SAP ABAP Message Class U9 Message Number 120 (Rerouting of relationships in the recipe was terminated)
Hierarchy
☛
SAP_APPL (Software Component) Logistics and Accounting
⤷ CA (Application Component) Cross-Application Components
⤷ PGSE (Package) Routing/Recipe and BOM Mapping to PPM
⤷ CA (Application Component) Cross-Application Components
⤷ PGSE (Package) Routing/Recipe and BOM Mapping to PPM
Attribute
Message class | U9 | ||
Short Description | Message Class for Output in Application Log | ||
Message Number | 120 | ||
Documentation status | Space: object requires documentation | ||
Authorization check Error Message | |||
Changed On | 20001004 |
Message Text
Rerouting of relationships in the recipe was terminated
Help Document
Diagnosis
You are transferring the master recipe with the recipe group and group counter to APO. Some phases are missing (for example, phases not relevant to planning). The system has attempted to reroute the relationships of these phases to their predecessors or successors. This led to a situation that made it necessary to terminate the rerouting of these relationships.
System Response
For some of the missing phases no new relationships were generated. It cannot be guaranteed that a correct PPM will be generated in APO.
Procedure
This situation usually occurs if the relationships lead to a cycle and the phases involved are missing in the transfer to APO.
- Check whether the PPM was correctly created in APO.
- If this is not the case, remove the cycle from the recipe and retransfer the recipe.