SAP ABAP Data Element PK_REUSEST (Reuse Strategy for Planned Orders)
Hierarchy
BBPCRM (Software Component) BBPCRM
   CRM (Application Component) Customer Relationship Management
     CRM_APPLICATION (Package) All CRM Components Without Special Structure Packages
       MD05 (Package) Development class KANBAN
Basic Data
Data Element PK_REUSEST
Short Description Reuse Strategy for Planned Orders  
Data Type
Category of Dictionary Type D   Domain
Type of Object Referenced     No Information
Domain / Name of Reference Type PK_REUSEST    
Data Type CHAR   Character String 
Length 1    
Decimal Places 0    
Output Length 1    
Value Table      
Further Characteristics
Search Help: Name    
Search Help: Parameters    
Parameter ID   
Default Component name    
Change document    
No Input History    
Basic direction is set to LTR    
No BIDI Filtering    
Field Label
  Length  Field Label  
Short 10 PrPl. Use 
Medium 15 Prodn Plan Use 
Long 30 Use of Production Plan 
Heading 36 Use of Production Plan for Kanban 
Documentation

Definition

Use of MRP planned orders for Kanban.

Use

Through this setting, you can specify that planned orders generated in the MRP run are to be used in Kanban. This makes sense, for example, if you have already specified the sequence of your planned orders using the sequencing functionality and do not want a new planned order to be scheduled within this sequence.

Instead of creating a new planned order, the system will attempt to use a planned order created by MRP when a kanban container is set to empty. With this setting, you specify the preconditions under which the planned orders are taken into account in this process.

You have the following options:

  • No planned orders are used. Instead, a new planned order is generated when a kanban is set to empty.
  • Only planned orders that have the same production version as that of the control cycle are used.
  • Both planned orders that have the same production version as that of the control cycle and planned orders without a production version are used.
  • All planned orders with or without a production version are taken into account.

In order that a planned order generated by MRP can be assigned to a kanban container, however, irrespective of this setting, the lot size of the planned order must match up with the kanban quantity. If this is not the case, a new planned order is generated when the kanban is set to empty.

Dependencies

You have chosen an in-house-production strategy with the control type Processing with Planned Orders and Cost Collector or Processing with Planned Orders/Preplanning with MRP.

Example

History
Last changed by/on SAP  20100310 
SAP Release Created in 700