SAP ABAP Data Element PS_NTER (Indicator: WBS dates are not current)
Hierarchy
☛
SAP_APPL (Software Component) Logistics and Accounting
⤷
PS-DAT (Application Component) Dates
⤷
CN_PSP_TRM (Package) Project Structure Plan Dates
⤷
⤷
Basic Data
| Data Element | PS_NTER |
| Short Description | Indicator: WBS dates are not current |
Data Type
| Category of Dictionary Type | D | Domain |
| Type of Object Referenced | No Information | |
| Domain / Name of Reference Type | SELKZ | |
| Data Type | CHAR | Character String |
| Length | 1 | |
| Decimal Places | 0 | |
| Output Length | 1 | |
| Value Table |
Further Characteristics
| Search Help: Name | ||
| Search Help: Parameters | ||
| Parameter ID | ||
| Default Component name | ||
| Change document | ||
| No Input History | ||
| Basic direction is set to LTR | ||
| No BIDI Filtering |
Field Label
| Length | Field Label | |
| Short | 8 | To schd. |
| Medium | 14 | To schedule |
| Long | 20 | Dates not current |
| Heading | 2 | Sd |
Documentation
Use
This indicator tells you that the scheduled dates for the WBS elements are now longer current, because:
- the activities dates for the WBS element have changed
- the network was rescheduled
To update the WBS element dates, carry out WBS scheduling.
History
| Last changed by/on | SAP | 19990105 |
| SAP Release Created in |