Message Number list used by SAP ABAP Class CL_PS_MILESTONE (Class for Milestone)
SAP ABAP Class
CL_PS_MILESTONE (Class for Milestone) is using
| # | Object Type | Object Name | Object Description | Note |
|---|---|---|---|---|
| 1 | CJ - 012 | Finish date must be earlier than "&" | ||
| 2 | CJ - 152 | Reconcile the milestone date with that of the WBS element | ||
| 3 | CJ - 484 | Unit & is not valid | ||
| 4 | CJ - 009 | Start date must be later than "&" | ||
| 5 | CN - 444 | Activities "predecessor" and "succesor" cannot be the same | ||
| 6 | CN - 811 | Profile & does not exist | ||
| 7 | CN - 809 | Enter a time unit, since you have entered either work or actual work | ||
| 8 | CN - 735 | & is not a workday | ||
| 9 | CN - 450 | Milestone & does not exist | ||
| 10 | CN - 441 | Milestone function indicator is not set | ||
| 11 | CN - 427 | Enter a valid workflow task | ||
| 12 | CN - 426 | Status and status change are ignored in manual activation | ||
| 13 | CN - 422 | Enter a valid standard network | ||
| 14 | CN - 411 | Enter standard network and activity | ||
| 15 | CN - 408 | Enter status for triggering function | ||
| 16 | CN - 407 | Invalid status. Check entry | ||
| 17 | CN - 405 | Enter either absolute or percentual interval | ||
| 18 | CN - 405 | Enter either absolute or percentual interval | ||
| 19 | CN - 404 | Enter date and time | ||
| 20 | CN - 403 | Enter unit | ||
| 21 | CN - 403 | Enter unit | ||
| 22 | CN - 401 | Maintain fixed date only or reference to activity | ||
| 23 | CN - 401 | Maintain fixed date only or reference to activity | ||
| 24 | CN - 409 | Enter status change for triggering function | ||
| 25 | CO - 035 | Date & is not a working day (previous working day: &) | ||
| 26 | CO - 503 | Factory calendar ID & is not defined (check entry) | ||
| 27 | CO - 051 | The order/network type & is not defined | ||
| 28 | CO - 031 | & is not a working day (next working day: &) | ||
| 29 | CO - 005 | Order type & not found (check entry) | ||
| 30 | PSB_API_MSGCL - 006 | Milestone not found | ||
| 31 | PSB_API_MSGCL - 006 | Milestone not found | ||
| 32 | PSB_API_MSGCL - 040 | Project index not found | ||
| 33 | PSB_API_MSGCL - 072 | Invalid keys | ||
| 34 | PSB_API_MSGCL - 084 | Invalid milestone usage | ||
| 35 | PSB_API_MSGCL - 110 | &1 date not in the factory calendar (future) | ||
| 36 | PSB_API_MSGCL - 111 | &1 date not in the factory calendar (past) | ||
| 37 | PSB_API_MSGCL - 112 | &1 date is incorrect; check entry | ||
| 38 | RU - 209 | Actual date(s) is in the future (check parameters) |