Hierarchy
⤷ CO-PC-IS (Application Component) Product Cost Controlling Information System
⤷ KKB (Package) Reporting for Costing
Basic Data
Data Element | KKB_SOLLBEL_G |
Short Description | Target Cost Debit |
Data Type
Category of Dictionary Type | D | Domain |
Type of Object Referenced | No Information | |
Domain / Name of Reference Type | WERTV8 | |
Data Type | CURR | Currency field, stored as DEC |
Length | 15 | |
Decimal Places | 2 | |
Output Length | 21 | |
Value Table |
Further Characteristics
Search Help: Name | ||
Search Help: Parameters | ||
Parameter ID | ||
Default Component name | ||
Change document | ||
No Input History | ||
Basic direction is set to LTR | ||
No BIDI Filtering |
Field Label
Length | Field Label | |
Short | 10 | Target deb |
Medium | 15 | Target cost |
Long | 20 | Target cost debit |
Heading | 15 | Target debit |
Documentation
Definition
Total of the target cost debit.
Use
Target costs are the planned costs adjusted to the actual operating rate.
The target debit of a manufacturing order is the sum of the activity-independent planned debit of the order and the activity-dependent planned debit of the order multiplied by the confirmed quantity of the order.
The target credit of a manufacturing order results from goods receipts to stock. The delivered confirmed quantity is valuated with the planned price in accordance with the defined price control.
The target costs are calculated in variance calculation and updated to the database. The target costs cannot be reported until you have calculated the variances for that target cost version.
For the calculation of variances, the target costs are compared with the control costs.
Dependencies
The calculation of target costs depends on the selected target cost version.
History
Last changed by/on | SAP | 20000211 |
SAP Release Created in |