SAP ABAP Data Element PHORI (Scheduling horizon (detailed planning))
Hierarchy
BBPCRM (Software Component) BBPCRM
   CRM (Application Component) Customer Relationship Management
     CRM_APPLICATION (Package) All CRM Components Without Special Structure Packages
       CX (Package) R/3 Application development: R/3 Scheduling
Basic Data
Data Element PHORI
Short Description Scheduling horizon (detailed planning)  
Data Type
Category of Dictionary Type D   Domain
Type of Object Referenced     No Information
Domain / Name of Reference Type NUMC3    
Data Type NUMC   Character string with only digits 
Length 3    
Decimal Places 0    
Output Length 3    
Value Table      
Further Characteristics
Search Help: Name    
Search Help: Parameters    
Parameter ID   
Default Component name    
Change document    
No Input History    
Basic direction is set to LTR    
No BIDI Filtering    
Field Label
  Length  Field Label  
Short 10 Schd.hor.d 
Medium 16 Sched. hor.det. 
Long 40 Scheduling horizon (detailed planning) 
Heading 11 Sch.H det. 
Documentation

Definition

The scheduling horizon is a time period that is in working days.

  • If a planned order has its basic start date within this period in the future, lead time scheduling is carried out using the selected routing.

    The production times are calculated from the float times of the scheduling margin key in the material master record and the the time from the individual operations.

  • If a planned order has its basic start date further in the future than this scheduling horizon, the basic dates are calculated from the in-house production times in the material master and are transfered to the production times.

Note

For performance reasons it is advisable to use the scheduling horizon to limit the period for which lead time scheduling and capacity planning should be carried out.

Dependencies

The scheduling horizon is only in effect, if the Scheduling indicator has been set.

Supplementary Documentation - PHORI 0001

Use

Procedure

Examples

Dependencies

The scheduling period for detailed planning can only be determined or changed in the workstep, "Parameters for detailed schdeduling". The value maintained there per plant, order group, type and production scheduler is only displayed in the workstep, "Define scheduling levels".

History
Last changed by/on SAP  19971020 
SAP Release Created in