SAP ABAP Data Element PS_NTER (Indicator: WBS dates are not current)
Hierarchy
☛ SAP_APPL (Software Component) Logistics and Accounting
   ⤷ PS-DAT (Application Component) Dates
     ⤷ CN_PSP_TRM (Package) Project Structure Plan Dates
Basic Data
Data Element PS_NTER
Short Description Indicator: WBS dates are not current  
Data Type
Category of Dictionary Type D   Domain
Type of Object Referenced     No Information
Domain / Name of Reference Type SELKZ    
Data Type CHAR   Character String 
Length 1    
Decimal Places 0    
Output Length 1    
Value Table      
Further Characteristics
Search Help: Name    
Search Help: Parameters    
Parameter ID   
Default Component name    
Change document    
No Input History    
Basic direction is set to LTR    
No BIDI Filtering    
Field Label
  Length  Field Label  
Short 8 To schd. 
Medium 14 To schedule 
Long 20 Dates not current 
Heading 2 Sd 
Documentation

Use

This indicator tells you that the scheduled dates for the WBS elements are now longer current, because:

  • the activities dates for the WBS element have changed
  • the network was rescheduled

To update the WBS element dates, carry out WBS scheduling.