| # | Object Type | Object Name | Object Description | Note |
|---|---|---|---|---|
| 1 | CAL_PR_KAL - KALID | Factory Calendar | ||
| 2 | PRPS - FABKL | Factory calendar key | ||
| 3 | PRPS - LOEVM | Deletion Indicator | ||
| 4 | PRPS - OBJNR | Object number | ||
| 5 | PRPS - POSID | Work Breakdown Structure Element (WBS Element) | ||
| 6 | PRPS - POST1 | PS: Short description (first text line) | ||
| 7 | PRPS - PSPNR | WBS Element | ||
| 8 | PRPS - PSPRI | Priority | ||
| 9 | PRPS - STUFE | Level in project hierarchy | ||
| 10 | PRPS - TXTSP | Language Key | ||
| 11 | PRPS - USR00 | 1st user field for 20 characters - WBS element- | ||
| 12 | PRPS - USR01 | 2nd user field 20 digits - WBS element | ||
| 13 | PRPS - USR02 | 3rd user-defined field 10 digits -WBS element | ||
| 14 | PRPS - USR03 | 4th user-defined field 10 digits -WBS element | ||
| 15 | PRPS - USR04 | 1st user-defined field for quantity(length 10,3) WBS element | ||
| 16 | PRPS - USR05 | 2nd use field for quantity (length 10,3) WBS element | ||
| 17 | PRPS - USR06 | 1st user field for values (length 10,3) WBS element | ||
| 18 | PRPS - USR07 | 2nd user field for values (length 10,3) -WBS element | ||
| 19 | PRPS - USR08 | 1st user field for date -WBS element | ||
| 20 | PRPS - USR09 | 2nd user field for date -WBS element | ||
| 21 | PRPS - USR10 | 1st user field for 'Ind. for evaluations' WBS elem. | ||
| 22 | PRPS - USR11 | 2nd user field for 'Indicator for eval.s' WBS elemnt | ||
| 23 | PRPS - VERNA | Name of responsible person (Project manager) | ||
| 24 | PRPS - VERNR | Number of the responsible person (project manager) | ||
| 25 | PRPS2_INC - FABKL | Factory calendar key | ||
| 26 | PRPS2_INC - LOEVM | Deletion Indicator | ||
| 27 | PRPS2_INC - PSPRI | Priority | ||
| 28 | PRPS2_INC - STUFE | Level in project hierarchy | ||
| 29 | PRPS2_INC - TXTSP | Language Key | ||
| 30 | PRPS2_INC - USR00 | 1st user field for 20 characters - WBS element- | ||
| 31 | PRPS2_INC - USR01 | 2nd user field 20 digits - WBS element | ||
| 32 | PRPS2_INC - USR02 | 3rd user-defined field 10 digits -WBS element | ||
| 33 | PRPS2_INC - USR03 | 4th user-defined field 10 digits -WBS element | ||
| 34 | PRPS2_INC - USR04 | 1st user-defined field for quantity(length 10,3) WBS element | ||
| 35 | PRPS2_INC - USR05 | 2nd use field for quantity (length 10,3) WBS element | ||
| 36 | PRPS2_INC - USR06 | 1st user field for values (length 10,3) WBS element | ||
| 37 | PRPS2_INC - USR07 | 2nd user field for values (length 10,3) -WBS element | ||
| 38 | PRPS2_INC - USR08 | 1st user field for date -WBS element | ||
| 39 | PRPS2_INC - USR09 | 2nd user field for date -WBS element | ||
| 40 | PRPS2_INC - USR10 | 1st user field for 'Ind. for evaluations' WBS elem. | ||
| 41 | PRPS2_INC - USR11 | 2nd user field for 'Indicator for eval.s' WBS elemnt | ||
| 42 | PRPS2_INC - VERNA | Name of responsible person (Project manager) | ||
| 43 | PRPS2_INC - VERNR | Number of the responsible person (project manager) | ||
| 44 | PRPS_BALK - FABKL | Factory calendar key | ||
| 45 | PRPS_BALK - LOEVM | Deletion Indicator | ||
| 46 | PRPS_BALK - OBJNR | Object number | ||
| 47 | PRPS_BALK - POSID | Work Breakdown Structure Element (WBS Element) | ||
| 48 | PRPS_BALK - POST1 | PS: Short description (first text line) | ||
| 49 | PRPS_BALK - PSPNR | WBS Element | ||
| 50 | PRPS_BALK - PSPRI | Priority | ||
| 51 | PRPS_BALK - STUFE | Level in project hierarchy | ||
| 52 | PRPS_BALK - TXTSP | Language Key | ||
| 53 | PRPS_BALK - USR00 | 1st user field for 20 characters - WBS element- | ||
| 54 | PRPS_BALK - USR01 | 2nd user field 20 digits - WBS element | ||
| 55 | PRPS_BALK - USR02 | 3rd user-defined field 10 digits -WBS element | ||
| 56 | PRPS_BALK - USR03 | 4th user-defined field 10 digits -WBS element | ||
| 57 | PRPS_BALK - USR04 | 1st user-defined field for quantity(length 10,3) WBS element | ||
| 58 | PRPS_BALK - USR05 | 2nd use field for quantity (length 10,3) WBS element | ||
| 59 | PRPS_BALK - USR06 | 1st user field for values (length 10,3) WBS element | ||
| 60 | PRPS_BALK - USR07 | 2nd user field for values (length 10,3) -WBS element | ||
| 61 | PRPS_BALK - USR08 | 1st user field for date -WBS element | ||
| 62 | PRPS_BALK - USR09 | 2nd user field for date -WBS element | ||
| 63 | PRPS_BALK - USR10 | 1st user field for 'Ind. for evaluations' WBS elem. | ||
| 64 | PRPS_BALK - USR11 | 2nd user field for 'Indicator for eval.s' WBS elemnt | ||
| 65 | PRPS_BALK - VERNA | Name of responsible person (Project manager) | ||
| 66 | PRPS_BALK - VERNR | Number of the responsible person (project manager) | ||
| 67 | PRPS_INC - FABKL | Factory calendar key | ||
| 68 | PRPS_INC - LOEVM | Deletion Indicator | ||
| 69 | PRPS_INC - OBJNR | Object number | ||
| 70 | PRPS_INC - POSID | Work Breakdown Structure Element (WBS Element) | ||
| 71 | PRPS_INC - POST1 | PS: Short description (first text line) | ||
| 72 | PRPS_INC - PSPRI | Priority | ||
| 73 | PRPS_INC - STUFE | Level in project hierarchy | ||
| 74 | PRPS_INC - TXTSP | Language Key | ||
| 75 | PRPS_INC - USR00 | 1st user field for 20 characters - WBS element- | ||
| 76 | PRPS_INC - USR01 | 2nd user field 20 digits - WBS element | ||
| 77 | PRPS_INC - USR02 | 3rd user-defined field 10 digits -WBS element | ||
| 78 | PRPS_INC - USR03 | 4th user-defined field 10 digits -WBS element | ||
| 79 | PRPS_INC - USR04 | 1st user-defined field for quantity(length 10,3) WBS element | ||
| 80 | PRPS_INC - USR05 | 2nd use field for quantity (length 10,3) WBS element | ||
| 81 | PRPS_INC - USR06 | 1st user field for values (length 10,3) WBS element | ||
| 82 | PRPS_INC - USR07 | 2nd user field for values (length 10,3) -WBS element | ||
| 83 | PRPS_INC - USR08 | 1st user field for date -WBS element | ||
| 84 | PRPS_INC - USR09 | 2nd user field for date -WBS element | ||
| 85 | PRPS_INC - USR10 | 1st user field for 'Ind. for evaluations' WBS elem. | ||
| 86 | PRPS_INC - USR11 | 2nd user field for 'Indicator for eval.s' WBS elemnt | ||
| 87 | PRPS_INC - VERNA | Name of responsible person (Project manager) | ||
| 88 | PRPS_INC - VERNR | Number of the responsible person (project manager) | ||
| 89 | PRTE - EDAUR | Forecasted length (duration) of the WBS element | ||
| 90 | PRTE - EEINH | Unit for duration of WBS element planned dates | ||
| 91 | PRTE - EENDE | Forecasted finish date of the WBS element | ||
| 92 | PRTE - EETRM | Scheduled finish date (Forecast) | ||
| 93 | PRTE - ESTRM | Scheduled start date (Forecast) | ||
| 94 | PRTE - ESTRT | Forecasted start date of the WBS element | ||
| 95 | PRTE - IDAUR | Actual length (duration) of the WBS element | ||
| 96 | PRTE - IEINH | Unit for duration of actual WBS element dates | ||
| 97 | PRTE - IENDE | Actual finish date of the WBS element | ||
| 98 | PRTE - ISTRT | Actual start date for the WBS element | ||
| 99 | PRTE - PDAUR | Length (duration) of the basic dates in the WBS element | ||
| 100 | PRTE - PEINH | Unit for duration of basic WBS element dates | ||
| 101 | PRTE - PENDE | WBS element: Basic finish date | ||
| 102 | PRTE - PETRM | Scheduled finish (Basic) | ||
| 103 | PRTE - PSTRM | Scheduled start (Basic) | ||
| 104 | PRTE - PSTRT | WBS element: Basic start date | ||
| 105 | PRTEB - EDAUR | Forecasted length (duration) of the WBS element | ||
| 106 | PRTEB - EEINH | Unit for duration of WBS element planned dates | ||
| 107 | PRTEB - EENDE | Forecasted finish date of the WBS element | ||
| 108 | PRTEB - EETRM | Scheduled finish date (Forecast) | ||
| 109 | PRTEB - ESTRM | Scheduled start date (Forecast) | ||
| 110 | PRTEB - ESTRT | Forecasted start date of the WBS element | ||
| 111 | PRTEB - IDAUR | Actual length (duration) of the WBS element | ||
| 112 | PRTEB - IEINH | Unit for duration of actual WBS element dates | ||
| 113 | PRTEB - IENDE | Actual finish date of the WBS element | ||
| 114 | PRTEB - ISTRT | Actual start date for the WBS element | ||
| 115 | PRTEB - PDAUR | Length (duration) of the basic dates in the WBS element | ||
| 116 | PRTEB - PEINH | Unit for duration of basic WBS element dates | ||
| 117 | PRTEB - PENDE | WBS element: Basic finish date | ||
| 118 | PRTEB - PETRM | Scheduled finish (Basic) | ||
| 119 | PRTEB - PSTRM | Scheduled start (Basic) | ||
| 120 | PRTEB - PSTRT | WBS element: Basic start date | ||
| 121 | PRTEINC - EDAUR | Forecasted length (duration) of the WBS element | ||
| 122 | PRTEINC - EEINH | Unit for the length (duration) of the WBS element | ||
| 123 | PRTEINC - EENDE | Forecasted finish date of the WBS element | ||
| 124 | PRTEINC - EETRM | Scheduled finish date (Forecast) | ||
| 125 | PRTEINC - ESTRM | Scheduled start date (Forecast) | ||
| 126 | PRTEINC - ESTRT | Forecasted start date of the WBS element | ||
| 127 | PRTEINC - IDAUR | Actual length (duration) of the WBS element | ||
| 128 | PRTEINC - IEINH | Unit for the length (duration) of the WBS element | ||
| 129 | PRTEINC - IENDE | Actual finish date of the WBS element | ||
| 130 | PRTEINC - ISTRT | Actual start date for the WBS element | ||
| 131 | PRTEINC - PDAUR | Length (duration) of the basic dates in the WBS element | ||
| 132 | PRTEINC - PEINH | Unit for the length (duration) of the WBS element | ||
| 133 | PRTEINC - PENDE | WBS element: Basic finish date | ||
| 134 | PRTEINC - PETRM | Scheduled finish (Basic) | ||
| 135 | PRTEINC - PSTRM | Scheduled start (Basic) | ||
| 136 | PRTEINC - PSTRT | WBS element: Basic start date | ||
| 137 | RCJ_PS_PLAN - DATFS | Earliest start date | ||
| 138 | RCJ_PS_PLAN - DATSE | Latest finish date | ||
| 139 | RCJ_PS_PLAN - ECKEN | Finish date (from basic dates) | ||
| 140 | RCJ_PS_PLAN - ECKST | Basic start date | ||
| 141 | RCJ_PS_PLAN - EDAUEH | Actual duration unit | ||
| 142 | RCJ_PS_PLAN - EDAUER | Duration | ||
| 143 | RCJ_PS_PLAN - IDAUEH | Actual duration unit | ||
| 144 | RCJ_PS_PLAN - IDAUER | Actual duration | ||
| 145 | RCJ_PS_PLAN - ISTEN | Actual finish date | ||
| 146 | RCJ_PS_PLAN - ISTST | Actual start date | ||
| 147 | RCJ_PS_PLAN - KURZTEXT | Short text/description of the object | ||
| 148 | RCJ_PS_PLAN - OBJEKTID | ID/Object key | ||
| 149 | RCJ_PS_PLAN - OBJEKTTYP | Object Type Text | ||
| 150 | RCJ_PS_PLAN - PDAUEH | Actual duration unit | ||
| 151 | RCJ_PS_PLAN - PDAUER | Forecast duration | ||
| 152 | RCJ_PS_PLAN - PROGEN | Forecast finish date | ||
| 153 | RCJ_PS_PLAN - PROGST | Forecast start date | ||
| 154 | RCJ_PS_PLAN - PSPRI | Priority | ||
| 155 | RCJ_PS_PLAN - STATXT | Edited status text | ||
| 156 | RCJ_PS_PLAN - STUFE | Level in project hierarchy | ||
| 157 | RCJ_PS_PLAN - TEENFR | Earliest scheduled finish (from basic dates) | ||
| 158 | RCJ_PS_PLAN - TEENSP | Latest scheduled finish (from basic dates) | ||
| 159 | RCJ_PS_PLAN - TESTFR | Earliest scheduled start (from basic dates) | ||
| 160 | RCJ_PS_PLAN - TESTSP | Latest scheduled start (from basic dates) | ||
| 161 | RCJ_PS_PLAN - TPENFR | Earliest scheduled finish (from forecast dates) | ||
| 162 | RCJ_PS_PLAN - TPENSP | Latest scheduled finish (from forecast dates) | ||
| 163 | RCJ_PS_PLAN - TPSTFR | Earliest scheduled start (from forecast dates) | ||
| 164 | RCJ_PS_PLAN - TPSTSP | Latest scheduled start (from forecast dates) | ||
| 165 | RCJ_PS_PLAN - USR00 | User field with 20 characters | ||
| 166 | RCJ_PS_PLAN - USR01 | User field with 20 characters | ||
| 167 | RCJ_PS_PLAN - USR02 | User field with 10 characters | ||
| 168 | RCJ_PS_PLAN - USR03 | User field with 10 characters | ||
| 169 | RCJ_PS_PLAN - USR04 | User field for quantity (length 10.3) | ||
| 170 | RCJ_PS_PLAN - USR05 | User field for quantity (length 10.3) | ||
| 171 | RCJ_PS_PLAN - USR06 | User-defined field for values (length 10,3) | ||
| 172 | RCJ_PS_PLAN - USR07 | User-defined field for values (length 10,3) | ||
| 173 | RCJ_PS_PLAN - USR08 | User field for date | ||
| 174 | RCJ_PS_PLAN - USR09 | User field for date | ||
| 175 | RCJ_PS_PLAN - USR10 | User-defined field: Indicator for reports | ||
| 176 | RCJ_PS_PLAN - USR11 | User-defined field: Indicator for reports | ||
| 177 | RCJ_PS_PLAN - VERNA | Name of responsible person (Project manager) | ||
| 178 | RCJ_PS_PLAN - VERNR | Number of responsible person (project mgr)/MRP controller | ||
| 179 | RCJ_PS_PLAN_EXT - OBJNR | Object number | ||
| 180 | RCJ_PS_PLAN_EXT - UNTRG | Indicator: Element is subdivided | ||
| 181 | RCJ_PS_PPT - ACIND | Doc. table index for activities | ||
| 182 | RCJ_PS_PPT - DATFS | Earliest start date | ||
| 183 | RCJ_PS_PPT - DATSE | Latest finish date | ||
| 184 | RCJ_PS_PPT - ECKEN | Finish date (from basic dates) | ||
| 185 | RCJ_PS_PPT - ECKST | Basic start date | ||
| 186 | RCJ_PS_PPT - EDAUEH | Actual duration unit | ||
| 187 | RCJ_PS_PPT - EDAUER | Duration | ||
| 188 | RCJ_PS_PPT - EINRUECK | Level in project hierarchy | ||
| 189 | RCJ_PS_PPT - FLIND | Index referring to record table for sequences | ||
| 190 | RCJ_PS_PPT - HAS_TEXT | Selection flag | ||
| 191 | RCJ_PS_PPT - IDAUEH | Actual duration unit | ||
| 192 | RCJ_PS_PPT - IDAUER | Actual duration | ||
| 193 | RCJ_PS_PPT - ISTEN | Actual finish date | ||
| 194 | RCJ_PS_PPT - ISTST | Actual start date | ||
| 195 | RCJ_PS_PPT - KURZTEXT | Short text/description of the object | ||
| 196 | RCJ_PS_PPT - LOEVM | Selection flag | ||
| 197 | RCJ_PS_PPT - MSIND | Document table index for milestones | ||
| 198 | RCJ_PS_PPT - NWIND | Document table index for networks | ||
| 199 | RCJ_PS_PPT - OBJECT | Selection flag | ||
| 200 | RCJ_PS_PPT - OBJEKTID | ID/Object key | ||
| 201 | RCJ_PS_PPT - OBJEKTTYP | Object Type Text | ||
| 202 | RCJ_PS_PPT - OBJNR | Object number | ||
| 203 | RCJ_PS_PPT - PDAUEH | Actual duration unit | ||
| 204 | RCJ_PS_PPT - PDAUER | Forecast duration | ||
| 205 | RCJ_PS_PPT - PROGEN | Forecast finish date | ||
| 206 | RCJ_PS_PPT - PROGST | Forecast start date | ||
| 207 | RCJ_PS_PPT - PSIND | Document table index for WBS elements | ||
| 208 | RCJ_PS_PPT - PSPNR | WBS Element | ||
| 209 | RCJ_PS_PPT - PSPRI | Priority | ||
| 210 | RCJ_PS_PPT - STATXT | Edited status text | ||
| 211 | RCJ_PS_PPT - STUFE | Level in project hierarchy | ||
| 212 | RCJ_PS_PPT - TEENFR | Earliest scheduled finish (from basic dates) | ||
| 213 | RCJ_PS_PPT - TEENSP | Latest scheduled finish (from basic dates) | ||
| 214 | RCJ_PS_PPT - TESTFR | Earliest scheduled start (from basic dates) | ||
| 215 | RCJ_PS_PPT - TESTSP | Latest scheduled start (from basic dates) | ||
| 216 | RCJ_PS_PPT - TPENFR | Earliest scheduled finish (from forecast dates) | ||
| 217 | RCJ_PS_PPT - TPENSP | Latest scheduled finish (from forecast dates) | ||
| 218 | RCJ_PS_PPT - TPSTFR | Earliest scheduled start (from forecast dates) | ||
| 219 | RCJ_PS_PPT - TPSTSP | Latest scheduled start (from forecast dates) | ||
| 220 | RCJ_PS_PPT - UNTRG | Indicator: Element is subdivided | ||
| 221 | RCJ_PS_PPT - USR00 | User field with 20 characters | ||
| 222 | RCJ_PS_PPT - USR01 | User field with 20 characters | ||
| 223 | RCJ_PS_PPT - USR02 | User field with 10 characters | ||
| 224 | RCJ_PS_PPT - USR03 | User field with 10 characters | ||
| 225 | RCJ_PS_PPT - USR04 | User field for quantity (length 10.3) | ||
| 226 | RCJ_PS_PPT - USR05 | User field for quantity (length 10.3) | ||
| 227 | RCJ_PS_PPT - USR06 | User-defined field for values (length 10,3) | ||
| 228 | RCJ_PS_PPT - USR07 | User-defined field for values (length 10,3) | ||
| 229 | RCJ_PS_PPT - USR08 | User field for date | ||
| 230 | RCJ_PS_PPT - USR09 | User field for date | ||
| 231 | RCJ_PS_PPT - USR10 | User-defined field: Indicator for reports | ||
| 232 | RCJ_PS_PPT - USR11 | User-defined field: Indicator for reports | ||
| 233 | RCJ_PS_PPT - VEIND | Doc. table index for activities | ||
| 234 | RCJ_PS_PPT - VERNA | Name of responsible person (Project manager) | ||
| 235 | RCJ_PS_PPT - VERNR | Number of responsible person (project mgr)/MRP controller | ||
| 236 | RCJ_WBSIND - PSIND | Document table index for WBS elements | ||
| 237 | RPSCO_LIS - OBJNR | Object number | ||
| 238 | SYST - TABIX | ABAP System Field: Row Index of Internal Tables |