Hierarchy
⤷
⤷
⤷
IMG Activity
| ID | PPPI_MD_3332 | Define Shift Sequence |
| Transaction Code | S_ALR_87006202 | IMG Activity: PPPI_MD_3332 |
| Created on | 19981222 | |
| Customizing Attributes | PPPI_MD_3332 | Define shift sequence |
| Customizing Activity | PPPI_MD_3332 | Define shift sequence |
Document
| Document Class | SIMG | Hypertext: Object Class - Class to which a document belongs. |
| Document Name | PPPI_MD_3332 |
In this step you define the following:
- Grouping
Here you can create shift sequences and shift definitions for special areas (for example, different plants or different areas of a plant) and choose between resources when maintaining available capacity.
- Work break schedule
Here you define the parameters that describe the individual work break schedules in more detail, for example:
- Start
- Finish
- Break times
- Shift definition
Here you define the parameters common to several resources that describe the individual shifts in more detail, for example:
- Start
- Finish
- Break times
- Validity period of a shift
The shift definition serves, depending on the resource type, the following purposes:
- For resources at which a manufacturing process takes place, you use the shift definition to define a time-dependent available capacity.
- For purely storage resources, you use the shift definition to determine time periods in which a volume-dependent or quantity-dependent available capacity changes.
In Logistics (LO) you can reference daily work schedules from the personnel system (HR). If you reference a daily work schedule in LO from HR and this is changed in HR, then this change will also directly affect the application in LO.
- Shift sequences
You can assign the shift sequence of a capacity category as available capacity at the resource.
You define a sequence of shifts per weekday. The shift sequence shows a summary of the shift definitions.
In capacity planning the system uses the predefined values from the shift definition to determine the available capacity of a resource.
The system calculates the following values:
- the capacity
- the actual operating time for the capacity
Standard settings
The standard system contains settings for various shift sequences.
Activities
Define
- Grouping
- Work break schedules
- Shift definitions
- Shift sequences
Business Attributes
| ASAP Roadmap ID | 203 | Establish Master Data |
| Mandatory / Optional | 2 | Optional activity |
| Critical / Non-Critical | 2 | Non-critical |
| Country-Dependency | A | Valid for all countries |
Assigned Application Components
| Documentation Object Class | Documentation Object Name | Current line number | Application Component | Application Component Name |
|---|---|---|---|---|
| SIMG | PPPI_MD_3332 | 0 | HLA0006270 | Resources |
Maintenance Objects
| Maintenance object type | C | Customizing Object |
| Assigned objects | ||||||
|---|---|---|---|---|---|---|
| Customizing Object | Object Type | Transaction Code | Sub-object | Do not Summarize | Skip Subset Dialog Box | Description for multiple selections |
| VC0C06 | C - View cluster | OP4A | PPPI_MD | Shift sequences/shift definitions/breaks from PP view |
History
| Last changed by/on | SAP | 19981222 |
| SAP Release Created in |