Message class U9  
Short Description Message Class for Output in Application Log    
Message Number 120  
Documentation status       Space: object requires documentation
Authorization check Error Message      
Changed On 20001004   
Message Text
Rerouting of relationships in the recipe was terminated
Help Document

Diagnosis

You are transferring the master recipe with the recipe group and group counter to APO. Some phases are missing (for example, phases not relevant to planning). The system has attempted to reroute the relationships of these phases to their predecessors or successors. This led to a situation that made it necessary to terminate the rerouting of these relationships.

System Response

For some of the missing phases no new relationships were generated. It cannot be guaranteed that a correct PPM will be generated in APO.

Procedure

This situation usually occurs if the relationships lead to a cycle and the phases involved are missing in the transfer to APO.

  1. Check whether the PPM was correctly created in APO.
  2. If this is not the case, remove the cycle from the recipe and retransfer the recipe.