SAP ABAP Data Element MLST_ACTDT (Actual date (Milestone met))
Hierarchy
SAP_APPL (Software Component) Logistics and Accounting
   PS-ST-OPR-NET (Application Component) Network and Activity
     CN_NET_OPR (Package) Operative Network
Basic Data
Data Element MLST_ACTDT
Short Description Actual date (Milestone met)  
Data Type
Category of Dictionary Type D   Domain
Type of Object Referenced     No Information
Domain / Name of Reference Type DATUM    
Data Type DATS   Date field (YYYYMMDD) stored as char(8) 
Length 8    
Decimal Places 0    
Output Length 10    
Value Table      
Further Characteristics
Search Help: Name    
Search Help: Parameters    
Parameter ID   
Default Component name ACTUAL_DATE   
Change document    
No Input History    
Basic direction is set to LTR    
No BIDI Filtering    
Field Label
  Length  Field Label  
Short 10 Actual 
Medium 15 Actual date 
Long 20 Actual date 
Heading 10 Actl. date 
Documentation

Definition

Date on which the percentage of completion was reached for the milestone.

The actual date is used to determine the actual percentage of completion when you use the milestone technique in earned value analysis.

Supplementary Documentation - MLST_ACTDT2850

Use

The actual date is calculated together with the percentage of completion for the activity. The actual date can be either:

  • entered manually or
  • copied from the activity confirmation, if the percentage of completion is less than or equal to the degree of completion in the confirmation.

Dependencies

You must have entered a percentage of completion in the milestone to be able to copy the date from the confirmation.

History
Last changed by/on SAP  19981109 
SAP Release Created in