SAP ABAP Data Element RED_ART (Reduction type)
Hierarchy
BBPCRM (Software Component) BBPCRM
   CRM (Application Component) Customer Relationship Management
     CRM_APPLICATION (Package) All CRM Components Without Special Structure Packages
       CX (Package) R/3 Application development: R/3 Scheduling
Basic Data
Data Element RED_ART
Short Description Reduction type  
Data Type
Category of Dictionary Type D   Domain
Type of Object Referenced     No Information
Domain / Name of Reference Type RED_ART    
Data Type CHAR   Character String 
Length 1    
Decimal Places 0    
Output Length 1    
Value Table      
Further Characteristics
Search Help: Name    
Search Help: Parameters    
Parameter ID   
Default Component name    
Change document    
No Input History    
Basic direction is set to LTR    
No BIDI Filtering    
Field Label
  Length  Field Label  
Short 10 RedType 
Medium 15 Reduction type 
Long 20 Reduction type 
Heading 15 Reduction type 
Documentation

Definition

Defines which operations are taken into account for the reduction of the lead time of the following objects:

Use

You can choose between the following reduction types:

  • Reduction of all operations

The reduction measures are carried out step-for-step for all operations until the whole lead time has been suficiently reduced. After reduction all the operations have the same reduction level.

  • Reduction of operations on the critical path

    You can only use this type of reduction for

    • Collective orders
    • Routings, planned orders and production orders that contain parallel sequences
    • Networks

      In each reduction step, reduction measures are only applied to those operations, for which a reduction of the lead time results in a reduction of the whole lead time. In collective orders and orders with parallel sequences, the sum of these operations is known as the critical path. Since there can be different critical paths for each reduction step, operations can have different reduction levels before a sufficent reduction of the whole lead time is achieved.

In both types of reduction the order floats are reduced according to their settings.

Dependencies

In routings, planned orders and productions orders that are not part of a collective order and do not contain parallel sequences, there is no critical path and consequently the second type of reduction has no effect, reduction of all operations is used.

Notes

Reduction of operations on the critical path makes greater demands on the system than standard reduction and can cause a reduction in performance.

History
Last changed by/on SAP  19980706 