Used only in connection with multiple reading of wattregisters. If the indicator is set, the multiple-read results refer only to the corresponding allocation month of the meter reading and not to the entire billing period.
Example
Multiple readings were carried out on the last day of each of the 12 months. The device was replaced in February; therefore, two meter reading results exist for this month. If the indicator is set, each meter reading result is only valid in its allocation month. For example, both of the results in February are valid in February only, so that the higher of the two demands in February remains. Twelve demand values are billed, and this results in twelve billing line items. If the indicator had not been set, the highest of the 13 demands for the entire billing period would remain, and this would have resulted in a single billing line item.