☛
ECC-DIMP (Software Component) DIMP
⤷
IS-AD-EV (Application Component) Add-Ons for Progress Analysis
⤷
AD03 (Package) IS A&D: Earned Value Management

⤷

⤷

Basic Data
Table Category | INTTAB | Structure |
Structure | AD03_RPSCO_LISC |
![]() |
Short Description | Key Figures for Commercial Reporting in Structure Overview |
Delivery and Maintenance
Pool/cluster | ||
Delivery Class | ||
Data Browser/Table View Maintenance | Display/Maintenance Allowed with Restrictions |
Components
![]() |
Field | Key | Data Element | Domain | Data Type |
Length | Decimal Places |
Short Description | Check table |
---|---|---|---|---|---|---|---|---|---|
1 | ![]() |
0 | 0 | Key Figures for Commercial Reporting in Structure Overview | |||||
2 | ![]() |
PROKSTPLAN | WERTV8 | CURR | 15 | 2 | Current project cost plan | ||
3 | ![]() |
PROKSTPLN2 | WERTV8 | CURR | 15 | 2 | Project cost plan (version 2) | ||
4 | ![]() |
AUFKSTPLAN | WERTV8 | CURR | 15 | 2 | Current order cost plan | ||
5 | ![]() |
AUFKSTPLN2 | WERTV8 | CURR | 15 | 2 | Order cost plan (version 2) | ||
6 | ![]() |
PROERLPLAN | WERTV8 | CURR | 15 | 2 | Current project revenue plan | ||
7 | ![]() |
PROERLPLN2 | WERTV8 | CURR | 15 | 2 | Project revenue plan (version 2) | ||
8 | ![]() |
AUFERLPLAN | WERTV8 | CURR | 15 | 2 | Current order revenue plan | ||
9 | ![]() |
AUFERLPLN2 | WERTV8 | CURR | 15 | 2 | Order revenue plan (version 2) | ||
10 | ![]() |
KREDFINPLN | WERTV8 | CURR | 15 | 2 | Current financial budget, credit side | ||
11 | ![]() |
DEBFINPLN | WERTV8 | CURR | 15 | 2 | Current cash budget, debit side | ||
12 | ![]() |
BUDGET | WERTV8 | CURR | 15 | 2 | Budget of a Measure (App. Request Variant Was Replaced) | ||
13 | ![]() |
FREIGABE | WERTV8 | CURR | 15 | 2 | Release | ||
14 | ![]() |
AUFTRANF | WERTV8 | CURR | 15 | 2 | Residual order plan | ||
15 | ![]() |
FESTPROBL | WERTV8 | CURR | 15 | 2 | Fixed price commitment | ||
16 | ![]() |
KSTOBLGES | WERTV8 | CURR | 15 | 2 | Total cost commitment | ||
17 | ![]() |
ISTKOSTEN | WERTV8 | CURR | 15 | 2 | Actual costs | ||
18 | ![]() |
ISTERLOESE | WERTV8 | CURR | 15 | 2 | Actual revenues | ||
19 | ![]() |
KZHLNG | WERTV8 | CURR | 15 | 2 | Total credit side payments (down payments and payments) | ||
20 | ![]() |
DZHLNG | WERTV8 | CURR | 15 | 2 | Total debit side payments (down payments and payments) | ||
21 | ![]() |
0 | 0 | Progress Calculation: All | |||||
22 | ![]() |
0 | 0 | Progress Analysis: Values | |||||
23 | ![]() |
EVPLANORG1 | WERTV8 | CURR | 15 | 2 | Budgeted cost of work scheduled | ||
24 | ![]() |
EVACTORG1 | WERTV8 | CURR | 15 | 2 | Budgeted cost of work performed | ||
25 | ![]() |
EVACTCORR1 | WERTV8 | CURR | 15 | 2 | Budgeted cost of work performed, adjusted | ||
26 | ![]() |
0 | 0 | Progress Analysis: Quantities | |||||
27 | ![]() |
EVPLANQUANORG1 | CQUA8 | QUAN | 15 | 3 | Budgeted cost of work scheduled, quantity | ||
28 | ![]() |
EV_PLAN_QUAN_ORG1_UNIT | MEINS | UNIT | 3 | 0 | BCWS, Unit of Measure | * | |
29 | ![]() |
EVACTQUANORG1 | CQUA8 | QUAN | 15 | 3 | Budgeted cost of work performed, quantity | ||
30 | ![]() |
EV_ACT_QUAN_ORG1_UNIT | MEINS | UNIT | 3 | 0 | BCWP, Unit of Measure | * | |
31 | ![]() |
EVACTQUANCORR1 | CQUA8 | QUAN | 15 | 3 | Budgeted cost of work performed, adjusted quantity | ||
32 | ![]() |
EV_ACT_QUAN_CORR1_UNIT | MEINS | UNIT | 3 | 0 | BCWP, Adjusted Quantity (Unit) | * | |
33 | ![]() |
0 | 0 | Progress Analysis: Percentage of completion (POC) | |||||
34 | ![]() |
POCPLANORGAGG1 | EV_PROGRES | DEC | 6 | 3 | Aggregate planned percentage of completion | ||
35 | ![]() |
POCPLANORGNAGG1 | EV_PROGRES | DEC | 6 | 3 | Non-aggregated planned percentage of completion | ||
36 | ![]() |
POCACTORGAGG1 | EV_PROGRES | DEC | 6 | 3 | Aggregated actual POC | ||
37 | ![]() |
POCACTORGNAGG1 | EV_PROGRES | DEC | 6 | 3 | Non-aggregated actual percentage of completion | ||
38 | ![]() |
POCACTCORRAGG1 | EV_PROGRES | DEC | 6 | 3 | Adjusted aggregated actual POC | ||
39 | ![]() |
POCACTCORRNAGG1 | EV_PROGRES | DEC | 6 | 3 | Adjusted non-aggregated actual percentage of completion | ||
40 | ![]() |
EWALVARORG | WERTV8 | CURR | 15 | 2 | Cost Variance Based on EV_ACT_ORG1 | ||
41 | ![]() |
EVSCHVARORG | WERTV8 | CURR | 15 | 2 | Schedule Variance Based on EV_ACT_ORG1 | ||
42 | ![]() |
EWALINDXORG | DEC5_2 | DEC | 7 | 2 | Cost Index Based on EV_ACT_ORG1 | ||
43 | ![]() |
EVSCHINDXORG | DEC5_2 | DEC | 7 | 2 | Date Index Based on POC_ACT_ORG_AGG1 | ||
44 | ![]() |
EWALVARCORR | WERTV8 | CURR | 15 | 2 | Cost Variance Based on EV_ACT_CORR1 | ||
45 | ![]() |
EVSCHVARCORR | WERTV8 | CURR | 15 | 2 | Schedule Variance Based on EV_ACT_CORR1 | ||
46 | ![]() |
EWALINDXCORR | DEC5_2 | DEC | 7 | 2 | Cost Index Based on EV_ACT_CORR1 | ||
47 | ![]() |
EVSCHINDXCORR | DEC5_2 | DEC | 7 | 2 | Date Index Based on POC_ACT_CORR_AGG1 | ||
48 | ![]() |
0 | 0 | Append Structure: Progress Determination | |||||
49 | ![]() |
0 | 0 | Progress Determination (Object Currency) | |||||
50 | ![]() |
0 | 0 | Progress Analysis: Progress Values (PV; Object Currency) | |||||
51 | ![]() |
EVPLANORG1 | WERTV8 | CURR | 15 | 2 | Budgeted cost of work scheduled | ||
52 | ![]() |
EVACTORG1 | WERTV8 | CURR | 15 | 2 | Budgeted cost of work performed | ||
53 | ![]() |
EVACTCORR1 | WERTV8 | CURR | 15 | 2 | Budgeted cost of work performed, adjusted | ||
54 | ![]() |
EWALVARORG | WERTV8 | CURR | 15 | 2 | Cost Variance Based on EV_ACT_ORG1 | ||
55 | ![]() |
EVSCHVARORG | WERTV8 | CURR | 15 | 2 | Schedule Variance Based on EV_ACT_ORG1 | ||
56 | ![]() |
EWALVARCORR | WERTV8 | CURR | 15 | 2 | Cost Variance Based on EV_ACT_CORR1 | ||
57 | ![]() |
EVSCHVARCORR | WERTV8 | CURR | 15 | 2 | Schedule Variance Based on EV_ACT_CORR1 |
History
Last changed by/on | SAP | 20130529 |
SAP Release Created in |