Data Element | CO_FLG_UPD |
Short Description | Adjustment of Operation/Component Quantities to Act. Values |
Data Type
Category of Dictionary Type | D | Domain |
Type of Object Referenced | No Information | |
Domain / Name of Reference Type | XFELD | |
Data Type | CHAR | Character String |
Length | 1 | |
Decimal Places | 0 | |
Output Length | 1 | |
Value Table |
Further Characteristics
Search Help: Name | ||
Search Help: Parameters | ||
Parameter ID | ||
Default Component name | ||
Change document | ||
No Input History | ||
Basic direction is set to LTR | ||
No BIDI Filtering |
Field Label
Length | Field Label | |
Short | 10 | QtyAdjust |
Medium | 20 | QtyAdjustActualVals |
Long | 40 | Adjustment quants in order to act. vals |
Heading | 0 |
Documentation
Definition
Determines that the following planned data in a production order is adjusted to the actual values in a confirmation:
- Operation quantities
- Component quantities
Use
You enter a partial confirmation with a larger yield than planned for an operation, or a final confirmation with a smaller or larger yield than planned. That is, a quantity that varies from the difference between the operation quantity and the planned scrap quantity in the operation. The system reacts as follows:
- If the indicator is set, the operation quantities in the order are adjusted to the actual quantities just confirmed. This applies to all operations in the production order that come after the operation just confirmed in the sequence of operations. The system carries out a quantity calculation that also takes into account the planned scrap of these operations. Also the quantities of the components that are assigned to these operations. With the operation and component quantities, all dependent objects such as purchase requisitions, capacity requirements and transport requests are adjusted.
Purchase orders are not adjusted. You can however, trigger a workflow task that informs the purchasing department that a purchase order contains an incorrect quantity.
After confirmation, the order is rescheduled in the background.
The order is not costed automatically because, after adjustment, the planned values no longer correspond to the original planned values. The order is also not costed again, if it has been set up elsewhere in the system in this way.
- If the indicator is not set, the planned values in the order remain unchanged.
Dependencies
This procedure does not apply to dependent orders in a collective order. Dependent orders are never adjusted. The quantities are not changed for any directly produced components that may exist, whereas the other components are adjusted.
History
Last changed by/on | SAP | 20000104 |