Hierarchy
⤷ CA (Application Component) Cross-Application Components
⤷ PM_PS_INTEGRATION (Package) PM/PS Interface
Basic Data
Data Element | ADCOMPARE |
Short Description | PM/PS Reference Element |
Data Type
Category of Dictionary Type | D | Domain |
Type of Object Referenced | No Information | |
Domain / Name of Reference Type | ADDCOMPARE | |
Data Type | CHAR | Character String |
Length | 40 | |
Decimal Places | 0 | |
Output Length | 40 | |
Value Table | ADCOMP |
Further Characteristics
Search Help: Name | ADCP | |
Search Help: Parameters | ADPSP | |
Parameter ID | ||
Default Component name | ||
Change document | ||
No Input History | ||
Basic direction is set to LTR | ||
No BIDI Filtering |
Field Label
Length | Field Label | |
Short | 10 | Ref. Elem. |
Medium | 20 | PM/PS Ref. Element |
Long | 30 | PM/PS Reference Element |
Heading | 0 |
Documentation
Definition
Allows a logical connection between the maintenance/service order and network operations or WBS elements.
Supplementary Documentation - ADCOMPARE 0001
Use
Dependencies
The value entered here is copied automatically to the field "PM/PS reference element" in the maintenance plan item during inclusion of the task list in the maintenance plan.
If the maintenance order is scheduled, the value is passed to the PM/CS order when you create it.
Example
Supplementary Documentation - ADCOMPARE 0002
Use
The value entered here is copied automatically to the respective PM/CS order during scheduling of the maintenance plan.
Dependencies
On including a task list, the value entered in the field "PM/PS reference element in the task list header is copied automatically.
However, you can change the value afterwards in the maintenance plan.
Example
Supplementary Documentation - ADCOMPARE 0003
Use
The value entered here is used to automatically assign WBS elements to the PM/CS order and/or network activities to a maintenance project.
Dependencies
The displayed value is either
- copied automatically from the respective maintenance plan item, or
- entered manually.
You can overwrite the value.
Automatic assignment of a WBS element and/or a network activity is only possible if the same value that is specified in the PM/CS order is also maintained in the WBS element and/or network activity.
Example
Supplementary Documentation - ADCOMPARE 0004
Use
The value entered here is used to assign a PM/CS order automatically to the WBS element
Dependencies
When you create an operational project, the specified value is copied to the operational project from the identically-named field in the respective WBS element.
Example
Supplementary Documentation - ADCOMPARE 0005
Use
The value entered here is used to assign a PM/CS order automatically to a network activity.
Dependencies
When you create an operational network, the maintained value is copied automatically from the identically-named field of the respective operational network activity.
Example
Supplementary Documentation - ADCOMPARE 0006
Use
The value entered here is used to assign a PM/CS order automatically to the WBS element.
Dependencies
This automatic assignment is only possible if the value maintained for the WBS-element is identical to the value maintained in the field of the same name in the PM/CS order.
Example
Supplementary Documentation - ADCOMPARE 0007
Use
The value entered here is used to assign a PM/CS order automatically to the network activity.
Dependencies
Automatic assignment of a PM order to this network activity is only possible if the value maintained for the network activity is identical to the value maintained in the field of the same name in the PM/CS order.
Example
Supplementary Documentation - ADCOMPARE 0008
Use
Enter a field value for the PM/PS reference element here.
Dependencies
Example
History
Last changed by/on | SAP | 20050411 |
SAP Release Created in |