SAP ABAP Data Element SA_DAT04 (Start date for production)
Hierarchy
BBPCRM (Software Component) BBPCRM
   PP-REM (Application Component) Repetitive Manufacturing
     MD04 (Package) Repetitive Manufacturing
Basic Data
Data Element SA_DAT04
Short Description Start date for production  
Data Type
Category of Dictionary Type D   Domain
Type of Object Referenced     No Information
Domain / Name of Reference Type DATUM    
Data Type DATS   Date field (YYYYMMDD) stored as char(8) 
Length 8    
Decimal Places 0    
Output Length 10    
Value Table      
Further Characteristics
Search Help: Name    
Search Help: Parameters    
Parameter ID   
Default Component name    
Change document    
No Input History    
Basic direction is set to LTR    
No BIDI Filtering    
Field Label
  Length  Field Label  
Short 10 Prod.start 
Medium 15 Prod.start date 
Long 20 Product.start date 
Heading 10 Prod.start 
Documentation

Definition

Date on which the planning operation should start. The planning operation is the operation in the routing where the scheduling work center is used.

If a setup time exists before processing, the start date corresponds to the time when the setup starts.

There are two options for calculating the date:

  • Using lead time scheduling
  • By entering the date manually in the planned order in the planning table

Dependencies

If you change this date, the system carries out forward scheduling starting from the new date.

If you change both the start and the finish date, the system carries out backward scheduling starting from the new finish date.