SAP ABAP Message Class PLM_SE_PRS_MESSAGES (Message class for PS services)
Basic Data
Hierarchy
SAP_APPL (Software Component) Logistics and Accounting
   PS (Application Component) Project System
     PLM_SE_PRS_XI_PROXY (Package) Proxy implementations for Project System
Attributes
Message class PLM_SE_PRS_MESSAGES
Short Description Message class for PS services  
Changed On 20100310 
Last Changed At 182855 
Messages
# Message Message Short Text Documentation status Authorization check
1 000 ChangeStateID could not be determined. The short text describes the object sufficiently
2 001 No update possible, data has been changed since last read The short text describes the object sufficiently
3 002 Mandatory field &1 not provided. The short text describes the object sufficiently
4 003 Field &1 not found in table &2. The short text describes the object sufficiently
5 004 Value &1 not found in table &2. The short text describes the object sufficiently
6 005 &1 party ID is missing. The short text describes the object sufficiently
7 006 The partner with ID &1 and role code &2 could not be read. The short text describes the object sufficiently
8 007 Invalid action code for party. The short text describes the object sufficiently
9 008 The required network ID is missing. The short text describes the object sufficiently
10 009 Provide only one ID as network parent! The short text describes the object sufficiently
11 010 Exactly one of ID or SenderTechnicalID has to be provided for activity &1 The short text describes the object sufficiently
12 011 The unit of measure for Free/Total Float Duration must be DAY! The short text describes the object sufficiently
13 012 The content of &1 exceeds the field length of the target field. The short text describes the object sufficiently
14 013 Invalid domain value: &1 in &2. The short text describes the object sufficiently
15 014 Exactly one duration unit allowed. The short text describes the object sufficiently
16 015 The partner &1 already exists. The short text describes the object sufficiently
17 016 The partner &1 is not assigned to this project. The short text describes the object sufficiently
18 017 WBS &1 already exists. The short text describes the object sufficiently
19 018 WBS &1 does not exist. The short text describes the object sufficiently
20 019 Milestone &1 already exists. The short text describes the object sufficiently
21 020 Milestone &1 does not exist. The short text describes the object sufficiently
22 021 Network &1 already exists. The short text describes the object sufficiently
23 022 Network &1 does not exist. The short text describes the object sufficiently
24 023 Only Customer/Vendor code values are permitted for Product Recipient. The short text describes the object sufficiently
25 024 For action &1 the mandatory fields are missing. The short text describes the object sufficiently
26 025 Activity &1 already exists. The short text describes the object sufficiently
27 026 Activity &1 does not exist. The short text describes the object sufficiently
28 027 No InternalID-TechnicalID correspondence found. The short text describes the object sufficiently
29 028 Material component already assigned to the activity. The short text describes the object sufficiently
30 029 Not assigned material component. The short text describes the object sufficiently
31 030 Relationship already exists. The short text describes the object sufficiently
32 031 Nonexistent relationship. The short text describes the object sufficiently
33 032 Enter either SuccessorNetworkID or SuccessorNetworkSenderTechnicalID. The short text describes the object sufficiently
34 033 Invalid value &1 for &2. The short text describes the object sufficiently
35 034 NetworkRelationship: Predecessor network must be the parent network. The short text describes the object sufficiently
36 035 NetworkRelationship: Predecessor activity must be the parent activity. The short text describes the object sufficiently
37 036 The action on milestone &1 could not be performed. The short text describes the object sufficiently
38 037 Exactly-once request cannot be locked: &1 (error code: &2). The short text describes the object sufficiently
39 038 Exactly-once request timed out (message UUID &1). The short text describes the object sufficiently
40 039 Internal error in exactly-once processing (message UUID &1). The short text describes the object sufficiently
41 040 UUID &1 for element &2 does not comply to required pattern. The short text describes the object sufficiently
42 041 Internal error storing response for request message UUID &1. The short text describes the object sufficiently
43 042 Error in creating the network relationship. The short text describes the object sufficiently
44 043 Error in changing the network relationship. The short text describes the object sufficiently
45 044 Error in deleting the network relationship. The short text describes the object sufficiently
46 045 Progress of WBS element &1 could be determined The short text describes the object sufficiently
47 046 Enter Completion Percent below 100. The short text describes the object sufficiently
48 047 Project Definition &1 could be changed successfully The short text describes the object sufficiently
49 048 Project Definition &1 changed successfully. The short text describes the object sufficiently
50 049 Progress of WBS element &1 could not be determined The short text describes the object sufficiently
51 050 ISO code of system language could not be determined. The short text describes the object sufficiently
52 051 Object number of project &1 could not be determined. The short text describes the object sufficiently
53 052 Object number of wbs element &1 could not be determined. The short text describes the object sufficiently
54 053 Object number of network &1 could not be determined. The short text describes the object sufficiently
55 054 Object number of activity &1 &2 could not be determined. The short text describes the object sufficiently
56 055 Object number of material component &1 could not be determined. The short text describes the object sufficiently
57 056 Name for &1 &2 could not be determined. The short text describes the object sufficiently
58 057 Field &1 is required. The short text describes the object sufficiently
59 058 External unit of measurement &1 is not unique for language &2. The short text describes the object sufficiently
60 059 Unit of measurement ISO code &1 is not supported. The short text describes the object sufficiently
61 060 &1 conversion failed: No external code exists for internal code &2. The short text describes the object sufficiently
62 061 Entry &1 in &2 does not exist in table &3. The short text describes the object sufficiently
63 062 Value &1 in &2 is larger than &3. The short text describes the object sufficiently
64 063 &1 has to be the same as &2. The short text describes the object sufficiently
65 064 Individual measure units have to be the same as &1. The short text describes the object sufficiently
66 065 Only customer and vendor are accepted in &1. The short text describes the object sufficiently
67 066 Project &1 does not exist. The short text describes the object sufficiently
68 067 &1 should be provided using unit &2. The short text describes the object sufficiently
69 068 Creating the partner failed. The short text describes the object sufficiently
70 069 There is a loop in the network hierarchy. The short text describes the object sufficiently
71 070 &1 has to uniquely identify a WBS element. The short text describes the object sufficiently
72 071 &1 has to uniquely identify a network. The short text describes the object sufficiently
73 072 &1 has to uniquely identify an activity in a given network. The short text describes the object sufficiently
74 073 Parent WBS element has to be the same for a network and its subnetworks. The short text describes the object sufficiently
75 074 Parent WBS element has to be the same for an acty and its parent ntwk. The short text describes the object sufficiently
76 075 Activity hierarchy can be at most one level deep. The short text describes the object sufficiently
77 076 Parent WBS element has to be the same for an acty and its acty element. The short text describes the object sufficiently
78 077 Parent network has to be the same for an acty and its acty element. The short text describes the object sufficiently
79 078 &1 The short text describes the object sufficiently
80 079 &1 has to be between &2 and &3. The short text describes the object sufficiently
81 080 Project ID &1 may not be used. The short text describes the object sufficiently
82 081 WBS element ID &1 may not be used. The short text describes the object sufficiently
83 082 Acty elements cannot have ntwk relations or milestones. The short text describes the object sufficiently
84 083 A network cannot be its own parent. The short text describes the object sufficiently
85 084 The ID of an acty elmnt must be different from the ID of its parent acty. The short text describes the object sufficiently
86 085 Insufficient authorization on milestone &1 The short text describes the object sufficiently
87 086 For action &1 the mandatory fields &2 or &3 are missing. The short text describes the object sufficiently
88 087 Insufficient authorization to create milestone The short text describes the object sufficiently
89 088 System status &2 is active (WBS &1), Milestone cannot be &3 The short text describes the object sufficiently
90 146 Progress of Activity &1 could be determined The short text describes the object sufficiently
91 149 Progress of Activity &1 could not be determined The short text describes the object sufficiently
History
Last changed on/by 20100310  SAP 
SAP Release Created in   605