Table/Structure Field list used by SAP ABAP Program LCJTRF84 (INSERT_ACT_DATE)
SAP ABAP Program
LCJTRF84 (INSERT_ACT_DATE) is using
| # | Object Type | Object Name | Object Description | Note |
|---|---|---|---|---|
| 1 | AFVGD - APLZL | General counter for order | ||
| 2 | AFVGD - ARBID | Object ID of the resource | ||
| 3 | AFVGD - AUFNRD | Order Number | ||
| 4 | AFVGD - AUFPL | Routing number of operations in the order | ||
| 5 | AFVGD - DAUNE | Normal duration/unit | ||
| 6 | AFVGD - DAUNO | Normal duration of the activity | ||
| 7 | AFVGD - EWDAN | Normal duration (from forecast) of activity | ||
| 8 | AFVGD - EWDNE | Unit for forecast normal duration | ||
| 9 | AFVGD - FPAVD | Earliest scheduled start date (forecast) | ||
| 10 | AFVGD - FPAVZ | Earliest scheduled start time (forecast) | ||
| 11 | AFVGD - FPEDD | Earliest scheduled finish date (forecast) | ||
| 12 | AFVGD - FPEDZ | Earliest scheduled finish time (forecast) | ||
| 13 | AFVGD - FSAVD | Earliest scheduled start: Execution (date) | ||
| 14 | AFVGD - FSAVZ | Earliest scheduled start: Execution (time) | ||
| 15 | AFVGD - FSEDD | Earliest scheduled finish: Execution (date) | ||
| 16 | AFVGD - FSEDZ | Earliest scheduled finish: Execution (time) | ||
| 17 | AFVGD - IEBD | Actual finish: Processing (date) | ||
| 18 | AFVGD - KALID | Factory Calendar | ||
| 19 | AFVGD - PLIFZ | Planned delivery time in days | ||
| 20 | AFVGD - SPAVD | Latest scheduled start date (forecast) | ||
| 21 | AFVGD - SPAVZ | Latest scheduled start time (forecast) | ||
| 22 | AFVGD - SPEDD | Latest scheduled finish date (forecast) | ||
| 23 | AFVGD - SPEDZ | Latest scheduled finish time (forecast) | ||
| 24 | AFVGD - SSAVD | Latest scheduled start: Execution (date) | ||
| 25 | AFVGD - SSAVZ | Latest scheduled start: Execution (time) | ||
| 26 | AFVGD - SSEDD | Latest scheduled finish: Execution (date) | ||
| 27 | AFVGD - SSEDZ | Latest scheduled finish: Execution (time) | ||
| 28 | AFVGD - STEUS | Control key | ||
| 29 | AFVGD - VORNR | Operation/Activity Number | ||
| 30 | AFVGI - ARBID | Object ID of the resource | ||
| 31 | AFVGI - KALID | Factory Calendar | ||
| 32 | AFVGI - STEUS | Control key | ||
| 33 | AFVGI - VORNR | Operation/Activity Number | ||
| 34 | AFVKI - APLZL | General counter for order | ||
| 35 | AFVKI - AUFPL | Routing number of operations in the order | ||
| 36 | AFVVI - DAUNE | Normal duration/unit | ||
| 37 | AFVVI - DAUNO | Normal duration of the activity | ||
| 38 | AFVVI - EWDAN | Normal duration (from forecast) of activity | ||
| 39 | AFVVI - EWDNE | Unit for forecast normal duration | ||
| 40 | AFVVI - FPAVD | Earliest scheduled start date (forecast) | ||
| 41 | AFVVI - FPAVZ | Earliest scheduled start time (forecast) | ||
| 42 | AFVVI - FPEDD | Earliest scheduled finish date (forecast) | ||
| 43 | AFVVI - FPEDZ | Earliest scheduled finish time (forecast) | ||
| 44 | AFVVI - FSAVD | Earliest scheduled start: Execution (date) | ||
| 45 | AFVVI - FSAVZ | Earliest scheduled start: Execution (time) | ||
| 46 | AFVVI - FSEDD | Earliest scheduled finish: Execution (date) | ||
| 47 | AFVVI - FSEDZ | Earliest scheduled finish: Execution (time) | ||
| 48 | AFVVI - IEBD | Actual finish: Processing (date) | ||
| 49 | AFVVI - PLIFZ | Planned delivery time in days | ||
| 50 | AFVVI - SPAVD | Latest scheduled start date (forecast) | ||
| 51 | AFVVI - SPAVZ | Latest scheduled start time (forecast) | ||
| 52 | AFVVI - SPEDD | Latest scheduled finish date (forecast) | ||
| 53 | AFVVI - SPEDZ | Latest scheduled finish time (forecast) | ||
| 54 | AFVVI - SSAVD | Latest scheduled start: Execution (date) | ||
| 55 | AFVVI - SSAVZ | Latest scheduled start: Execution (time) | ||
| 56 | AFVVI - SSEDD | Latest scheduled finish: Execution (date) | ||
| 57 | AFVVI - SSEDZ | Latest scheduled finish: Execution (time) | ||
| 58 | CAUFVD - PLART | Basis for scheduling | ||
| 59 | CAUFVD - WERKS | Plant | ||
| 60 | CAUFVTAB - PLART | Basis for scheduling | ||
| 61 | CAUFVTAB - WERKS | Plant | ||
| 62 | COAUTHINF - CHANGE | Ind.: Authorization exists | ||
| 63 | COOPRINF - AUFNRD | Order Number | ||
| 64 | OPRAUTH - CHANGE | Ind.: Authorization exists | ||
| 65 | PROJ - VGPLF | Planning method for project basic dates | ||
| 66 | PROJ2_INC - VGPLF | Planning method for project basic dates | ||
| 67 | PROJ_INC - VGPLF | Planning method for project basic dates | ||
| 68 | PRPS - FABKL | Factory calendar key | ||
| 69 | PRPS - PSPNR | WBS Element | ||
| 70 | PRPS2_INC - FABKL | Factory calendar key | ||
| 71 | PRPS_INC - FABKL | Factory calendar key | ||
| 72 | PRTE - EDAUR | Forecasted length (duration) of the WBS element | ||
| 73 | PRTE - EEINH | Unit for duration of WBS element planned dates | ||
| 74 | PRTE - EENDE | Forecasted finish date of the WBS element | ||
| 75 | PRTE - ESTRT | Forecasted start date of the WBS element | ||
| 76 | PRTE - FLGEM | Indicator: Forecast dates set manually | ||
| 77 | PRTEB - CHNGE | (Change) action allowed | ||
| 78 | PRTEB - EDAUR | Forecasted length (duration) of the WBS element | ||
| 79 | PRTEB - EEINH | Unit for duration of WBS element planned dates | ||
| 80 | PRTEB - EENDE | Forecasted finish date of the WBS element | ||
| 81 | PRTEB - ESTRT | Forecasted start date of the WBS element | ||
| 82 | PRTEB - FLGEM | Indicator: Forecast dates set manually | ||
| 83 | PRTEINC - EDAUR | Forecasted length (duration) of the WBS element | ||
| 84 | PRTEINC - EEINH | Unit for the length (duration) of the WBS element | ||
| 85 | PRTEINC - EENDE | Forecasted finish date of the WBS element | ||
| 86 | PRTEINC - ESTRT | Forecasted start date of the WBS element | ||
| 87 | PRTEINC - FLGEM | Indicator: Forecast dates set manually | ||
| 88 | RCJ_ACTIND - ACIND | Doc. table index for activities | ||
| 89 | RCJ_ACTIND - NWIND | Document table index for networks | ||
| 90 | RCJ_ACTIND - PSIND | Document table index for WBS elements | ||
| 91 | RCLST - OBJECT | Data objects of a task list | ||
| 92 | RCWBS - SEL01 | Selection flag | ||
| 93 | RCWBT - ETERM | Finish date for an object (WBS element, activity ...) | ||
| 94 | RCWBT - IDENT | Work breakdown structure element (WBS element) | ||
| 95 | RCWBT - SELKZ | Selection flag | ||
| 96 | RCWBT - STERM | Start date for an object (WBS element, operation) | ||
| 97 | SYST - STEPL | ABAP System Field: Current Step Loop or Table Control Line | ||
| 98 | SYST - TABIX | ABAP System Field: Row Index of Internal Tables | ||
| 99 | SYST - UZEIT | ABAP System Field: Current Time of Application Server | ||
| 100 | T001W - FABKL | Factory calendar key | ||
| 101 | T430 - LIEF | External processing | ||
| 102 | T430 - TERM | Indicator: Scheduling | ||
| 103 | TCBP - UPDTS | Schedule every change | ||
| 104 | TJ01 - VRGNG | Business Transaction |