SAP ABAP Data Element EVTIM (Time-Based Progress Calculation)
Hierarchy
☛
BBPCRM (Software Component) BBPCRM
⤷
CRM (Application Component) Customer Relationship Management
⤷
CRM_APPLICATION (Package) All CRM Components Without Special Structure Packages
⤷
CNEV (Package) R/3 application development PS earned value analysis
⤷
⤷
⤷
Basic Data
| Data Element | EVTIM |
| Short Description | Time-Based Progress Calculation |
Data Type
| Category of Dictionary Type | D | Domain |
| Type of Object Referenced | No Information | |
| Domain / Name of Reference Type | XFELD | |
| Data Type | CHAR | Character String |
| Length | 1 | |
| Decimal Places | 0 | |
| Output Length | 1 | |
| Value Table |
Further Characteristics
| Search Help: Name | ||
| Search Help: Parameters | ||
| Parameter ID | ||
| Default Component name | ||
| Change document | ||
| No Input History | ||
| Basic direction is set to LTR | ||
| No BIDI Filtering |
Field Label
| Length | Field Label | |
| Short | 10 | Time-Based |
| Medium | 15 | Time.Bsd PrgClc |
| Long | 20 | Time-Based Prog.Clc |
| Heading | 1 | T |
Documentation
Definition
The earned value is calculated by applying the percentage of completion (POC) to a cost amount. The POC can be applied in two ways:
- Multiplication
In this case the POC is simply multiplied by the cost amount.
Example:
Plan period 1: 20H $200
Plan period 2: 30H $330
POC: 60%
Earned value: $530 * 60% = $318
- Time phased
In this case, the earned value is calculated by first applying the POC to the quantity and then using the corresponding costs.
Example:
Plan period 1: 20H $200
Plan period 2: 30H $330
POC: 60%
Earned value: 50H * 60% = 30H
Period 1: 20H / 20H * $200 = $200
Period 2: 10H / 30H * $330 = $110
Total: $310