Hierarchy
⤷ CRM-CIC (Application Component) Interaction Center WinClient
⤷ CO (Package) R/3 Application development: PP Production orders
Basic Data
Data Element | VSSZT |
Short Description | Propose dates |
Data Type
Category of Dictionary Type | D | Domain |
Type of Object Referenced | No Information | |
Domain / Name of Reference Type | XFELD | |
Data Type | CHAR | Character String |
Length | 1 | |
Decimal Places | 0 | |
Output Length | 1 | |
Value Table |
Further Characteristics
Search Help: Name | ||
Search Help: Parameters | ||
Parameter ID | ||
Default Component name | DATE_AND_TIME | |
Change document | ||
No Input History | ||
Basic direction is set to LTR | ||
No BIDI Filtering |
Field Label
Length | Field Label | |
Short | 10 | PrpseDates |
Medium | 15 | Propose dates |
Long | 20 | Propose dates |
Heading | 6 | Date |
Documentation
Definition
Specifies that for the confirmation of operations, the system is to propose the start and finish dates of the individual operation segments, as calculated by lead time scheduling.
Use
The system differentiates between the proposed dates before the first confirmation and the proposed dates before all other confirmations:
The following dates are proposed for the first confirmation:
- In the start of work field: The earliest start date of the operation or, if this date is in the future, the current date with the time
- In the end of work field: The current date with the time
The following dates are proposed for all other confirmation:
- In the start of work field: The actual finish of the last confirmation
- In the end of work field: The current date with the time
Supplementary Documentation - VSSZT 2100
Definition
In confirmation, the start and end dates for scheduling are determined as follows:
- Actual dates not available for operation
Start date: Earliest scheduled start date of the operation if the date is in the past. Otherwise, the system uses the current date.
End date: End date that you entered during the current session in the last confirmation. Otherwise, the system uses the current date.
- Actual dates available for operation
Start date: Actual end date of the operation. If the start date falls after the end date, the system uses the end date as the start date.
End date: End date that you entered during the current session in the last confirmation. Otherwise, the system uses the current date.
Supplementary Documentation - VSSZT 2500
Definition
Use this indicator to specify that start and finish dates calculated in scheduling should be the default values when confirming activities.