SAP ABAP Data Element BP_TI_GES1 (Maintain overall values)
Hierarchy
BBPCRM (Software Component) BBPCRM
   CA-GTF-BS (Application Component) Business Application Support
     KABP (Package) Cost Accounting budget and planning
Basic Data
Data Element BP_TI_GES1
Short Description Maintain overall values  
Data Type
Category of Dictionary Type D   Domain
Type of Object Referenced     No Information
Domain / Name of Reference Type X    
Data Type CHAR   Character String 
Length 1    
Decimal Places 0    
Output Length 1    
Value Table      
Further Characteristics
Search Help: Name    
Search Help: Parameters    
Parameter ID   
Default Component name    
Change document    
No Input History    
Basic direction is set to LTR    
No BIDI Filtering    
Field Label
  Length  Field Label  
Short 10 Total 
Medium 15 Total values 
Long 20 Total values 
Heading 15 Total values 
Documentation

Definition

Indicator which controls whether overall values are totaled up.

Dependencies

In project cost planning, the following plan values are totaled up in WBS elements:

  • Structure plan values in WBS elements
  • Cost element plan values in WBS elements
  • Unit costing values in WBS elements
  • Structure plan values for the level directly below
  • These structure plan values arise from the total for structure plan values, cost element plan values, and unit costings in the subordinate WBS elements.

Example

The third level in a WBS has two WBS elements with the following plan values:

Plan value    WBS elem.1    WBS elem.2    Total

Structure    $10,000    $15,000        $25,000

Cost elements    $5,000    $5,000        $10,000

Unit costing    $7,500    $7,500        $15,000

                        -------

                        $50,000

This total of $50,000 overwrites the structure plan value in the WBS element directly above on the second level.

History
Last changed by/on SAP  20010720 
SAP Release Created in