SAP ABAP Data Element MAT_PRKST (Material planning in networks: primary costs)
Hierarchy
BBPCRM (Software Component) BBPCRM
   PS-COS-PLN-CAL (Application Component) Costing
     KPKA (Package) Projects: Costing networks
Basic Data
Data Element MAT_PRKST
Short Description Material planning in networks: primary costs  
Data Type
Category of Dictionary Type D   Domain
Type of Object Referenced     No Information
Domain / Name of Reference Type PRKST    
Data Type CURR   Currency field, stored as DEC 
Length 11    
Decimal Places 2    
Output Length 15    
Value Table      
Further Characteristics
Search Help: Name    
Search Help: Parameters    
Parameter ID   
Default Component name    
Change document    
No Input History    
Basic direction is set to LTR    
No BIDI Filtering    
Field Label
  Length  Field Label  
Short 10 Mat.plang 
Medium 15 Mat.planning 
Long 20 Material planning 
Heading 10 Mat.plang 
Documentation

Definition

Amount of forecast material costs, in controlling area currency.

Use

You can use the amount maintained here to plan material costs for an activity at an early planning stage, even when not all the details for the material components are available.

If you later add material components for the activity, in the information system the amount of the material components is subtracted from the planning amount until it has been completely used up.

Example

For the internally processed activity, you plan material costs of $2000. The expected material costs for the cost element stored in the network profile are then recorded in the activity.

Later, you assign a total of $1500 in raw material components to the activity. The following values are then recorded in the activity:

Raw material    $1500

Expected material costs    $500

History
Last changed by/on SAP  19981210 