SAP ABAP Data Element KKB_SOLLBEL_G (Target Cost Debit)
Hierarchy
SAP_FIN (Software Component) SAP_FIN
   CO-PC-IS (Application Component) Product Cost Controlling Information System
     KKB (Package) Reporting for Costing
Basic Data
Data Element KKB_SOLLBEL_G
Short Description Target Cost Debit  
Data Type
Category of Dictionary Type D   Domain
Type of Object Referenced     No Information
Domain / Name of Reference Type WERTV8    
Data Type CURR   Currency field, stored as DEC 
Length 15    
Decimal Places 2    
Output Length 21    
Value Table      
Further Characteristics
Search Help: Name    
Search Help: Parameters    
Parameter ID   
Default Component name    
Change document    
No Input History    
Basic direction is set to LTR    
No BIDI Filtering    
Field Label
  Length  Field Label  
Short 10 Target deb 
Medium 15 Target cost 
Long 20 Target cost debit 
Heading 15 Target debit 
Documentation

Definition

Total of the target cost debit.

Use

Target costs are the planned costs adjusted to the actual operating rate.

The target debit of a manufacturing order is the sum of the activity-independent planned debit of the order and the activity-dependent planned debit of the order multiplied by the confirmed quantity of the order.

The target credit of a manufacturing order results from goods receipts to stock. The delivered confirmed quantity is valuated with the planned price in accordance with the defined price control.

The target costs are calculated in variance calculation and updated to the database. The target costs cannot be reported until you have calculated the variances for that target cost version.

For the calculation of variances, the target costs are compared with the control costs.

Dependencies

The calculation of target costs depends on the selected target cost version.

History
Last changed by/on SAP  20000211 
SAP Release Created in