SAP ABAP Message Class MILL_PC Message Number 118 (Select one PB or GR row and an item of the segment. order)
Hierarchy
☛
ECC-DIMP (Software Component) DIMP
⤷
IS-MP-PP (Application Component) Production Planning and Control (PP) enhancements
⤷
MILL_PP (Package) IS: Mill Products - Production Planning and Control

⤷

⤷

Attribute
Message class | ![]() |
MILL_PC | |
Short Description | ![]() |
Mill: Message Pool for Confirmations | |
Message Number | ![]() |
118 | |
Documentation status | ![]() |
||
Authorization check Error Message | |||
Changed On | ![]() |
20050301 |
Message Text
Select one PB or GR row and an item of the segment. order
Help Document
Diagnosis
You tried to assign a segmentation order to another order item or process batch. However, you have not selected all the lines necessary for this. System Response
Procedure
If you want to create a different assignment for an item in a segmentation order, you must select the following lines:
- Reassign between order items
Select the relevant segmentation order item in the Segmentations area (screen 8475 Mill: SG screen) and the required order item in the Goods receipts area (screen 8485 Mill: GR screen). - Reassign between process batch
Select the relevant segmentation order item in the Segmentations area (screen 8475 Mill: SG screen) and the required process batch in the Process batch area (screen 8495 Mill: PB screen).
Note
You can only reassign an item of a segmentation order between two order items or two process batches.
For example, you can not assign an item of a segmentation order that is assigned to a process batch to an order item.