SAP ABAP Data Element TERMX_RATE (Lead time scheduling (rate-based planning))
Hierarchy
BBPCRM (Software Component) BBPCRM
   CRM (Application Component) Customer Relationship Management
     CRM_APPLICATION (Package) All CRM Components Without Special Structure Packages
       CX (Package) R/3 Application development: R/3 Scheduling
Basic Data
Data Element TERMX_RATE
Short Description Lead time scheduling (rate-based planning)  
Data Type
Category of Dictionary Type D   Domain
Type of Object Referenced     No Information
Domain / Name of Reference Type XFELD    
Data Type CHAR   Character String 
Length 1    
Decimal Places 0    
Output Length 1    
Value Table      
Further Characteristics
Search Help: Name    
Search Help: Parameters    
Parameter ID   
Default Component name    
Change document    
No Input History    
Basic direction is set to LTR    
No BIDI Filtering    
Field Label
  Length  Field Label  
Short 10 Scheduling 
Medium 15 Scheduling 
Long 21 Scheduling 
Heading Sch 
Documentation

Definition

Specifies how the production dates are determined.

  • If the indicator has been set and a valid routing exists, lead time scheduling is carried out. The production dates are calculated from the floats in the scheduling margin key of the material master and the individual operation times in the routing.

    If the CapReqmnts indicator has also been set, capacity requirements are generated for the operations. The dates for the capacity requirements are the operation dates.

  • If the indicator has not been set, lead time scheduling is not carried out. The order basic dates are determined from the in-house production time in the material master and used as production dates.

    If the CapReqmnts indicator has also been set, capacity requirements are generated for the operations. The dates for the capacity requirements are the operation dates.

In detailed scheduling you can choose between differnt scheduling types. In rate-based scheduling and rough-cut scheduling backward scheduling is used.

Supplementary Documentation - TERMX_RATE0001

Dependencies

If you set the scheduling based on takts indicator, scheduling based on takts in Sequencing determines the planned order dates:

  • Dates that have been determined by lead time scheduling are not overwritten by scheduling based on takts.
  • The basic dates for planned orders that are determined in scheduling based on takts are not adjusted in lead time scheduling or finite scheduling. The stem automatically makes the requisite settings in the date adjustment screen section.