SAP ABAP Data Element UELAP (Overlap scheduling in the short-term area)
Hierarchy
☛
BBPCRM (Software Component) BBPCRM
⤷
CRM (Application Component) Customer Relationship Management
⤷
CRM_APPLICATION (Package) All CRM Components Without Special Structure Packages
⤷
MD03 (Package) Appl. development R/3 MPS/determin. requirements planning
⤷
⤷
⤷
Basic Data
| Data Element | UELAP |
| Short Description | Overlap scheduling in the short-term area |
Data Type
| Category of Dictionary Type | D | Domain |
| Type of Object Referenced | No Information | |
| Domain / Name of Reference Type | UELAP | |
| Data Type | CHAR | Character String |
| Length | 1 | |
| Decimal Places | 0 | |
| Output Length | 1 | |
| Value Table |
Further Characteristics
| Search Help: Name | ||
| Search Help: Parameters | ||
| Parameter ID | ||
| Default Component name | ||
| Change document | ||
| No Input History | ||
| Basic direction is set to LTR | ||
| No BIDI Filtering |
Field Label
| Length | Field Label | |
| Short | 10 | Overlpping |
| Medium | 15 | Overlapping |
| Long | 20 | Overlapping |
| Heading | 5 | Ovlpg |
Documentation
Definition
The overlapping indicator along with the cycle time in the material master record is used to split the planned orders into several partial quantities whereby the in-house production time overlaps by the cycle time.
You can determine whether,
- the planned orders are allowed to overlap in the future
- the planned orders are allowed to overlap in the past
- no overlapping is allowed
Use
You can define the overlapping for each lot-sizing procedure. Here, you must maintain the following additional parameters in the material master record:
- You must maintain the cycle time (MRP data screen) for all lot-sizing procedures. The cycle time defines the number of days that the planned orders are to overlap each other.
- For the fixed lot size, you must enter the partial quantity to be used for splitting in the field Rounding value.
- For all other lot-sizing procedures, you enter the partial quantity in the field entitled Maximum lot size.
Supplementary Documentation - UELAP 0001
Use
Procedure
Examples
Dependencies
The overlapping period is specified in the material master via the cycle time.
History
| Last changed by/on | SAP | 19950403 |
| SAP Release Created in |