Hierarchy
⤷ CO-PC-IS (Application Component) Product Cost Controlling Information System
⤷ KKB (Package) Reporting for Costing
Basic Data
Data Element | KKB_KONTBEL_G |
Short Description | Control Cost Debit |
Data Type
Category of Dictionary Type | D | Domain |
Type of Object Referenced | No Information | |
Domain / Name of Reference Type | WERTV8 | |
Data Type | CURR | Currency field, stored as DEC |
Length | 15 | |
Decimal Places | 2 | |
Output Length | 21 | |
Value Table |
Further Characteristics
Search Help: Name | ||
Search Help: Parameters | ||
Parameter ID | ||
Default Component name | ||
Change document | ||
No Input History | ||
Basic direction is set to LTR | ||
No BIDI Filtering |
Field Label
Length | Field Label | |
Short | 10 | Ctrl costs |
Medium | 16 | Control costs |
Long | 24 | Control cost debit |
Heading | 24 | Control cost debit |
Documentation
Definition
Amount of the control cost debit.
Use
The control costs are compared with the target costs in variance calculation.
Prerequisites
You must calculate the work in process before you calculate the variances.
Dependencies
The system calculates the control costs automatically when it calculates the variances.
The control costs are calculated in different ways depending on the variances to be calculated.
For the total variances and production variances the control costs are the actual costs less the work in process and scrap. For the planning variances the control costs are calculated based on the preliminary cost estimate for the order. For total variances and production variances the reference quantity is the confirmed quantity delivered to stock. For planning variances the the reference quantity is the planned order quantity.
Deducting the work in process and the scrap from the actual costs ensures that only true variances are calculated.