Hierarchy
⤷ CRM (Application Component) Customer Relationship Management
⤷ CRM_APPLICATION (Package) All CRM Components Without Special Structure Packages
⤷ CNPC (Package) R/3 Customizing PP Project Management
IMG Activity
ID | SIMG_OLPR_OP4A | Define Shift Sequences |
Transaction Code | S_ALR_87004920 | IMG Activity: SIMG_OLPR_OP4A |
Created on | 19981222 | |
Customizing Attributes | SIMG_OLPR_OP4A | Define shift sequence |
Customizing Activity | SIMG_OLPR_OP4A | Define Shift Sequences |
Document
Document Class | SIMG | Hypertext: Object Class - Class to which a document belongs. |
Document Name | SIMG_OLPR_OP4A |
In this step you define the following:
- Grouping
Using the grouping you can create shift sequences and shift definitions for special areas (for example, different plants or different areas of a plant) and when maintaining the available capacity choose from between work centers.
- Work break schedule
Here you define parameters that describe the individual work break schedules in more detail, as for example:
- Start
- Finish
- Break times
- Shift definition
Here you define the parameters common to several work centers that describe the individual shifts in more detail, for example:
- Start
- Finish
- Break times
- Validity period of a shift
In Logistics (LO) you can reference daily work schedules from the personnel system (HR). If you reference a daily work schedule in LO from HR and this is changed in HR then this change has a direct effect on changes in LO.
- Shift sequences
You can assign the shift sequence of a capacity category as the available capacity at the work center.
You define a sequence of shifts per weekday. The shift sequence represents a collection of shift definitions.
In capacity planning the system uses the predefined values from the shift definition to determine the available capacity of a work center.
The system calculates the following values:
- the capacity
- the actual operating time for the capacity
Standard settings
The SAP standard package contains settings for various shift sequences.
Activities
You should define the following:
- groupings
- shift sequences
- shift definitions
- work break schedules
Business Attributes
ASAP Roadmap ID | 204 | Establish Functions and Processes |
Mandatory / Optional | 1 | Mandatory activity |
Critical / Non-Critical | 2 | Non-critical |
Country-Dependency | A | Valid for all countries |
Assigned Application Components
Documentation Object Class | Documentation Object Name | Current line number | Application Component | Application Component Name |
---|---|---|---|---|
SIMG | SIMG_OLPR_OP4A | 0 | HLA0006683 A HLA0006678 |
Maintenance Objects
Maintenance object type | C | Customizing Object |
Assigned objects | ||||||
---|---|---|---|---|---|---|
Customizing Object | Object Type | Transaction Code | Sub-object | Do not Summarize | Skip Subset Dialog Box | Description for multiple selections |
VC0C06 | C - View cluster | OP4A | OLPR | Shift Sequences/Shift Definitions/Breaks from PP View |
History
Last changed by/on | SAP | 19981222 |
SAP Release Created in |