SAP ABAP Data Element DADJ3 (Adjusting dates when dispatching planned orders)
Hierarchy
☛
BBPCRM (Software Component) BBPCRM
⤷ CRM (Application Component) Customer Relationship Management
⤷ CRM_APPLICATION (Package) All CRM Components Without Special Structure Packages
⤷ CX (Package) R/3 Application development: R/3 Scheduling
⤷ CRM (Application Component) Customer Relationship Management
⤷ CRM_APPLICATION (Package) All CRM Components Without Special Structure Packages
⤷ CX (Package) R/3 Application development: R/3 Scheduling
Basic Data
Data Element | DADJ3 |
Short Description | Adjusting dates when dispatching planned orders |
Data Type
Category of Dictionary Type | D | Domain |
Type of Object Referenced | No Information | |
Domain / Name of Reference Type | DADJ3 | |
Data Type | CHAR | Character String |
Length | 1 | |
Decimal Places | 0 | |
Output Length | 1 | |
Value Table |
Further Characteristics
Search Help: Name | ||
Search Help: Parameters | ||
Parameter ID | ||
Default Component name | ||
Change document | ||
No Input History | ||
Basic direction is set to LTR | ||
No BIDI Filtering |
Field Label
Length | Field Label | |
Short | 10 | Dispatch. |
Medium | 17 | Dispch.pl.ords |
Long | 25 | Dispatching plnd orders |
Heading | 10 | Dispatch. |
Documentation
Definition
You use this indicator to define how dependent requirements dates are to be adjusted when the basic dates in the planned order are adjusted. This is then used for dispatching the planned orders in the graphic planning table. Four options are available:
- The basic dates are always adjusted and the dependent requirements dates of the components are always set to the start dates of the operations.
- The basic dates are always adjusted and the dependent requirements dates of the components are set to the order start date of the planned order.
- The basic dates are only adjusted if a delay occurs (for example, if the dates gave to be postponed meaning that the delivery date cannot be adhered to), and the dependent requirements dates of the components are set to the start dates of the operations.
- The basic dates are only adjusted if a delay occurs and the dependent requirements dates of the components are set to the order start dates of the planned order.
When dispatching the planned order in the planning table, the order finish date is also adjusted.
Supplementary Documentation - DADJ3 0001
Dependencies
If you set the scheduling based on takts indicator, scheduling based on takts in Sequencing determines the planned order dates:
- Dates that have been determined by lead time scheduling are not overwritten by scheduling based on takts.
- The basic dates for planned orders that are determined in scheduling based on takts are not adjusted in lead time scheduling or finite scheduling. The stem automatically makes the requisite settings in the date adjustment screen section.
History
Last changed by/on | SAP | 19980728 |
SAP Release Created in |