SAP ABAP Message Class PR Message Number 031 (Replenishment lead time is greater than 999 days, please check)
Hierarchy
☛
SAP_BASIS (Software Component) SAP Basis Component
⤷ BC-SRV-BSF (Application Component) Business Service Functions
⤷ SPRG (Package) Forecast Basis Separation
⤷ BC-SRV-BSF (Application Component) Business Service Functions
⤷ SPRG (Package) Forecast Basis Separation
Attribute
Message class | PR | ||
Short Description | Forecast: Help messages | ||
Message Number | 031 | ||
Documentation status | |||
Authorization check Error Message | |||
Changed On |
Message Text
Replenishment lead time is greater than 999 days, please check
Help Document
Diagnosis
The replenishment lead time calculated by the system exceeds 999 days.
The replenishment lead time is calculated as follows:
- for in-house production; production time plus goods receipt processing time,
- for external procurement; the sum of the planned delivery time plus processing time for purchasing plus the goods receipt processing time.
System Response
Procedure
Check the times which are recorded in the material's master record and correct them.
History
Last changed on/by | 19941123 | SAP | |
SAP Release Created in |